Mariners are advised that circa the 21/04/2026, Geo Ocean IV will conduct a Pre-Installation Survey Campaign within the East Anglia THREE Offshore Windfarm area. During the period of Pre-Installation Survey, all vessels are requested to keep a 500m safety distance from the Geo Ocean IV at all times.
GEOxyz will utilise the ‘Geo Ocean IV' to perform a Pre-Installation Survey within the East Anglia Three Offshore Windfarm.
The vessel will conduct Multibeam Echo Sounder (MBES) and Side Scan Sonar (SSS) surveys of the WTG foundation locations, at a radius of 170m.
The Multibeam Echo Sounder is hull mounted and the Side Scan Sonar is towed from the stern of the vessel at a height of 6.5m to 10m above the seabed.
Geo Ocean IV is expected to mobilize from the port of ‘Lowestoft or Great Yarmouth’ circa the 21/04/2026. It is anticipated that the campaign will last approximately 15 days, the end of the campaign will be communicated by closure of this notice to mariners.
Geo Ocean IV will monitor VHF Channel 16 and VHF DSC Channel 70 continuously throughout the operation. It is currently anticipated that weather permitting, works will be carried out on a continuous basis (i.e.,24- hour working, seven days a week) unless notified otherwise.
See detailed map on our bulletin websitePlease be advised that Partrac Ltd will be undertaking maintenance on the two weather monitoring buoys that have been deployed within the East Anglia Three Offshore Windfarm area. Partrac will utilise the vessel ‘Green Isle’ for maintenance of these buoys. All Marine traffic is advised to maintain a 500m safety zone around the Green Isle during maintenance operations.
Weather Buoy maintenance to be conducted by the ‘Green Isle’.
It is currently anticipated that weather permitting, works will commence circa the 13/04/2026 The weather buoys will remain on station throughout the construction phase of the East Anglia THREE Offshore Windfarm.
Completion of maintenance works will be notified by future Notice to mariners.
See detailed map on our bulletin websiteMariners are advised that circa the 20/04/2026, Geo Ocean III will conduct a Boulder and Debris Removal Campaign within the East Anglia THREE Offshore Windfarm area. During the period of boulder and debris removal, all vessels are requested to keep a 500m safety distance from the Geo Ocean III at all times.
GEOxyz will utilise the ‘Geo Ocean III' to perform boulder and debris removal within the East Anglia THREE Offshore Windfarm.
The vessel will conduct investigation by ROV followed by relocation of boulders and debris with grab in the WTG locations and IAC strings.
Geo Ocean III is expected to mobilize from the port of ‘Ostende’ circa the 20/04/2026. It is anticipated that the campaign will last approximately 16 days, the end of the campaign will be communicated by closure of this notice to mariners.
Geo Ocean III will monitor VHF Channel 16 and VHF DSC Channel 70 continuously throughout the operation. It is currently anticipated that weather permitting, works will be carried out on a continuous basis (i.e.,24- hour working, seven days a week) unless notified otherwise.
See detailed map on our bulletin websitePlease be advised that Geoquip Marine Operations AG and GEO Denmark will be performing geotechnical operations in the form of soil investigation at Bowdun Offshore Wind Farm Array, on behalf of Thistle Wind Partners.
Mariners are advised about geotechnical investigations in the Thistle Wind Partners Bowdun E3 Windfarm Array area, chart provided in Figure 1, and coordinates in Table 1 below. Geoquip Marine is conducting these investigations on behalf of Thistle Wind Partners. Two survey vessels, Geoquip Seehorn and Geo – Connector will be performing these operations. Vessel details and contact information are provided below. The work is expected to commence on 19 April 2026.
See detailed map on our bulletin websiteMariners are advised about Marine Survey Works for the Eastern Green Link 2 Project. Scottish Hydro Electric Transmission Plc and National Grid Electricity Transmission Plc are delivering the Eastern Green Link 2 (EGL 2) Project. The EGL 2 project will play a vital role in achieving the UK and Scottish Government’s net zero targets and significantly increase the UK’s capacity for clean, green renewable power.
EGL2 are due to commence an unexploded ordnance (UXO) target investigation ROV survey on
1 April 2026.
This work consists of a single UXO target investigation to be conducted within the safety perimeter shown in Figure 1, the coordinates for this area are provided in Table 1.
The works consist of an ROV carrying out visual target investigation for the purposes of identifying potential unexploded ordnance, small excavations on the seabed may also be undertaken to identify targets. There may also be a small amount of debris recovery required depending on what is found during the investigation.
The work is estimated to finish on approximately the 20 April 2026, subject to weather.
Works are being undertaken under an approved Marine Licence from the Marine Directorate (MS- 00011033) and the approved Marine Licence from the Marine Management Organisation (L/2023/00211/2)
There will be no unexploded ordnance detonations performed; this is investigation works only.
Mariners are requested to maintain a safety perimeter of 500 m from the vessel Trym.
See detailed map on our bulletin websiteMariners are advised that cable laying activities are being carried out by CLV Seaway Phoenix within the East Anglia THREE Offshore Windfarm, the vessel is laying inter array cables between WTGs and the East Anglia THREE Offshore converter station (OFCS). Additional Vessels ‘Grand Canyon 3’ & ‘Windea Clausius’ will mobilise and join the project circa the 27/02/2026.
Cable laying operations will continue to be conducted within the East Anglia THREE Offshore Windfarm by CLV Seaway Phoenix. The vessels will install subsea cables between WTGs and the Offshore Converter Station (OFCS). The Grand Canyon 3 will conduct trenching and burial operations supporting the Cable-Laying operation. During cable deployment, trenching & burial, both the vessels will be restricted in their ability to manoeuvre.The Seaway Phoenix will carry out cable laying activities, and be supported by the Seaway Moxie & Windea Clausius, which will both undertake equipment and personnel transfers to WTGs and the OFCS via a Walk to Work (W2W) gangway system. While conducting these transfers, the Seaway Moxie & Windea Clausius will also be restricted in manoeuvrability.
For further information regarding Inter Array Cable Installation Operations, please see attached East Anglia THREE Notice To Mariners 006-2026 Inter- Array Cable Installation.
See detailed map on our bulletin website
Mariners are advised that ‘Rollingstone’ will conduct Seabed Rock Installation (SRI) at the Offshore Converter Station within the East Anglia THREE Offshore Windfarm Array, as detailed in section 2.1 of EA3 NTM-010-2026 - Subsea Rock Installation
NKT will conduct Seabed Rock Installation (SRI) at the East Anglia 3 Offshore Converter Station (OFCS) in the North Sea using the vessel DPFPV Rollingstone. Operations will be conducted continuously, 24 hours a day. The work will be performed in a single campaign.
Rock will be placed on the export cables at the interface to the OFCS. In/out surveys will be performed prior to and following rock placement.
It is requested that all vessels maintain a minimum of 1.5Nm separation distance from Rollingstone and pass at reduced speed. Fishing gear or other equipment with seabed intervention should not be deployed when approaching the working corridor.
Rollingstone is expected to mobilize circa 29/03/2026. Rollingstone will monitor VHF Channel 16 and VHF DSC Channel 70 continuously throughout the operations. It is currently anticipated that weather permitting, works will be conducted on a continuous basis (i.e.,24- hour working, seven days a week) unless notified otherwise. During operations, the Rollingstone will have restricted maneuverability as defined under COLREGs (International Regulations for Preventing Collisions at Sea, 1972). They will display the appropriate day shapes and lights and will transmit an Automatic Identification System (AIS) message. All vessels are required to monitor VHF Channel 16 and VHF DSC Channel 70 continuously throughout the operation.
See detailed map on our bulletin websiteMariners are advised that circa the 27/03/2026, Geo Ocean V will conduct Boulder and Debris Target Inspections within the East Anglia THREE Offshore Windfarm area set out in section 2.1 of this document. During the period of boulder and debris inspections, all vessels are requested to keep a 500m safety distance from the Geo Ocean V at all times.
GEOxyz will utilise the ‘Geo Ocean V' to perform boulder and debris target inspections within the East Anglia Three Offshore Windfarm.
The vessel will conduct investigation by ROV at the WTG locations.
Geo Ocean V is expected to mobilize from the port of ‘Lowestoft’ circa the 27/03/2026. It is anticipated that the works will last approximately 2 days, the end of the works will be communicated by closure of this notice to mariners.
Geo Ocean V will monitor VHF Channel 16 and VHF DSC Channel 70 continuously throughout the operation. It is currently anticipated that weather permitting, works will be carried out on a continuous basis (i.e.,24- hour working, seven days a week) unless notified otherwise.
See detailed map on our bulletin website2 x Unmanned survey vessels (USV) will be conducting subsea inspection works at Seagreen offshore windfarm. These surveys will include surveys of all 114 WTGs, 1 OSS and every Inter Array Cable (circa 1400km) on the site. These surveys will be operating 24/7 for the duration of the campaign.
ED2 Cable Installation Works: Mull-Iona
Please be advised that Briggs Marine Contractors (on behalf of SHEPD) will be undertaking a ROV survey of the recently installed cable between Mull and Iona.
Please refer to Figure 1 that shows the location of the planned works. Please also refer to Table 2 overleaf that lists the coordinates for the area.
The ROV survey will take place with the CBS Hurricane and will be regularly passing inside the working corridor.
Please refer to Table 1 that lists scope of work, estimated date range and the relevant vessels that will be utilised. As work progresses, further updates will be provided.
See detailed map on our bulletin websitePlease be advised that Briggs Marine Contractors (on behalf of SHEPD) will be conducting ROV surveys and installing additional subsea cable protection between Coll and Tiree.
Please be advised that Briggs Marine Contractors (on behalf of SHEPD) will be conducting ROV surveys and installing additional subsea cable protection between Coll and Tiree.
Please refer to Figure 1 that shows the location of the planned works.
Please also refer to Table 2 overleaf that lists the coordinates for the area.
The cable protection installation will take place with the CBS Hurricane and will consist of a ROV survey and Diving operations.
Please refer to Table 1 that lists scope of work, estimated date range and the relevant vessels that will be utilised. As work progresses, further updates will be provided.
See detailed map on our bulletin websiteThe offshore geophysical site investigation of the proposed Morecambe Offshore Wind Project is planned to commence approximately 10 April 2026, with operations continuing until 20 April 2026, subject to weather. The works are being undertaken by the Fugro Frontier (vessel details in attached notice)
The Fugro Frontier will be performing a UXO site investigation for the purpose of UXO ALARP ahead of a planned geotechnical site investigation in May 2026. The Fugro Frontier will be conducting operations within 50x50m boxes using the following sensors:
§ Multibeam Echosounder (MBES)
§ Side Scan Sonar (SSS)
§ Magnetometer (MAG)
§ Survey Verification Test (SVT)
See detailed map on our bulletin websiteGlobal Marine Systems Limited (GMSL), on behalf of SHEFA, will be undertaking the installation of the SHEFA-2 Fibre Optic Cable system in the North Sea. Operations are anticipated to take place in Q2 2026. The vessels, CS Sovereign and Glomar Supporter, will be undertaking underwater activities in the area and mariners should exercise caution and communicate with the vessel.
Mariners are advised that Global Marine Systems Limited (GMSL), on behalf of SHEFA, will be undertaking the installation of the SHEFA-2 Fibre Optic Cable system in the North Sea. Operations are anticipated to take place in Q2 2026.
The vessels, CS Sovereign and Glomar Supporter, will be undertaking underwater activities in the area and mariners should exercise caution and communicate with the vessel.
The vessels will be limited in manoeuvrability therefore, vessels working in the area should proceed with caution within 1NM from the cable ships during operations and all activity should remain clear 250m either side of the vessels, 500m corridor in total.
