Under a Cable Maintenance Agreement and on notification from a Maintenance Authority, a cable repair ship operator will mobilise one of its vessels to conduct a repair on a subsea cable. The maintenance authority will provide an estimated position of the cable fault based on tests carried out from the cable Terminal Stations located either end of the marine cable. Permitting, Charting, and existing cable information is assessed prior to the vessel departing.
On arriving at the suspected cable fault location, the repair vessel will attempt to localise the cable fault further by using one of three different techniques:
In the event the cable being damaged but not broken, the cable will need to be cut. This is carried out from the ROV or by using a cutting grapnel. A grapnel is a device with multiple hooks (attached to the vessel by rope) and dragged along the seabed in order to cut or hook the cable. The essence of grappling is that sufficient rope be streamed to ensure the grapnel is in continuous contact with the seabed without reducing sensitivity in tension due to excessive rope. The ROV on the other hand uses one of its manipulator arms to attach a gripper to the cable which is connected to the ship via a rope or wire for recovery.
Remotely Operated Vehicle (ROV) |
---|
The first cable section recovered to deck will be sealed and buoyed off. The second cable end will then be recovered from the seabed, cleaned and prepped ready for a new section of cable to be spliced in. This operation is a delicate process and is carried out under strict health and safety and hygiene procedures. The armour wires are removed and the cable is stripped back to the individual fibres. These fibres are then spliced together with the fibres in the new cable section (the fibres are coloured or mapped to ensure the correct fibres are spliced together). On completion of all the fibres being spliced together, the cable joint is sealed, moulded and a protected casing attached. Once the first joint has taken place the vessel will lay out the new cable to the location of the earlier dispatched cable buoy, which is then recovered. Again the cable ends are prepared, the fibres spliced and the joint sealed together. The cable is rigorously tested before the vessel slowly moves away from the site and simultaneously lowers the cable to the seabed, thus avoiding the cable looping and sitting back on itself.
For maximum cable protection the cable should then be immediately reburied. Using the ROV, a high pressure water jet liquefies the seabed beneath the cable which then drops into the trench created. Cutting tools on the ROV can be used in areas of hard seabed.
TO DOWNLOAD THIS FILE, YOU MUST AGREE TO THE TERMS AND CONDITIONS "TERMS" NOTED AT THE FOOT OF THIS WEBSITE WHICH APPLY TO YOUR USE OF THIS WEBSITE AND TO USE OF THE FILE YOU HAVE CLICKED TO DOWNLOAD. IF YOU DO NOT AGREE TO THE TERMS, YOU WILL NOT BE ABLE TO DOWNLOAD THE FILE AND YOU SHOULD NOT USE THIS WEBSITE. TO CONFIRM YOUR ACCEPTANCE OF THE TERMS AND TO COMMENCE THE DOWNLOAD OF THE FILE, PLEASE CLICK THE "DOWNLOAD" CHECK BOX. IF YOU DO NOT AGREE TO THE TERMS, PLEASE CLICK THE "CANCEL" BUTTON. YOUR ATTENTION IS DRAWN TO CONDITION 3 NOTED BELOW WHICH FORMS PART OF THE TERMS IN RELATION TO OUR LIABILITY TO YOU.