Once the requirement for a cable system has been identified and funds raised to build it, the first thing which happens is that a cable manufacturer and installer is contracted by the cable system parties.
A desk top study is then commissioned which identifies a route and the risks to that route.
Items for consideration would be :-
When the route has been selected and designed, then the initiation of acquisition of permits for the cable system is undertaken. This will involve engagement with Government Administrations, other seabed users and stakeholders i.e. fisheries, cable owners, pipeline owners, etc.
The purpose of the route survey is to identify a safe route for the cable. Even though the Desk Top Study has identified the potential route, the Route Survey will confirm the assumptions made. The Route Survey comprises:
Once the route survey is complete and the cable system design is finalised, manufacture of the cable is undertaken. When manufacture of the cable is complete, it is loaded to the cableship for deployment.
At the shore approaches where the cable is landed (the shore end), burial is carried out by divers in the shallow water. If the water is too shallow for the main lay vessel to approach safely, a smaller shallow drafted vessel may be lay used to lay the shore end.
Cable Laying Operations |
---|
The main lay vessel (the cableship) is used to lay the rest of the cable system. In water depths where there are risks due to fishing and other man made activities such as anchoring etc., the cable is generally buried to a target depth of approximately 1 metre.
The cable is laid to conform to the contours of the seabed to avoid cable lying in suspension. During the cable laying process, the cable is being constantly tested to ensure that no damage has occurred to it.
At the end of the cable lay, a final splice is made to join the cable ends together to make a connection between the cable stations. Final tests are then made to ensure the cable is working correctly.
Cable Laying Video |
---|
Following the cable laying operations, the cable positions will be notified to various administrations such as Hydrographic Offices, the Regulatory Administrations and other seabed users such as fisheries.
TO DOWNLOAD THIS FILE, YOU MUST AGREE TO THE TERMS AND CONDITIONS "TERMS" NOTED AT THE FOOT OF THIS WEBSITE WHICH APPLY TO YOUR USE OF THIS WEBSITE AND TO USE OF THE FILE YOU HAVE CLICKED TO DOWNLOAD. IF YOU DO NOT AGREE TO THE TERMS, YOU WILL NOT BE ABLE TO DOWNLOAD THE FILE AND YOU SHOULD NOT USE THIS WEBSITE. TO CONFIRM YOUR ACCEPTANCE OF THE TERMS AND TO COMMENCE THE DOWNLOAD OF THE FILE, PLEASE CLICK THE "DOWNLOAD" CHECK BOX. IF YOU DO NOT AGREE TO THE TERMS, PLEASE CLICK THE "CANCEL" BUTTON. YOUR ATTENTION IS DRAWN TO CONDITION 3 NOTED BELOW WHICH FORMS PART OF THE TERMS IN RELATION TO OUR LIABILITY TO YOU.