The operational VHF channel for project vessels is Channel 70 and all vessels will monitor Channel 16. Vessels are encouraged to seek further information from local port authorities in areas of operations.
For further details on vessel and schedule see attachment.
See detailed map on our bulletin websiteMariners are advised that the Valaris 248 is positioned alongside the Offshore Converter Platform supporting the ongoing commissioning programme. The SOV "Rem Energy” is expected to commence operations on or around 2nd April 2026 supporting the operations & maintenance of the offshore windfarm.
A scheduled service from an assigned pool of Platform Supply Vessels providing supplies to the Offshore Converter Platform & JUV until further notice. Those nominated vessels are:
An eight legged jacket with 8 driven pin piles has been installed as a foundation for the OCP followed by the OCP itself.
The Sofia Offshore Wind Farm Boundary Co-ordinates where the works will take place are provided below. All non-project vessels are requested to remain outside this area.
Mariners are requested to remain where possible 500m from vessels. During these works, SOVs will have restricted manoeuvrability and shall also be exhibiting the correct day shapes/ lights and flag for vessels engaged in diving operations and restricted in ability to manoeuvre.
Emergency Response & Rescue Vessel
The EERV Putford Jaguar is supporting the commissioning phase of the Offshore Converter Platform, providing close standby cover as required during overside works.
Service Operation Vessels
The Service Operations Vessel (SOV) “Purus Power” & Daughter craft “Purus Transporter” continues to support the SOWF project throughout the construction of the offshore windfarm.
The 'SOVs' ACTA Centaurus and Austri Enabler continues operations within the Sofia Array.
SOVs shall be transiting to / from the Sofia Array and the port of Blyth / Sunderland throughout this period.
Crew Transfer Vessel
The Crew Transfer Vessel (CTV) and MHO Gurli continue operations at the Sofia OWF.
All Mariners are advised to always give a wide berth of approx. 500m metres from the above vessels. The vessels shall be exhibiting the correct day signals / night lights for the operations as defined by COLREGS and can be contacted on VHF 16 for further information as required reference proximity / nearby operations etc.
See detailed map on our bulletin websiteRhyl Flats Windfarm - RF14, RF18, RF07 & RF19 Jack up Vessel - Generator and Transformer Campaign
All mariners are advised that MPI Adventure will be carrying out maintenance operations at Rhyl flats Offshore Wind Farm from 10/04/2026 until 18/04/2026. These dates are subject to weather and sea conditions. Specific coordinates of locations where works occur are found below.
Works Locations
|
Location |
Coordinates |
Works type |
|||
|
Lat DDM |
Lon DDM |
Northing |
Easting |
||
|
RF14 |
53°22.771'N |
003°38.620'W |
388,222
|
290,761
|
Generator Replacement |
|
RF18 |
53°22.388'N |
003°36.925'W |
387,469
|
292,624
|
Generator Replacement |
|
RF07 |
53°22.903'N |
003°36.600'W |
388,416
|
293,006
|
Generator Replacement |
|
RF19 |
53°22.817'N |
003°41.433'W |
387,200 |
332,100 |
Transformer Replacement |
Mariners must observe the safety zone of 500m when the MPI Adventure is attached or anchored next to RF14, RF18, RF07 & RF19. It is also requested that mariners observe a distance of at least 500m when MPI Adventure is manoeuvring into position for the safety of all sea users operating
All mariners and their equipment are requested to remain at least 500m from all infrastructure at all times. CTVs will be regularly on site and mariners should keep a safe working distance of 500 m from these vessels where possible
See detailed map on our bulletin websiteAll Mariners are advised that the SGRE Vessel “Wind Peak” continues Wind Turbine (WTG) Generator installation at the Sofia Array. The vessel will also be supported by ongoing commissioning activities carried out with the following SGRE Vessels: “IWS SeaWalker”, “FOB Swath 9” & “FOB Swath 10”.
The following table highlights WTG installation progress and next 7 day forecast.
|
Total WTGs Installed (100 in Total) |
WTGs Installed (Since Previous Update) | WTGs Location Forecast (Next 7 Days) |
| 77 | F15, | E13, G15, J13, G13, H15 – Trip #14 |
Vessels operational during these works are as follows:
| Vessel Name | Vessel Type | Length (M) | Gross Tonnage | IMO | Call Sign | MMSI Number |
| Wind Peak | WTG Installation Vessel | 150 | 34100 | 9957828 | OZVU2 | 219032994 |
| IWS Seawalker | Service Operation Vessel | 90 | 6712 | 9968580 | LAVP8 | 257784000 |
| FOB Swath 9 | Crew Transfer Vessel | 33 | 372 | 9920576 | OYKP2 | 219027989 |
| FOB Swath 10 | Crew Transfer Vessel | 32 | 372 | 9920588 | OYMX2 |
219027988 |
The exact finish date will be dependent on the prevailing weather conditions and work progress. Mariners are requested to remain where possible 500m from Construction vessels when exhibiting the day shapes / night lights for vessels restricted in their manoeuvrability.
Service Operation Vessels
The Service Operations Vessels (SOV) "Rem Energy", “Purus Power” & Daughter craft “Purus Transporter” continues to support to the SOWF project throughout the construction of the offshore windfarm.
The SOV 'ACTA Centaurus' and 'Austri Enable continues operations within the Sofia Array.
SOVs shall be transiting to / from the Sofia Array and the port of Blyth / Sunderland throughout this period.
Crew Transfer Vessel
The Crew Transfer Vessel (CTV) MHO Gurli continues operations at the Sofia OWF.
All vessels can be contacted on VHF 16 throughout as required. All vessels shall be operating to / from the Port of Hull and will be operational 24 hours / day.
See detailed map on our bulletin websiteICCP campaign (Impressed Current Cathodic Protection) is to replace one anode at each of the six locations/turbines specified in section 2, along with one reference cell at IGJ02. Implementing this campaign necessitates the utilisation of an external diving system. The anodes are positioned at the end of each transition piece. The company that will be executing the campaign is REDS (Reach Engineering & Diving Services Ltd).
IGJ02 51 55.943'N 001 59.565'E
IGJ03 51 55.422’N 001 59.246’E
IGH07 51 55.025’N 001 57.472’E
IGC02 51 57.144’N 001 53.915’E
IGG09 51 53.226’N 001 55.606’E
IGI10 51 52.338’N 001 56.477’E
See detailed map on our bulletin websiteVenterra are planning to deploy three Floating LiDAR Buoys in the area around the NOAH Met Mast under Marine Licence L/2020/00313/1. This document is to notify mariners regarding the deployment.
Venterra have deployed three Floating LiDAR Buoys in the area around the NOAH Met Mast. Deployment operations took take place on or around 6th April 2026. The three buoys will remain on station for a minimum of 1 month, recovery expected in May 2026, weather permitting.
Marine users are advised to always maintain a 500m separation from each buoy and operational vessel at all times.
See detailed map on our bulletin websiteMariners are advised that a geophysical survey is planned for the Eastern Green Link 5 (EGL 5) project. The marine survey activities for EGL 5 are planned to commence on the 12th of January 2026 and are expected to complete approximately April 2026.
Mariners are advised that a geophysical survey is planned for the Eastern Green Link 5 (EGL 5) project. The marine survey activities for EGL 5 are planned to commence on the 12th of January 2026 and are expected to complete approximately April 2026.
Eastern Green Link 5 Geophysical survey area consists of multiple Notice to Mariners referenced below (this notice is highlighted in bold):
NtM_EGL5-SSEN-MAR-XX-CO-MC-004
NtM_EGL5-SSEN-MAR-XX-CO-MC-001 - Geophysical survey area outside 12nm
EGL5-SSEN-MAR-XX-CO-MC-002 – Geotechnical survey area outside 12nm
SSEN Transmission and National Grid Electricity Transmission (NGET) are working together to address the need for increased capacity within the transmission network between Scotland and England. EGL5 will help provide increased capacity, carrying up to 2 GW of electricity, enough for two million homes. This will be achieved through a High Voltage Direct Current (HVDC) cable connection between Aberdeenshire and Lincolnshire.
The EGL 5 geophysical survey works are being carried out by Ocean Infinity Limited.
The area of work, pertaining to this Notice to Mariners (NtM) for EGL 5, is highlighted in Figure 1, with the survey vessels contact details for the project found in Table 1. Contact details for the project Fisheries Liaison Officers (FLO) are detailed below.
See detailed map on our bulletin website
All mariners and stakeholders are advised that monopile B02 is unlit until further notice.
All mariners and stakeholders are advised that monopile B02 is unlit until further notice.
Whilst unlit the monopile shall be monitored by the guard vessel Ocean Rose
B02 location and coordinates shown in the attached notice to mariners.
See detailed map on our bulletin websiteSeabed Frame unable to be recovered from deployed location - risk of snagging, alert to all marine users.
During recovery operations following completion of metocean data collection at the Muir Mhor site, the seabed frame was unable to be recovered. Seabed frame recovery was not possible due to transponder onboard vessel being unable to make a connection with acoustic receiver on the seabed frame. It is not yet confirmed whether the seabed frame is in the deployed location and is simply damaged, or whether it has been moved.
See attached photo for details of the frame.
Last known location of the seabed frame is the deployed location as per coordinates given in this notice.
Report has been made to Marine Directorate on 22/07/2025. Further updates on recovery will be posted to a separate notice (ID-5431).
Search operations were undertaken in March 2026; object not located. Further update to follow.
See detailed map on our bulletin websiteP21 Jack up campaign consisting of 17 components over 14 assets order will be (subject to weather) (GAD03, IGLO1, GAB03, IGI06 Complete) Awaiting weather window to relocate from GAB03 to IGD02 remaining assets GAF01, IGF03, PORT CALL, IGC06, IGI01, IGK03, GAE05, GAF05
Jack up Location GAF05 Gear Box 51° 45.077' N 1° 58.938' E
Jack up Location IGK03 Main Bearing/ Gear Box/ Generator 51° 52.817 N 1° 58.188' E
Jack up Location IGF10 Gearbox 51° 51.618' N 1° 53.892'E
NR Cheetah Jack up CTV Support
See detailed map on our bulletin websiteA UXO was found and is currently sitting in position 51'57.924'N 001'56.122'E as per NTM. This is inside the Greater Gabbard windfarm - we have no plans to remove/ move/ detonate. This has been surveyed and the risk of detonation is low however we would advise a 500m exclusion zone Re surveyed 03/26
Global Marine are conducting the installation of the Q&E South telecommunications cable from the French Territorial Waters to Cayeux-sur-Mer, France. Timings are dependent upon weather and other operational conditions.
There will be various vessels associated with the works. The vessels will be limited in manoeuvrability therefore, vessels working in the area should proceed with caution within 1NM from the cable ship during operations and all activity should remain clear 250m either side of the vessel, 500m corridor in total. Please distribute this information accordingly so that other sea users are aware.
Please contact myself Adrian Carter, Permitting Manager (adrian.carter@oceaniq.co.uk) or Chris Butler, Project Manager (chris.butler@globalmarine.group) if you have any queries regarding this notification or if you have any information on any underwater activity in this area that is relevant to the operation.
See detailed map on our bulletin website
Balance of Plant Asset Inspections at Moray East Wind Farm
Please be advised that Moray Offshore Windfarm (East) Limited (Moray East) are planning as part of the annual operations and maintenance of assets, general visual inspection of the asset foundations (Table 1 and Figure 1). Asset foundation inspections will be carried out by the Voe Vanguard which is expected to be on site from 20th April to 25 July 2026. Works will be completed at all 100 WTG within the red boundary in Figure 1.
Please be aware that, during the survey activities, by virtue of its mode of operation the vessel (Voe Vanguard) will be Restricted in her Ability to Manoeuvre (RAM) as defined under COLREGs (International Regulations for Preventing Collisions at Sea 1972, Rule 3). Masters of vessels are therefore requested to maintain their vessels and gears at a minimum safe passing distance from the vessel of 500 metres when it is undertaking work and showing the appropriate shapes and lights in accordance with COLREGs Rule 27.In order to not compromise the safety of the Survey Vessel, their crew, and their ability to undertake its contracted works, fishermen who have static fishing gears deployed within 500 m from the WTG where survey activities are planned (see Table 1 and Figure 1) are requested to provide the coordinates of such deployed gears in DMS and details of whether the surface markers used are visible at all states of visibility to Alex Winrow-Griffin (Brown & May Marine) using the contact information below (Section 58 of the Merchant Shipping Act 1995).Fishermen who have static gears deployed beyond 12 nm are reminded that static gear must be marked in accordance with Commission Implementing Regulation (EU) No. 404/2011 (https://www.gov.uk/guidance/marking-of-fishing-gear-retrieval-and-notification-of-lost-gear#marking-of-fishing-gear)
See detailed map on our bulletin websiteGeophysical surveys around selected turbines at Moray East Wind Farm
Please be advised that Moray Offshore Windfarm (East) Limited (Moray East) are planning to undertake geophysical surveys within the site boundary (Table 1 and Figure 1). Survey operations will be carried out by the Geosurveyor XI which is expected to be on site from 15th April to 25th May 2026. The survey will take place within the red boundary in Figure 1.The geophysical survey scope will include Multibeam Echosounder (MBES), Side Scan Sonar (SSS) of a maximum of 50 m width at 22 inter-array cables and 2 interconnector cables, and a 300m2 area around 30 WTGs and 3 OSP locations. The coordinates of the work site boundary are presented in the below Table 1 and shown in Figure 1.
1. General Safety AdvicePlease be aware that, during the survey activities, by virtue of its mode of operation the vessel (Geosurveyor XI) will be Restricted in her Ability to Manoeuvre (RAM) as defined under COLREGs (International Regulations for Preventing Collisions at Sea 1972, Rule 3). Masters of vessels are therefore requested to maintain their vessels and gears at a minimum safe passing distance from the vessel of 500 metres when it is undertaking work and showing the appropriate shapes and lights in accordance with COLREGs Rule 27.In order to not compromise the safety of the Survey Vessel, their crew, and their ability to undertake its contracted works, fishermen who have static fishing gears deployed within 500 m from the WTG where survey activities are planned (see Table 1 and Figure 1) are requested to provide the coordinates of such deployed gears in DMS and details of whether the surface markers used are visible at all states of visibility to Alex Winrow-Griffin (Brown & May Marine) using the contact information below (Section 58 of the Merchant Shipping Act 1995).Fishermen who have static gears deployed beyond 12 nm are reminded that static gear must be marked in accordance with Commission Implementing Regulation (EU) No. 404/2011 (https://www.gov.uk/guidance/marking-of-fishing-gear-retrieval-and-notification-of-lost-gear#marking-of-fishing-gear)
See detailed map on our bulletin websiteThis is to raise awareness that as part of the annual operations and maintenance of assets, geophysical surveys will be taking place within the Moray Offshore Windfarm (West) Limited (Moray West) site.
Survey operations will be carried out by the Geosurveyor XI which is expected to arrive at the Moray West site 16th April. Geophysical surveys are programmed to be carried out along the Moray West Offshore Export Cable (OEC) on 17th-18th April. The vessel will then proceed to Moray East to survey the windfarm assets, before returning to the Moray West site to complete the geophysical surveys across the rest of the site (around turbines and inter array cables).
The geophysical surveys within the OEC are anticipated to take one day and will be carried out during daylight hours only. Survey operations within the OEC will be able to work around any fishing gear sighted from the vessel. It is anticipated that the vessel will resume work on the Moray West site on approximately 3rd May, with the survey period covering approximately 38 days (16 days of work and a contingency for weather downtime/ delays on Moray East). Works within the Moray West red boundary (Figure 1) will take place throughout a 24-hour period.
See detailed map on our bulletin websiteXOCEAN is planning the collection of geophysical data using remotely piloted Uncrewed Surface Vessels (USVs) along a proposed cable route corridor in Orkney, from the islands of Sanday to North Ronaldsay.
XOCEAN is planning the collection of geophysical data using remotely piloted Uncrewed Surface Vessels (USVs) along a proposed cable route corridor in Orkney, from the islands of Sanday to North Ronaldsay.
The USVs are expected to operate out of Westray Marina for the full survey duration.
A mix of USVs with both hull mounted survey sensors (Multibeam Echosounders & Sub-Bottom Profilers) and also towed sensors (SideScan Sonar & Magnetometer) through the water in proximity of the seabed will be used.
A crewed Support Vessel will be chartered throughout the survey to support the USVs with departures and arrivals from Westray Marina and assist in towing them back in if a technical issue occurs.
Dates/Duration: Operations are expected to commence around 15 April 2026.
It is expected that the survey activities shall be completed within 30 days (subject to weather).
Survey Area: Figure 1 below indicates the operational area which is shown by the darker green area. This is outlined in Table 1 below also.
Fishing Gear Clearance: No fishing gear clearance is presently being requested for these surveys.
See detailed map on our bulletin websiteUSV Operations Sheringham Nearshore
Operation of remotely piloted Uncrewed Surface Vessels (USVs) are planned in the southern North Sea, UK, during April and May 2026. The vessels will be engaged in survey activities on behalf of Sheringham Shoal and Dudgeon Extensions ProjCo Limited in the nearshore area of Sheringham (0-12 LAT) as outlined in Figure 1. It is expected there will be two USVs operational at any one time. Dates: Survey operations are expected to commence from 14th April 2026 for approximately two weeks, subject to weather and other operational factors.
See detailed map on our bulletin websiteMariners are advised that the East Cardinal Buoy at the Sofia OWF remains until. A remedey plan is currently being worked on to support reinstatement of the unlit buoy as soon as weather allows.
| Buoy | ID | Lat (DDM) | Long (DDM) | Light and Mark Specifications |
| East Cardinal | E3 | 54 59.04N | 002 30.27E |
|
See detailed map on our bulletin website
All mariners and stakeholders are advised that Passive Acoustic Monitoring (PAM) moorings for the purpose of underwater noise monitoring will be deployed within the Inch Cape Offshore wind farm site, and at two locations in the proximity of the wind farm site. The deployments are ongoing and will remain in place for 14-30 days in total.
All mariners and stakeholders are advised that Passive Acoustic Monitoring (PAM) moorings for the purpose of underwater noise monitoring will be deployed within and in the proximity of the Inch Cape Wind Farm site.
A total of eight moorings will be deployed within the wind farm site and will remain in place for approximately 7-14 days. Following this period, the moorings will be recovered and redeployed at different locations within the site to remain in place for further 7-14 days. These locations are shown in the attached notice to mariners
A total of two moorings have been deployed outside the wind farm site and will remain in place for 14-30 days. The location and coordinates are provided in Figure 4 and Table 3.
These moorings will not be surface marked as the top of the mooring extends approximately 4-7m above the seabed.
The crew transfer vessel Manor Victor shall deploy the devices with operations expected to be completed within six days.
See detailed map on our bulletin websiteThe Offshore Service Vessel, Trym, will perform boulder relocation operations within Dogger Bank B offshore construction area
The works will be performed in a single campaign, commencing on the 10th of April 2026 continuing until approximately the 30th of April 2026. The works will be continuous, 24 hours a day.
The operations involve the relocation and/or removal of subsea boulders by means of a Remote Operated Vehicle (ROV) around the Wind Turbine Generator (WTG) locations.
During operations, the Trym will be restricted in its ability to manoeuvre as defined under COLREGs (International Regulations for Preventing Collisions at Sea 1972) and will display the appropriate day shapes and night lights. The vessel will also transmit an Automatic Identification System (AIS) message.
It is requested that all vessels maintain a minimum of 500m safety separation distance from the Offshore Trym and pass at reduced speed.
See detailed map on our bulletin websiteVarious activities within the Sheringham Shoal windfarm that may impact on other mariners.
The Jack-Up vessel “ZITON WIND SERVER” is expected to arrive at Sheringham Shoal wind farm on 12th April 2026. Seven WTG locations are planned for major component exchange.
Mariners are advised that Sheringham Shoal Offshore Wind Farm will be conducting a scheduled blade repair campaign between 1 April and 30 June 2026.
During the summer the CTV “Ava Sofie” will look to complete ladder cleaning activities for Bird waste and marine growth removal on all 88 WTGs.
PLEASE SEE ATTACHED NTM FOR FURTHER DETAILS ON ALL 3 ACTIVITIES.
See detailed map on our bulletin websiteGeophysical survey in the Tidal and Nearshore areas of Sandford Bay, Peterhead. Between 0m-25m LAT.
Nearshore Geophysical survey, performed under a Marine Licence issued by the Marine Directorate Licencing Operations Team (MD-LOT) – MS-00011499 and a Licence issued by Crown Estates Scotland - ref. AMR/CES/EI-0067.
The Shore Possibility (Tidal) and Presence (Nearshore) will be restricted in their ability to maneuver and will display the appropriate lights and shapes prescribed by the International Regulations for Preventing Collisions at Sea. Other vessels are requested to provide a minimum clearance of 500m from the survey vessels during marine operations and pass at a safe speed. Regular Security Messages will be issued on VHF Channel 16 and this Channel will be always monitored by the vessels. The vessels will also transmit regular Automatic Transmission Identification System (AIS) Messages.
See detailed map on our bulletin websitePlease be advised that Aspect Land & Hydrographic Surveys Ltd (on behalf of SHEPD) will be undertaking subsea inspections across the West Highland marine areas.
Please be advised that Aspect Land & Hydrographic Surveys Ltd (on behalf of SHEPD) will be undertaking subsea inspections across the West Highland marine areas.
Given the different conditions and water depths anticipated at each site, a range of vessels will be available for the project.The inspection works will be centred on a 50m cable corridor.
VESSEL DETAILSThe vessel conducting the works will be restricted in its ability to manoeuvre and will display the appropriate lights and shapes.Other vessels are requested to pass at a safe speed and provide a minimum clearance of 500m (COLREGs Rule 16 & 18) during marine operations.The vessel will monitor VHF Channel 16 throughout survey operations.
See detailed map on our bulletin websiteFall Pipe Vessel (FPV) Rollingstone will continue with subsea rock installation at various locations on Dogger Bank C
Rollingstone will start operations on 10th of April 2026 and will perform rock placement during multiple loadouts, finishing her scope around 30th of April 2026. Work will be continuous, 24 hours a day.
During operations, Rollingstone will be restricted in their ability to manoeuvre, as defined under COLREGs (International Regulations for Preventing Collisions at Sea 1972) and will display the appropriate day shapes and lights. The vessel will also transmit an Automatic Identification System (AIS) message.
It is requested that all vessels maintain a minimum of 500m separation distance from the Rollingstone and pass at reduced speed.
See detailed map on our bulletin websiteMariners are advised that a marine cable route survey is planned for the proposed Shetland HVDC Link 2 cable. The survey will involve geophysical, geotechnical and benthic surveying. SSEN Transmission conduct marine surveys to gain information on seabed morphology, installation design, sediment structure and to gain benthic characterisation and habitat mapping.
Reach Subsea UK LTD are conducting a survey campaign on behalf of Scottish Hydro Electric Transmission Plc. Trading as Scottish and Southern Electricity Networks Transmission (SSENT). SSEN Transmission plan to commence the marine survey inside 12nm on 28th March 2026. The survey equipment will consist of Multi Beam Echo Sounder (MBES), Side Scan Sonar (SSS), Sub-Bottom Profiler (SBP), Magnetometer, Benthic grabs, Vibrocores and Core Penetration Tests across 2 different vessels that will likely be no further inshore than 15m LAT. The survey equipment will also require calibration testing, which may be conducted outwith the survey corridor.
See detailed map on our bulletin websiteRecent surveys have discovered 2 exposures on an HVDC cable in the Thames Estuary.
The westerly exposure is 26m long, the easterly is 27m long.
See detailed map on our bulletin websiteMariners are advised that a geophysical survey is planned for the Eastern Green Link 5 (EGL 5) project. The marine survey activities for EGL 5 are planned to commence on the 23rd of November 2025 and are expected to complete approximately April 2026.
Mariners are advised that a geophysical survey is planned for the Eastern Green Link 5 (EGL 5) project. The marine survey activities for EGL 5 are planned to commence on the 23rd of November 2025 and are expected to complete approximately April 2026. SSEN Transmission and National Grid Electricity Transmission (NGET) are working together to address the need for increased capacity within the transmission network between Scotland and England. EGL5 will help provide increased capacity, carrying up to 2 GW of electricity, enough for two million homes. This will be achieved through a High Voltage Direct Current (HVDC) cable connection between Aberdeenshire and Lincolnshire.The EGL 5 geophysical survey works are being carried out by Ocean Infinity Limited.The area of work, pertaining to this Notice to Mariners (NtM) for EGL 5, is highlighted in Figure 1, with the survey vessels contact details for the project found in Table 1. Contact details for the project Fisheries Liaison Officers (FLO) are detailed below.
See detailed map on our bulletin websiteOperations of a remotely piloted Uncrewed Surface Vessel (USV) are planned out of Carlingford starting around the start of April 2026. The vessel will be engaged in geophysical survey activities in the Walney West of Duddun Offshore Wind Farm, approximately 16km off the coast of Barrow in Furness. It is expected there will be a single USV operational at any one time.
Operations of a remotely piloted Uncrewed Surface Vessel (USV) are planned out of Carlingford starting last week of March 2026. The vessel will be engaged in geophysical survey activities in the Walney West of Duddun Offshore Wind Farm, approximately 16km off the coast of Barrow in Furness. It is expected there will be a single USV operational at any one time.
Dates/Duration: Operations are expected to commence around 3rd April 2026. It is expected that the survey activities shall be completed within 1.5 days (subject to weather).
Survey Area: Figure 1 below indicates the operational area. This is outlined in the attached NtM also.
Exclusion Area / Closest Point of Approach: Seafarers are kindly asked to provide a clearance of >500m from the USV at all times when they are in operation.
Support Vessel: The USV operations will be supported by a crewed Support Vessel.
See detailed map on our bulletin websiteAttached is a Notice to Mariners issued by RWE concerning Exposed or the risk of Exposed Cables within the Robin Rigg Wind Farm. Please Note that the notice that was issued on 31 – 01 – 25 is now rescinded Please Read the Updated Notice Regards : Tom Watson Tel……07903 173 624
Attached is a Notice to Mariners issued by RWE concerning Exposed or the risk of Exposed Cables within the Robin Rigg Wind Farm.
Please Read the Updated Notice
Regards : Tom Watson
Tel……07903 173 624
See detailed map on our bulletin websiteOEG will be returning to EA2 to conduct disposals of positively identified UXO's. These works are expected to begin on 5th April and continue until Mid June, date TBC. During this time the Northern Victoria will carry out Archaeology and debris relocations, fish net recovery/relocations and UXO disposals.
During OEG's return scope on EA2 with the Northern Victoria the vessel has a total of 24 archaeology targets to relocate, 5 abondonded fishing nets that are to be recovered to deck or relocated away form planned works locations and multiple debris relocations using a combination of orange peel grab, ROV and ROV/SMT techniques.
UXO disposals will be carried out using Low Order techniques. There are no High orders expected to be carried out by the disposal team and securite broadcasts will be made at certain times around disposals to all vessels in the area to keep thier distance.
See detailed map on our bulletin websiteExport Cable Repair - Barrow Offshore Wind Farm Attached is a Notice to Mariners issued by GEO-4D (Transmission Capitol) concerning the repair to the damaged Barrow Offshore Wind Farm Export Cable Barrow Offshore Wind Farm Please read the notice
Sub-Sea Export Cable Repair - N-Sea - will act as the principal contractor using the dedicated DP2 Vessel ‘GEOQUIP ELENA’
‘GEOQUIP ELENA’ can be expected to arrive on-site on or around Saturday 18th. April (picture along with vessel details are on page 3 of the attached notice)
PLEASE READ THE ATTACHED NOTICE
All MARINERS PLEASE NOTE THAT AT ALL TIMES WHILE ON-SITE TO AFFECT REPAIR ‘GEOQUIP ELENA’ WILL BE RESTRICTED IN HER ABILITY TO MANOEUVRE
THEREFORE, WHENEVER THIS VESSEL IS ON-SITE A WIDE BERTH, MINIMUM 500 METERS, IS REQUESTED AT ALL TIMES AND PASSING VESSELS ARE REQUESTED TO REDUCE SPEED IF POSSIBLE.
Small chartlets included with the NtM show the coordinates and the route of the Barrow Export Cable running along the seabed
IN THE LEAD UP TO AND FOR THE DURATION OF THIS SURVEY/REPAIR FISHERMEN ARE REQUESTED, AND ADVISED, NOT TO SET ANY GEAR CLOSE TO OR ALONG THE LENGTHS OF THE CABLE SHADED RED ON THE CHARTLETS - PAGES 2 & 6 - ON THE ATTACHED NOTICE.
PLEASE RE-LOCATE ANY GEAR ALREADY IN CLOSE PROXIMITY – IF IN DOUBT PLEASE CONTACT ME
‘GEOQUIP ELENA’ will keep a listening watch on VHF Channels 16 & 12 and can be contacted for information relating to vessel movements only.
PLEASE READ THE NOTICE
Page 2 : General information along with two small chartlets showing route of BARROW EXPORT CABLE
Page 3 : Pictures and details of GEOQUIP ELENA
Page 4 : General schedule of repair works – plus General Safety Advice
Page 5 : Contractors contact details (if required)
Page 6 : Small Chartlet showing ‘work area’ along with co-ordinates
Please do not hesitate to contact me if you are unsure about any of the above or require any further information, also please pass this information to any of your colleagues who you think might be interested.
If you know of any fisherman who works the area and does not receive this information or anybody else who would benefit from this information please let me know.
……………………………………………………………………………………………….
If in any doubt please contact me
Regards : Tom Watson
Tel……….. Mobile 07903 173 624
See detailed map on our bulletin websitePlease be advised that Aspect Land & Hydrographic Surveys Ltd (on behalf of SHEPD) will be undertaking a subsea inspection in the Outer Hebrides marine area. Please refer to Figure 1 that highlights the location.
Please be advised that Aspect Land & Hydrographic Surveys Ltd (on behalf of SHEPD) will be undertaking a subsea inspection in the Outer Hebrides marine area. Please refer to Figure 1 that highlights the location.
Given the different conditions and water depths anticipated on site, a range of vessels will be available for the project, detailed overleaf.
The inspection works will be centred on a 50m cable corridor, defined by the start and end coordinates listed in Table 1.
See detailed map on our bulletin websiteUnmanned survey vessel debris following collision. Planning is underway to recover this, likely to be Spring 2026
Re surveyed 03/26
See detailed map on our bulletin websiteGeophysical survey along the BBL asset. The proposed surveys will utilise the N-Sea Geo Focus vessel and includes bathymetric multibeam echosounder (MBES).
Notice to Mariners for construction activities associated with Hornsea Project Three Offshore Wind Farm. This notice will be updated weekly to provide insights into the project's activities throughout the construction phase.
Mariners are advised that the Commissioning “Walk to Work” (W2W) Vessel IWS Windwalker and supporting Crew Transfer Vessels (CTVs) Fob Swath 6 and Fob Swath 7 will commence Wind Turbine Generator (WTG) commissioning operations within the East Anglia THREE offshore windfarm area circa the 18/03/2026. Operations will be conducted by Siemens Gamesa Renewable Energy (SGRE). The main working area will be as detailed in Attached EAT NTM 008-2026 Wind Turbine Generator Commissioning Campaign.
IWS Windwalker and supporting CTVs will commission 95 WTGs at the locations set out in section 2.2 ofEAT NTM 008-2026 Wind Turbine Generator Commissioning Campaign.Installed WTGs shall be marked with the following aids to navigation:LightsFl Y 2.5s light (visible through 360°)Minimum 2 nm range
Partially constructed monopiles shall be marked with the following aids to navigation where a transition piecehas not been installed:
LightsFl Y 2.5s light (visible through 360°)Minimum 2 nm rangeWeather permitting, offshore works will be carried out on a continuous basis (i.e. 24-hour working, seven daysa week).During operations, the IWS Windwalker will have restricted manoeuvrability as defined under COLREGS(International Regulations for Preventing Collisions at Sea, 1972). They will display the appropriate day shapesand lights and will transmit an Automatic Identification System (AIS) message.
Program Schedule:The IWS Windwalker will mobilise at the Port of Lowestoft, with first commissioning activitiesanticipated to start around 18/03/202
The CTVs will mobilise at the Port of Lowestoft and support the IWS Windwalker throughout thecampaign.
WTG installation is expected to be completed end of Q4 2026.
See detailed map on our bulletin website21x scientific seabed passive acoustic monitoring systems are currently deployed across the UK Celtic Sea area. Servicing of the acoustic monitoring stations will take place from week commencing 30/03/2026, subject to weather conditions. Units are fully subsurface with no surface markers. Mariners should exercise caution during operations and avoid trawling or seabed gear deployment near positions. Mariners are advised to exercise caution in the vicinity during active operations.
*Servicing Operations
Servicing of the acoustic monitoring stations will take place from week commencing 30 March 2026, subject to weather conditions.
Operations will involve service vessels working at or near station positions for short durations during suitable weather windows.
Mariners are advised to exercise caution in the vicinity of these positions during active operations.
Some primary aims of the SubSea Soundscape project are;
To support a new Marine mammal evidence base for the Celtic Sea.
To create a region wide acoustic soundscape model and open-source baseline acoustic data of the Celtic Sea integrating new S3 data and other secured acoustic data sources.
To Co-develop road maps for the use of acoustic soundscape models for consenting.
Navigation Advice
Equipment is fully subsurface and presents no hazard to surface navigation.
Trawling, dredging, or seabed gear deployment in the vicinity of marked positions could be avoided to reduce risk of entanglement or equipment damage.
Total vertical height of unit: approx. 5 m above seabed.
Minimum clearance above highest point: 55 m in shallowest locations.
Each acoustic monitoring system will comprise:
• Acoustic release system
• Fish tag detection system (69 kHz)
• Broadband hydrophone and cetacean click-train logger
• Mooring frame with integrated components
See detailed map on our bulletin website
Geophysical survey in the Tidal and Nearshore areas of Bridlington, Yorkshire. Between 0m-25m
Nearshore Geophysical survey, performed under a Marine Licence issued by the Marine Directorate Licencing Operations Team (MD-LOT) – MS-00011499 and a Licence issued by Crown Estates Scotland - ref. AMR/CES/EI-0067.
The Shore Presence will be restricted in the ability to maneuver and will display the appropriate lights and shapes prescribed by the International Regulations for Preventing Collisions at Sea. Other vessels are requested to provide a minimum clearance of 500m from the survey vessels during marine operations and pass at a safe speed. Regular Security Messages will be issued on VHF Channel 16 and this Channel will be always monitored by the vessels. The vessels will also transmit regular Automatic Transmission Identification System (AIS) Messages.
See detailed map on our bulletin websiteMariners are advised about Marine Survey Works for the Eastern Green Link 2 Project. Scottish and Southern Electricity Networks Transmission and National Grid Electricity Transmission Plc are delivering the Eastern Green Link 2 (EGL 2) Project. The survey works for EGL 2 precedes the installation of an electricity transmission link from the East coast of Scotland (Sandford Bay, Peterhead) to the East coast of England (South of Bridlington/Flamborough Head) due to be completed in 2029
EGL2 are due to commence an unexploded ordnance (UXO) target investigation ROV survey on the 9th of March 2026.
The works are to be conducted within the Exclusion Block (Block 3) shown by Figure 1, the coordinates for this area are provided in Table 1.
The works consist of an ROV carrying out visual target investigation for the purposes of identifying potential unexploded ordnance, small excavations on the seabed may also be undertaken to identify targets. There will also be a small amount of debris recovery required depending on what is found during the investigations.
The work is estimated to finish on approximately the 30th of April 2026, subject to weather.
Works are being undertaken under an approved Marine Licence from the Marine Directorate (MS-00011033) and the approved Marine Licence from the Marine Management Organisation (L/2023/00211/2)
There will be no unexploded ordnance detonations performed; this is investigation works only.
See detailed map on our bulletin websiteScottish & Southern Electricity Networks (SSEN) wish to inform Mariners of the completion of marine works in the near-shore area off Warbeth, Orkney which forms part of the Orkney -Caithness HVAC Link Project. As a result two subsea structures are now located on the sea bed and pose a hazard.
Scottish & Southern Electricity Networks (SSEN) wish to inform Mariners of the completion of marine works in the near-shore area off Warbeth, Orkney which forms part of the Orkney -Caithness HVAC Link Project. The completion of this work includes the installation of two subsea assets in the form of two ducts and associated rock bags approx 1km SW of Warbeth Beach, Orkney and have been placed with in the boundaries of the 4 points and associated coordinates detailed in the attached NTM. The works have resulted in a reduction in charted water depth.
Mariners are advised to stay well clear of the area as detailed until further notice.
See detailed map on our bulletin websiteMariners are advised that a subsea survey carried out in 2025 has identified multiple cable exposures along a 120km section the Sofia Export Cable Route. Fishing restrictions therefore continue to apply within the Sofia OWF export cable exclusion boundaries. The Rock Placement vessel 'Seapiper' has commenced remedial works on the Sofia Export Cable.
The Seapiper will work at locations where post cable lay burial operations require an additional level of depth protection.
The vessel will transit directly from the loading quarry in Norway to site and will not use any UK port.
Mariners are requested to remain where possible 500m from vessels and equipment. Fishing vessels are requested to pass at a safe speed and distance.
During these rock placement works the “Seapiper” will be restricted in its ability to manoeuvre as it carries out the rock placement work and shall also be always exhibiting the correct day shapes/lights.
The vessel can be contacted on VHF 16 for further information as required reference proximity/nearby operations etc.
Please note that rock placement will cause a reduction of navigable depth, but this is unlikely to exceed a 10% reduction. The actual positions of rock placement will be updated as part of the as-built information of the project.
Note
At this this time, it is important to note that the cable is sensitive to any external impact and constitutes a SUBSEA SNAGGING RISK for anchoring, fishing gear or other equipment with seabed intervention. Seabed activities should be avoided within the designated area until further notice.
The guard vessel 'Enterprise II' continues monitoring operations within the Sofia Export Cable Corridor between KP4 & KP90 and shall be monitoring VHF 16 during their scope of the works.
See detailed map on our bulletin websiteEssential maintenance works will be taking place at WTGs C02 and A02.
Between the 1st March and the 30th April 2026 (subject to weather delays), mariners must observe an approved safety zone of 500m whenever the Geoquip Elena vessel is carrying out essential maintenance work at WTGs C02 or A02 (see chart provided). A minimum separation distance of 500m is also requested when the vessel is working between these WTG positions or observed manoeuvring into position. Note that the Geoquip Elena shall be considered as limited in manoeuvrability, as defined within the COLREGs (1972).
The Iceni Warrior and Iceni Defiant (CTVs) will be supporting the Geoquip Elena with the maintenance work.
See detailed map on our bulletin websitePlease be advised that Fugro will be conducting Seabed Cone Penetration Tests (CPT) within the Caledonia Offshore Wind Farm Site. The Fugro Revelation will mobilise on the 27th March 2026 and transit to the Caledonia OWF Site will take approximately 3-4 days, weather permitting.
Fugro will conduct Seabed CPT at potential turbine locations within the Caledonia Site Boundary, advancing the cone until refusal is achieved. This is an in-situ test to determine seabed soil properties, and it does not involve any sediment removal. As the aim of the survey relates to potential location of wind turbines, no survey operations will occur within the Structure Exclusion Zone (SEZ) in the south east of the site (please see map in attached NtM).
The Seabed CPT work is part of a larger geotechincal survey campaign that will be undertaken within the Array Area. Details of the subsequent scopes in the campaign, and the vessels undertaking them, will be issued as seperate Kingfisher Notices before they are due to commence.
The NtM has been revised to reflect the new mobilisation date and has been re-uploaded below. Caledonia will issue a Weekly Notice of Operations (WNoO) by email and publish on the Caledonia website each Thursday during periods of active survey operations. If you would like to be added to the distribution list, please contact Caledonia Consents (details below).
See detailed map on our bulletin websiteInspection of Wind Turbine Generator blades, across 11 locations in the North and South fields of Galloper Windfarm.
Galloper Windfarm, RWE - NTM: GWF-O&M 05 – 2026 – WTG Blade Inspections.
Please be advised that Galloper Windfarm will be carrying out WTG Blade Inspections. The campaign will be using the HST Tynemouth/Seacat Liberty/Seacat Mayflower across North and South fields
The vessel will be operating Daytime only, commencing 02/04/2026– weather dependant.
An Exclusion zone of 250 metres will be required whilst the work scope is underway.
See detailed map on our bulletin website
Please be advised that confirmed Unexploded Ordnance can be found at the following locations displayed in section 2.1 for Offshore and 2.2 for Export Cable Route. All vessels are advised to navigate with caution and keep clear of the positions highlighted for EA3 CDM ZONE and EA3 ECR ZONE by a 300m radius.
Mariners are advised that SSE Renewables will be returning to Berwick Bank Wind Farm area to continue geotechnical survey work. The survey will be within the Berwick Bank Wind Farm site boundary.
It should be noted that SSE Renewables are not expecting fishers to relocate gear - on this occasion the vessels will aim to work around any gear on location. A scouting/guard vessel will also be contracted to operate ahead of the survey vessels to ensure that this can be achieved. There will be no towed gear as part of this survey.
The Zenith and Quest (operated by Fugro) will commence operations on 6th April and 25th April, respectively, for a duration of 207 survey days. To account for weather delays and other eventualities, we would like to extend the validity of this notice until 30 November 2026.
The guard vessel will be either the Tranquillity S or the Reaper alternating approximately every 21 days
See detailed map on our bulletin websiteNeuConnect Interconnector Campaign 3 cable lay works began on 9th February 2026 and the UK section of the cable lay was completed on 17th March 2026. Post lay and burial works are still ongoing.
Mariners are advised that cable lay and burial works are due to commence at the NeuConnect UK cable offshore and nearshore at the landfall site on the Isle of Grain, Kent. Works will be conducted by Prysmian PowerLink and supported by their subcontractors.
Installation works are composed of the three operational campaigns: 1. Campaign 1 (C1) – Kilometre Point (KP) 0 – KP 56. 2. Campaign 2 (C2) – KP 56 – KP 199. 3. Campaign 3 (C3) – KP 199 – KP342 (outside UK EEZ Boundary)
Table 1: Estimated schedule of NeuConnect operations in the UK
| Campaign | KP Start | KP End | Coordinates Start (DDM) | Coordinates End (DDM) | Start Date * | End Date * | Status |
| C1 | KP0 | KP56 | Lat 51 27,802'N Long 0 42,724'E | Lat 51 39,214'N Long 1 24, 953 E | 16/09/2024 | 18/11/2024 | Completed |
| C2 | KP56 | KP199 | Lat 51 39,214'N Long 1 24 953 E | Lat 52 23 561 N Long 2 45,833 ' E | 07/07/2025 | December 2025 | Completed |
| C3 | KP199 | KP264 | Lat 52 23,561' N Long 2 45 , 833 E | Lat 52 54,996'N Long 3 10,089 ' E | 03/02/2026 | 17/03/2026 | Completed |
Activities undertaken as part of cable installation works are as follows: • Landfall works • Pre lay • Cable lay (this NtM) • Post lay
All operations require 24-hour working. Cable Lay- C1 Cable lay operations for C1 were completed November 2024. Cable Lay – C2 Cable lay operations for C2 were completed December 2025. Cable Lay – C3 The recovery of cable and joint is to commence on 09 February until 13 February. The cable installation began on 09 February and completed works in UK waters on 17 March 2026. Support vessels may assist with specific tasks. Post lay and burial activities remain ongoing.
Vessels will shelter in Port of Sheerness in the event of weather downtime.
Details of vessels and guard vessel deployment locations are provided in the attached Marine Notice
See detailed map on our bulletin websitePartrac Ltd., on behalf of XOCEAN and Scottish & Southern Electricity Networks (SSEN), is deploying a metocean seabed frame mooring for an interconnector cable project between Holm on the Orkney mainland and the Isle of Burray. Details of the deployment position are provided below in Table 1 and Figure 1, and the frame will be deployed for 30 days.
Partrac Ltd., on behalf of XOCEAN and Scottish & Southern Electricity Networks (SSEN), is deploying a metocean seabed frame mooring for an interconnector cable project between Holm on the Orkney mainland and the Isle of Burray. Details of the deployment position are provided below in Table 1 and Figure 1, and the frame will be deployed for 30 days.
Partrac is planning to carry out the frame deployment within week commencing 9th February 2026 over one day, weather permitting, using the vessel Green Isle (Figure 3). During deployment and recovery activities, the vessel will be restricted in their ability to manoeuvre and will display the appropriate lights and shapes prescribed by the International Regulations for Preventing Collisions at Sea.
Other vessels are requested to provide a minimum clearance of 50m from the installation vessel during operations, and post-installation, and to pass at a safe speed.
Survey Area: Figure 1 below indicates the operational area which is shown by the red boundary. This is outlined in Table 1 below also. The seabed frame position is detailed in Figure 2 with coordinates in Table 2.
See detailed map on our bulletin websiteAll mariners and stakeholders are advised that seabed preparation activities will continue within the Inch Cape Offshore Wind Farm and export cable corridor. N-Sea Pathfinder will join the boulder relocation works.
On behalf of Inch Cape Offshore Ltd, N-Sea will continue seabed preparation activities within the wind farm site boundary and its export cable corridor. Boulder clearance will focus on the wind farm site and the export cable 2 route.
Seabed preparation includes the relocation of any boulders which may affect the installation of offshore structures, inter-array cables and export cables.
The boulder relocation vessel, FS Aries will be joined by N-Sea Pathfinder on or around Wednesday the 19th of March.
See detailed map on our bulletin websiteVessel conducting search & retrieval activities to find & remove the Seabed Frame. This will involve a search area around the last known location. We request marine users to remain 500m away from all assets and ensure fishing gear is at a safe distance to avoid entanglement. MARINERS ARE REMINDED to navigate with caution and keep continued watch on VHF Ch. 70 / 16 when navigating the area.
Last known location of the seabed frame is the deployed location as per coordinates given in this notice. Please ensure fishing gear is at a safe distance to avoid entanglement. Acitivities will commence in November through January 2026, with a weather window expected to allow operations from 17th January 2026. Vessel mobilisation port is expected to be Peterhead Port.
Notice Update 17/03/2026: Vessel Gaoth na Mara (details below) will mobilise from Peterhead Port on 19th March for operations 19th-21st March.
Notice Update 15/01/2026 for vessel details: Vessel is Gaoth na Mara, IMO9679737, vessel bridge mobile +447498176389.
We request marine users to remain 500m away from all assets and ensure fishing gear is at a safe distance to avoid entanglement. MARINERS ARE REMINDED to navigate with caution and keep continued watch on VHF Ch. 70 / 16 when navigating the area.
Note: this notice is a replacemnt for Notice ID5300 which was originally submitted 26th August 2025.
The Seabed Frame search will involve a drop-down camera or ROV for subsea visuals, with a search area around the deployed location. Upon locating the Seabed Frame, retrieval will be undertaken.
See detailed map on our bulletin websitePlease be advised that Aspect Land & Hydrographic Surveys Ltd (on behalf of SHEPD) will be undertaking subsea inspections in the Argyll marine areas. Please refer to Figure 1 - Figure 2 that highlights each cable location.
Please be advised that Aspect Land & Hydrographic Surveys Ltd (on behalf of SHEPD) will be undertaking subsea inspections in the Argyll marine areas. Please refer to Figure 1 - Figure 2 that highlights each cable location.
Given the different conditions and water depths anticipated at each site, a range of vessels will be available for the project, detailed overleaf.
The inspection works will be centred on a 50m cable corridor, defined by the start and end coordinates listed in Table 1.
See detailed map on our bulletin websiteSurvey Activities: XOCEAN is planning the collection of geophysical data using remotely piloted Uncrewed Surface Vessels (USVs) along a proposed cable route corridor in Orkney, from the islands of Sanday to North Ronaldsay.
Survey Activities: XOCEAN is planning the collection of geophysical data using remotely piloted Uncrewed Surface Vessels (USVs) along a proposed cable route corridor in Orkney, from the islands of Sanday to North Ronaldsay. The USVs are expected to operate out of Westray Marina for the full survey duration. A mix of USVs with both hull mounted survey sensors (Multibeam Echosounders & Sub-Bottom Profilers) and also towed sensors (SideScan Sonar & Magnetometer) through the water in proximity of the seabed will be used. A crewed Support Vessel will be chartered throughout the survey to support the USVs with departures and arrivals from Westray Marina and assist in towing them back in if a technical issue occurs.
Dates/Duration: Operations are expected to commence around 20 March 2026. It is expected that the survey activities shall be completed within 30 days (subject to weather).
Fishing Gear Clearance: No fishing gear clearance is presently being requested for these surveys.
Situational Awareness: Although the USVs are uncrewed, they are remotely piloted throughout the 24-hour operation. The USV sends real time images and situational awareness data over satellite to allow this monitoring. The situational awareness aids available are listed below.
See detailed map on our bulletin websiteThe Trinity House Buoy Installation Vessel, Galatea, has installed the Dogger Bank C boundary demarcation buoys in the Southern North Sea.
The 17 construction boundary demarcation buoys will remain in location until the windfarm construction activities have been completed and handed over to the Operations and Maintenance teams.
Once the permanent Aids to Navigation (AtoN) have been installed on the WTGs, Trinity House will approve the permanent AtoN and the boundary buoys will be removed.
If anyone finds a buoy that is off station or encounters a buoy location where it is not functioning or is missing, they should report this to the Dogger Bank Duty Marine Coordinator as soon as possible.
See detailed map on our bulletin websiteThe Offshore Support Vessel, Nora B, will perform the Pre-Lay Grapnel Run operations in Dogger Bank C OWF Inter Array Cable Array Area.
This campaign will commence around 16th March 2026 and continue until approximately 15th of April 2026. The works will be continuous, 24 hours a day. Charts of the DBC array area are provided below.
The operations include a single pre-lay grapnel run over the centre of part of the array cable routes prior to IAC installation by means of a grapnel train to mitigate the risk of encountering subsea obstructions such as discarded fishing gear, wires, etc.
During operations, the Nora B will be restricted in its ability to manoeuvre as defined under COLREGs (International Regulations for Preventing Collisions at Sea 1972) and will display the appropriate day shapes and lights. The vessel will also transmit an Automatic Identification System (AIS) message.
It is requested that all vessels maintain a minimum of 1.5Nm separation distance from the vessel and pass at reduced speed. Fishing gear or other equipment with seabed intervention should not be deployed when approaching the working corridor.
See detailed map on our bulletin websiteResearch Buoy Demobilisation Notification - Morlais Demonstration Zone.
The Marine Characterisation Research Project (MCRP) is an innovative research and development project that will ensure the safe phased deployment of tidal energy turbines in the Morlais Demonstration Zone (MDZ). Working with a team of experts, the project have developed an Environmental Monitoring and Mitigation Plan to safeguard marine wildlife. The findings will be made available for future marine renewable energy projects to enable the growth of tidal stream energy.The aim of the project is to facilitate environmental data collection, and support research and development of turbine centred monitoring and mitigation devices. The knowledge gained will enable the safeguarding of wildlife during the development of the MDZ.To best exploit the opportunity available to gather valuable and relevant information, the MCRP procured a scientific lidar research buoy, upon which the MCRP deployed data collection equipment, in order to gather baseline data from the MDZ and test the equipment.Following a successful refit in the port of Holyhead during November 2024, the Marius buoy has been redeployed in the Morlais zone for a further 18-month period of data collection.As this period of research and development comes to a close, the MCRP wish to notify you of the demobilisation of the Marinus buoy circa early April, weather dependent.
See detailed map on our bulletin websiteMariners are advised that a geotechnical survey is planned for the Eastern Green Link 5 (EGL 5) project. The marine survey activities for EGL 5 are planned to commence on the 23rd of November 2025 and are expected to complete approximately April 2026. This has been updated to include nearshore works in Lincolnshire.
SSEN Transmission and National Grid Electricity Transmission (NGET) are working together to address the need for increased capacity within the transmission network between Scotland and England. EGL5 will help provide increased capacity, carrying up to 2 GW of electricity, enough for two million homes. This will be achieved through a High Voltage Direct Current (HVDC) cable connection between Aberdeenshire and Lincolnshire.
The EGL 5 geotechnical survey works are being carried out by Ocean Infinity Limited.
The area of work, pertaining to this Notice to Mariners (NtM) for EGL 5, is highlighted in Figure 1, with the survey vessels contact details for the project found in Table 1. Contact details for the project Fisheries Liaison Officers are detailed in the attached NtM.
Please note, this survey will be able to operate around static fishing gear. Therefore, fishing gear clearance is not being requested.
Navigational Safety Advice:
Vessels are requested to pass at a safe speed and distance and fishing vessels are advised to remain a safe distance, approximately 550m (0.3 nautical miles) from the areas identified. During these works the vessel will have restricted manoeuvrability as it completes its work scope.
VHF CH 16 will be monitored at all times and will be used to contact the coastguard in the event of an emergency.
The geotechnical survey works are being carried out by Ocean Infinity Limited and Geoforce using the following vessels:
Survey vessel: A7803 (IMO 9924261; MMSI 563175900; Call Sign 9V8529)
Survey vessel: VOE Vanguard (IMO 9809693; MMSI 232008636; Call Sign MEBN9
See detailed map on our bulletin websiteAll mariners and stakeholders are advised that WTG foundation transition piece installation activities shall commence within the Inch Cape site boundary.
On behalf of Inch Cape Offshore Ltd, Seaway 7 shall commence the installation of 54 WTG foundation transition piece components.
The transition pieces will be transported from the Port of Leith to the Inch Cape site and installed by the heavy lift vessel Seaway Alfa Lift.
Alfa Lift is expected to arrive at the Inch Cape site on or around the 17th of March to commence installation which will continue for several months, further details are in the attached notice to mariners.
See detailed map on our bulletin websitePlease be advised that Aspect Land & Hydrographic Surveys Ltd (on behalf of SHEPD) will be undertaking subsea inspections across the Outer Hebrides marine areas.
Please be advised that Aspect Land & Hydrographic Surveys Ltd (on behalf of SHEPD) will be undertaking subsea inspections across the Outer Hebrides marine areas.
Given the different conditions and water depths anticipated at each site, a range of vessels will be available for the project. The inspection works will be centred on a 50m cable corridor.
Vessel Details
The vessel conducting the works will be restricted in its ability to manoeuvre and will display the appropriate lights and shapes.
Other vessels are requested to pass at a safe speed and provide a minimum clearance of 500m (COLREGs Rule 16 & 18) during marine operations.
The vessel will monitor VHF Channel 16 throughout survey operations. Mobile contacts for the vessel are listed at the end of the attached NtM.
See detailed map on our bulletin websiteMariners are advised that the Jack Up Vessels Wind Osprey and Wind Pace will commence Wind Turbine Generator (WTG) installation operations within the East Anglia THREE offshore windfarm area. Marine operations will be conducted by Cadeler A/S and construction operations by Siemens Gamesa Renewable Energy (SGRE). The main working area will be inside the CDM Zone of the wind farm array.
Wind Osprey and Wind Pace will install 95 WTGs
Installed WTGs shall be marked with the following aids to navigation:
Lights
Partially constructed monopiles shall be marked with the following aids to navigation where a transition piece has not been installed:
Lights
Weather permitting, offshore works will be carried out on a continuous basis (i.e. 24-hour working, seven days a week).
During operations, the Wind Osprey and Wind Pace will have restricted manoeuvrability as defined under COLREGS (International Regulations for Preventing Collisions At Sea, 1972). They will display the appropriate day shapes and lights and will transmit an Automatic Identification System (AIS) message.
See detailed map on our bulletin websiteFollowing EGL2 Nearshore UXO TI Campaign along the EGL2 survey corridor, SHET and NGET are advising Mariners of wet storage of a cut length of steel wire rope (SWR) protruding the seabed in the positions listed below. The remainder of the wire is buried beneath the seabed. The wire does not constitute a hazard to general navigation; however, it may present a risk to small vessels when anchoring.
Following EGL2 Nearshore UXO TI Campaign along the EGL2 survey corridor, SHET and NGET are advising Mariners of wet storage of a cut length of steel wire rope (SWR) protruding the seabed in the positions listed below. The remainder of the wire is buried beneath the seabed. The wire does not constitute a hazard to general navigation; however, it may present a risk to small vessels when anchoring.
During a routine inspection of the export cables (ECR A & ECR B) , two sections of the cables were found to be partially exposed through the boulder field. This may constitute a hazard to activities such as fishing and anchoring
It is requested that mariners avoid activities which are likely to disturb the seabed within a 500m Radius of this location until the exposed export cable has been re-investigated. A further Notice to Mariners will be issued to confirm the course of action we will be taking to rectify this. Please note that the standard safety rules apply when fishing in or near wind farms and associated cables. All mariners are requested to make themselves aware of their obligations for conducting activities over buried and protected cables under International and UK Cable (Sub-sea) Protection Legislation.
Mariners are reminded to navigate with caution and keep continued watch on VHF Ch. 12 / 16 when navigating the area. The Marine Coordination Centre will be responsible for monitoring and policing the Safety Zone and can be contacted directly for advice. Further information on the risks to fishing adjacent to subsea cables can be found in Weblinks: www.kis-orca.eu https://www.seafish.org/article/kingfisher-bulletin
See detailed map on our bulletin websiteAll mariners and stakeholders are advised that a Passive Acoustic Monitoring (PAM) mooring array for the purpose of monitoring marine mammals’ detections has been serviced and redeployed along the east coast of Scotland, within 2 km of the coast, between St Andrews Bay and Inverbervie.
All mariners and stakeholders are advised that a Passive Acoustic Monitoring (PAM) mooring array for the purpose of monitoring marine mammals’ detections is currently deployed along the east coast of Scotland, within 2 km of the coast, between St Andrews Bay and Inverbervie.
The PAM array will remain in situ for 2 years (i.e. up to August 2027) with a service interval every 3 months. The moorings will not be surface marked as the top of the mooring extends approximately 4-7m above the seabed.
During a servicing trip on Saturday 21st February, an item has been dropped to the sea during the recovery of the Passive Acoustic Monitoring mooring at Carnoustie, coordinates shown in the attached notice to mariners.
One PAM mooring was redeployed during the service trip on 21 February 2026, locations and coordinates for the passive acoustic monitors currently in place are shown in the attached notice to mariners.
See detailed map on our bulletin websiteUXOControl B.V. will be carrying out UXO Identification operations within the Vanguard East Export Cable Route and Offshore Array location detailed below using the Multi Purpose Offshore Support Vessel Aquarius G complete with Work Class ROV System. The DP2 vessel will be operating through the location, but will remain in position when the ROV is deployed for UXO identification. Only once a location has been finished will the vessel move to the next point.
The Jack-up WTG Installation Vessel, Voltaire, will install wind turbine generators (WTG) within the Dogger Bank B construction area.
The works will commence around the 21st of February 2026 continuing until approximately Q2 2027. The works will be continuous, 24 hours a day. A chart of the DBB construction area boundary coordinates and a table of WTG location coordinates is provided below. A running list of the completed WTG installations and the next locations to be installed is presented in the Weekly Notice of Operations.
During operations, the Voltaire will be restricted in its ability to manoeuvre as defined under COLREGs (International Regulations for Preventing Collisions at Sea 1972) and will display the appropriate day shapes and lights. The vessel will also transmit an Automatic Identification System (AIS) message.
During operations, a Statutory Safety zone of 500m radius will be in place around the Voltaire during the installation of WTGs
See detailed map on our bulletin websiteMariners are advised that Seaway 7 have deployed a Wave Rider Buoy within the East Anglia THREE Offshore Windfarm Area
Seaway 7 deployed a Wave Rider Buoy on the 01/05/2025 within the boundary of the East Anglia THREE Offshore Windfarm Array during the Monopile Noise monitoring campaign as referenced in EA3 NTM 026 - 2025 Monopile Installation (Noise Monitoring Buoy Deployment). The Wave rider Buoy will remain on station until the end of the project.
The Wave Rider Buoy is equipped with a flashing yellow light and has a range of four nautical miles.
Recovery and/or periodic maintenance of the Wave Rider Buoy will be notified via future Notice to Mariners
See detailed map on our bulletin website
Please be advised that Partrac Ltd have completed maintenance on the Northern weather monitoring buoy, installed within the East Anglia Three Offshore Wind Farm Area.
Positions for both North & South weather buoys are identified in the attached Notice To Mariners 005 -2025. There will be periodic maintenance for both weather buoys during construction of EA3.
There is an exclusion zone of 100m around the weather buoys, mariners are advised to abide by the 100m safety zone and navigate with caution at all times.
See detailed map on our bulletin websiteAfter each TP has been installed by the Jack-up Vessel (JUV), Seaway Ventus, Contractor shall perform the TP Completions Scope with the Norside Supporter (CSV), with a delayed start from Seaway Ventus. CSV shall operate on a single 12-hour shift for the duration of the project. ETA For works is Circa 25/04/2025.Bolting and Grouting operations will be conducted by the Norside Supporter within the East Anglia THREE offshore windfarm area.
Norside Supporter Will be Bolting and Grouting 95 monopiles and transition pieces at the WTG locations set out in section 2.2 of this document. It is currently anticipated that weather permitting, offshore works will be carried out on a continuous basis (i.e. 24-hour working, seven days a week)
See detailed map on our bulletin websiteMariners are advised that North Falls Offshore Wind Farm (NFOWF) will undertake a metocean survey within the Wind Turbine Array Area
OverviewMariners are advised that North Falls Offshore Wind Farm (NFOWF) will undertake a metocean survey within the Wind Turbine Array Area, at the Primary and Secondary locations shown in Table 1 and Figure 2.
Survey Duration Mobilisation will commence on or after 18 February 2026, with the metocean survey lasting between 12 and 18months. The planned survey end date will be no later than 16 August 2027.
Survey Tasks The metocean survey work is being undertaken by Partrac, who will use the vessel CT Vector to deploy the metocean equipment at the Primary and Secondary locations shown in Table 1 and Figure 2. It is expected that the deployment operation will last for one day.
The metocean equipment will consist of one seabed frame deployed at each location (i.e., a total of two seabed frames). Each seabed frame will be equipped with an acoustic Doppler current profiler (ADCP) and additional sensors (temperature sensor, water-level sensor, and turbidity sensor). Each seabed frame will be connected to a clump weight, with approximately 100 m leaded polypropylene ground line between the seabed frame and clump weight.
As a consequence of equipment being deployed, all mariners are advised to keep a safe clearance distance of no less than 500 m from the deployment vessel and metocean equipment deployment locations. No towed survey equipment will be deployed from the vessel.
See detailed map on our bulletin websiteCTV - HST Tynemouth supporting service operations over the summer months commencing 1st March 2026
CTV - HST Tynemouth supporting service operations over the summer months commencing 1st March 2026
See detailed map on our bulletin websiteAll Mariners are advised that a service campaign on the infield Demarcation & Met-Ocean Buoys of the SOWF array site is still to commence (vessels still to be confirmed). Mariners are advised of Seabed Met-Ocean Buoy Moorings that remain in place at SOWF (Excluding Buoy) and are yet to be recovered. Note: these locations are to be avoided by at least 200m.
Vessels shall be monitoring channel VHF 16 and shall be displaying the relevant day shapes / night lights when restricted in its ability to manoeuvre.
Mariners are requested to refrain from entering and transiting through the construction area as demarcated by these demarcation buoys.
The table below provides a summary of each Cardinal and Special Mark Buoy deployed at the SOWF array, including target coordinates in WGS84 Degrees Decimal Minutes and a description of top mark and lantern characteristics. The Demarcation Buoys will be deployed for a period of approximately three years.
| Buoy | ID | Latitude | Longitude | Lantern Characteristics | Lantern Colour |
| North Cardinal | N1 | 55° 08.133’ N | 002° 09.518' E |
VQ 0.5s |
White |
| North Cardinal | N2 | 55° 08.436’ N | 002° 13.418’ E |
Q 1s |
White |
| East Cardinal | E1 | 55° 06.480’ N | 002° 16.929’ E |
Q(3) 10s |
White |
| East Cardinal | E2 | 55° 02.571’ N | 002° 23.925' E |
VQ(3) 5s |
White |
| East Cardinal | E3 | 54° 59.043’ N | 002° 30.269’ E |
Q(3) 10s |
White |
| East Cardinal | E4 | 54° 55.085’ N | 002° 26.631’ E |
VQ(3) 5s |
White |
| East Cardinal | E5 | 54° 51.523’ N | 002° 20.709' E |
Q(3) 10s |
White |
| South Cardinal | S1 | 54° 49.725’ N | 002° 16.726' E |
Q(6) + LFL 15s |
White |
| West Cardinal | W1 | 54° 51.829’ N | 002° 12.194' E |
Q(9) 15s |
White |
| West Cardinal | W2 | 54° 56.229’ N | 002° 03.867' E |
VQ(9) 10s |
White |
| West Cardinal | W3 | 55° 00.623’ N | 001° 56.196' E |
Q(9) 15s |
White |
| West Cardinal | W4 | 55° 04.648’ N | 002° 02.498' E |
VQ(9) 10s |
White |
| Special Mark | SP1 | 55° 02.741’ N | 001° 59.265' E |
FI Y 5s |
Yellow |
| Special Mark | SP2 | 55° 06.569’ N | 002° 05.756' E |
FI Y 5s |
Yellow |
| Special Mark | SP3 | 55° 04.525’ N | 002° 20.428' E |
FI Y 5s |
Yellow |
| Special Mark | SP4 | 55° 00.617’ N | 002° 27.418' E |
FI Y 5s |
Yellow |
| Special Mark | SP5 | 54° 56.871’ N | 002° 29.602' E |
FI Y 5s |
Yellow |
| Special Mark | SP6 | 54° 53.324’ N | 002° 23.621' E |
FI Y 5s |
Yellow |
| Special Mark | SP7 | 54° 54.030’ N | 002° 08.026' E |
FI Y 5s |
Yellow |
| Special Mark | SP8 | 54° 58.427’ N | 001° 59.703' E |
FI Y 5s |
Yellow |
The table below provides a summary of the Met-ocean Buoys deployed at the SOWF Array.
| Site Location | Buoy Position | Latitude | Longitude | Lantern Characteristics | Lantern Colour |
| SOWF | OCP | 55° 00.278N | 002° 14.916E | FI(5) Y 20s | Yellow |
| SOWF | Array North | 55° 05.542N | 002° 12.877E | FI(5) Y 20s | Yellow |
| SOWF | Array South | 54° 54.987N | 002° 15.575E | FI(5) Y 20s | Yellow |
| SOWF | Array East | 54° 58.160N | 002° 22.521E | FI(5) Y 20s | Yellow |
| SOWF | Array West | 55° 01.463N | 002° 03.822E | FI(5) Y 20s | Yellow |
The table below provides detail of Seabed Met-Ocean Buoy Moorings that remain in place at SOWF (Excluding Buoy).
| Site Location | Buoy Position | Latitude | Longitude | Note: |
| SOWF | OCP | 55° 00.439' N | 002° 14.798' E | To avoid location by at least 200m |
| SOWF | Array North | 55° 05.392' N | 002° 12.993' E | To avoid location by at least 200m |
| SOWF | Array South | 54° 55.064' N | 002° 14.632' E | To avoid location by at least 200m |
| SOWF | Array East | 54° 58.315' N | 002° 22.609' E | To avoid location by at least 200m |
See detailed map on our bulletin website
Activities related to the development of the Triton Knoll wind farm continue, as detailed below. For background information visit: http://www.tritonknoll.co.uk.
Mariners are advised that the following vessels continue to be active at the Triton Knoll Offshore Wind Farm (TKOWF) as outlined within previously issued NtM's:
|
Vessel Name |
Type |
Call Sign |
MMSI |
IMO |
Operating Port |
Commence Date |
| Windcat 11 | Crew Transfer Vessel | 2BIS9 | 235066459 | N/A | Grimsby | 14/12/2020 |
| Esvagt Havelok | Service Operations Vessel | OYFR2 | 219026496 | 9878981 | Grimsby | 25/09/2021 |
| Njord Amundsen | Support Vessel | ZDSO3 | 236112802 | 1036355 | Grimsby | 10/05/2024 |
|
All vessels can be contacted via VHF channel 16 when operational in field. *** Note *** All 90 WTG's have now been fully installed, whilst WTG commissioning and service continues. All Export Cables are fully installed/buried and need to be deemed live/energised. All Inter Array Cables are fully installed and buried and need to be deemed live/energised. Whilst the main installation works have been completed, major construction commissioning works are continuing. *** Note *** Whilst TKOWFL is reopening the site to fishing from the 14th December 2021, TKOWFL kindly request that all fishermen intending to fish within the boundaries of the Triton Knoll wind farm, contact the Triton Knoll control room prior to entering and exiting the field, and inform them of their fishing intentions This precaution is requested to safeguard all vessels operational at the TKOWF site (including fishing vessels) and your cooperation, to ensure the safety of all parties is appreciated. The following contact details should be used when notifying the Triton Knoll control room of fishing activity: Control Room Manager: Lee Wheat Radio: VHF channel 16 Callsign: TK MCC Phone: +44 1793 896250 Email: tkcr@rwe.com *** Note *** Application of Triton Knoll Wind Farm Safety Zones During Construction The Secretary of State has granted the Application of Safety Zones on the Triton Knoll Wind Farm Project as follows:
|
Mariners are advised that all foundations monopiles have been installed and all inter-array and export cables have been installed.
Navigation Warning - 08th January 2021
Mariners are advised that the remnants of a Wave Rider Buoy sinker weight and partial rigging are located within the Triton Knoll Offshore Wind Farm Construction site at the following location;
53° 30.442N 000° 50.564E
It is advised that the partial rigging could potentially be floating up to 9.7m above the seabed, reducing the navigable safe water in the immediate area to 10m LAT. Mariners are advised to avoid the indicated position by 250 metres.
Possible Dangers to Navigation - Properties of the polypropylene show that the rope is buoyant, this makes the line sensitive for thruster currents. Taking the site water depth into consideration (19.7m LAT) and the maximum expected height above seabed of the rope 9.7m the line is expected to be floating submerged at approximately -10m LAT. In addition, it is noted that over time sediments will be trapped between the fibres and the heavier rope may finally sink. The polypropylene rope may impose a risk to foul propellers / propulsion of vessels due to the buoyant nature of the rope. As the rope is submerged at a depth of ~-10m LAT the risk is considered minimum for vessels with a shallow draught (<5m) and medium for a vessel with a deeper draught (>5m). Over time sediments will be trapped between the fibres and the heavier rope may finally sink thereby reducing the risk to propellers/propulsion of vessels. The clump weight itself (chain) is expected to have sunk into the seabed and has no significant height above seabed. In addition, the edges of the clump weight are mostly rounded (chain), the risk the clump weigh imposes to fishing activities/gear is therefore considered to be minimal.
Navigation Warning - 16th March 2021
Mariners are advised that two UXO targets have been confirmed within the Triton Knoll Offshore Wind Farm Array.
Mariners are advised that the two confirmed targets are located within 20 metres water depth (LAT) and a 10 metre radius exclusion zone is required around each target. The following table provides the coordinates and a description for each target.
| Description of Target | Latitude | Longitude |
Water Depth (LAT) Metres |
Required Exclusion Zone (Metres Radius) |
| Archaeological - The item is thought to be an air-delivered bomb. It appears to be in a stable condition and is resting on the seabed. Marine growth and concretion cover the body, indicating it has been in situ for a significant duration. The tail section of the bomb is missing, which is typical of unexploded bombs from WWII found in these circumstances and there is a significant hole in the case. The dimensions and characteristics gathered are consistent with a 500kg German bomb. Considering the state of the bomb the Net Explosive Quantity of the bomb is likely to be <5kg. | 53°31'50.249"N | 00°47'45.908"E | 20 | 10 |
| Archaeological - The item is thought to be an air-delivered bomb. It appears to be in a stable condition and is resting on the seabed. Marine growth and concretion cover the body, indicating it has been in situ for a significant duration. The tail section of the bomb is missing, which is typical of unexploded bombs from WWII found in these circumstances and there is a significant hole in the case. The dimensions and characteristics gathered are consistent with a 500kg German bomb. Considering the state of the bomb the Net Explosive Quantity of the bomb is likely to be <5kg. | 53°31'49.895"N | 00°47'45.115"E | 20 |
10 |
All mariners and stakeholders are advised that the recently installed temporary navigation light on the P32 monopile has been reported as unlit.
All mariners and stakeholders are advised that the recently installed temporary navigation light on the P32 monopile has been reported as unlit.
See detailed map on our bulletin websiteAll mariners and stakeholders are advised that WTG foundation monopile installation activities will commence within the Inch Cape Offshore Wind Farm.
On behalf of Inch Cape Wind Ltd. Jan de Nul will commence the installation of wind turbine generator foundation monopiles. The monopile components will be transported from the Port of Leith to the Inch Cape site and installed at 54 locations within the wind farm boundary.
The installation vessel Les Alizes is expected to arrive at Inch Cape to commence operations on or around the 25th of December. Each monopile will be installed with a lit temporary navigation structure, the light shall exhibit Flashing (Fl) Yellow (Y) 2.5 seconds (s)
Monopile installation is expected to continue until May 2026.
See detailed map on our bulletin websiteEOLOS intends to deploy a Floating LiDAR buoy (unit FL200 E35) to conduct a measurement campaign at the Morecambe Offshore Wind Farm. The campaign will last between 12 and 24 months, after which EOLOS will recover the buoy along with the entire mooring system.
Mariners are advised that circa between 02/12/2025 and 06/12/2025, the Jack-up Barge (JUB) ‘JB 120’ will commence jacking up next to the East Anglia THREE Offshore Converter Station (OFCS) within the East Anglia THREE Windfarm array.
The jack-up vessel ‘JB 120’ will be positioned next to the East Anglia THREE OFCS within the East Anglia THREE Offshore Windfarm area.
During operations, the ‘JB 120’, ‘CENTAURUS’ (Lead tug), ‘FAIRPLAY 62’ (Assistant tug) and ‘FAIRPLAY 32’ (Assistant tug) will be restricted in their ability to manoeuvre as defined under COLREGs (International Regulations for Preventing Collisions at Sea 1972) and will display the appropriate day shapes and lights. The vessels will also transmit an Automatic Identification System (AIS) message.
A Statutory Safety zone of 500m radius will be in place around the ‘JB 120’ at all times.
‘JB 120’ and supporting tugs are supplied with VHF multi-channel radios and mobile phones.
See detailed map on our bulletin websiteThe Service Operational Vessel, IWS Sun Walker, will carry out Balance of Plant (BoP) and Asset Preservation operations within Dogger Bank C construction site.
The works will be performed in a single campaign, commencing on the 7th of December 2025 and continuing until approximately Q4 2026. The works will be continuous, 24 hours a day. The operations will include visual inspections and remedial maintenance at the Offshore Substation Platform (OSP) and at installed WTG foundation locations. During operations, the IWS Sun Walker will be restricted in its ability to manoeuvre as defined under COLREGs (International Regulations for Preventing Collisions at Sea 1972) and will display the appropriate day shapes and lights. The vessel will also transmit an Automatic Identification System (AIS) message. It is requested that all vessels maintain a minimum of 500m separation distance from the SOV and pass at reduced speed. Fishing gear or other equipment with seabed intervention should not be deployed when approaching the working area.
See detailed map on our bulletin websiteMariners are advised that the Trinity House buoy Installation Vessel ‘Patricia’ has relocated four navigational buoys marking the boundary of the East Anglia THREE Offshore Windfarm.
THV Patricia has relocated the EA3 East 1 Buoy, EA3 East 2 Buoy, EA3 East Buoy 3 and the EA3 Special 3 Buoy marking the boundary of the East Anglia THREE Offshore Windfarm Array.
The demarcation buoys will remain on station throughout construction of the East Anglia THREE Offshore Windfarm.
For futher information regarding East Anglia THREE aids to navigation, please see attached EA3 Notice To Mariners 080- 2025 - Aids To Navigation – Demarcation Buoys.
See detailed map on our bulletin websiteMariners are advised that Emergency Response and Rescue Vessel (ERRV) ‘ESVAGT Carpathia’ is expected to mobilise from the port of Lowestoft. All vessels are requested to keep a 500m safety distance from the ‘ Esvagt Carpathia’ whilst carrying out operations within the East Anglia THREE Offshore Windfarm Array.
The ERRV ‘ESVAGT CARPATHIA’ provides relief duties for standby emergency rescue services during thecommissioning phase of the East Anglia THREE Offshore Converter station (OFCS) ‘EA3 OFCS’. The ESVAGT CARPATHIA will be required to cover these duties when the primary Emergency Response Rescue Vessel 'ESVAGT CARTPATHIA' conducts port calls for crew changes and resupplies.
It is currently anticipated that weather permitting, operations will be carried out on an on-demand basis (i.e.weekly, bi-weekly, ad hoc).Arrival and departure plan of the 'ESVAGT CARTPATHIA' will be notified via the East Anglia THREE Weekly Noticeof Operations.Completion of the 'ESVAGT CARTPATHIA’s' work scope will be notified by closure of this Notice to Mariners.All vessels will continuously monitor VHF Channel 16 and VHF DSC Channel 70 throughout operations.It is currently anticipated that weather permitting, works will be carried out on a continuous 24-hour basis,seven days a week, unless notified otherwise.
See detailed map on our bulletin websitePlease be advised that the crew transfer vessel NR Predator is expected to mobilise from the port of Lowestoft
Crew Transfer Vessel NR Predator will provide assistance during the construction phase of the East Anglia THREE Offshore Windfarm Array and will make regular transits between East Anglia THREE CDM and the ports of Lowestoft and Great Yarmouth.
Outer Thames Estuary Special Protection Area (SPA):
As required under Deemed Marine License Condition 13(1)(c)(v) to minimise disturbance to red throated diver in the Outer Thames Estuary Special Protection Area (SPA) during construction of East Anglia THREE, these areas shall as far as practicable be avoided during transits from 01st November to 31st March.
See detailed map on our bulletin websiteMariners are advised that Emergency Response and Rescue Vessel (ERRV) ‘ESVAGT COBRA’ is expected to mobilise from the port of Lowestoft circa the 03/11/2025.
The ERRV ‘ESVAGT COBRA’ provides standby emergency rescue services during the commissioning phase of the East Anglia THREE Offshore Converter station (OFCS) ‘EA3 OFCS’.
‘ESVAGT COBRA’ will carry out regular transits between East Anglia THREE Windfarm and the port of Lowestoft and is equipped with VHF multi-channel radios and mobile phones.
See detailed map on our bulletin websitePlease be advised that the platform supply vessel ‘BOS PRELUDE’ is expected to mobilise from the port of Emden circa the 02/11/2025. Earliest arrival at East Anglia THREE site circa the 04/11/2025.
The platform supply vessel ‘BOS PRELUDE’ provides supply service during the commissioning phase of the East Anglia THREE Offshore Converter station (OFCS) ‘EA3 OFCS’.
‘BOS PRELUDE’ will deliver supplies to the ‘EA3 OFCS’ and the jack-up vessel ‘JB 120’ (as long as installed next to the OFCS) as well as carry out regular voyages between East Anglia THREE Windfarm and the ports of Emden (Germany, main service port) and Lowestoft (UK) and is equipped with VHF multi-channel radios and mobile phones.
Outer Thames Estuary Special Protection Area (SPA):
As required under Deemed Marine License Condition 13(1)(c)(v) to minimise disturbance to red throated diver in the Outer Thames Estuary Special Protection Area (SPA) during construction of East Anglia THREE, these areas shall as far as practicable be avoided during transits from 01st November to 31st March.
See detailed map on our bulletin websiteReported faults on AIS system, Fog Warning and Aviation lights at Hywind Scotland Windfarm.
Reported faults on AIS system, Fog Sounding Warning and Aviation lights.
Please review attached notice for further information on each item.
HS1 - Failed aviation lighting
HS1 & HS3 - No AIS Signal
HS2 & HS4 - Failed fog sounder
See detailed map on our bulletin website2 x Measurement Systems to be deployed with associated buoyage, mooring & anchoring within Marine Growth Campaign Area. We request marine users to remain 500m away from all assets and expect a mooring excursion radius of ~200m.
Muir Mhòr Offshore Wind Farm Limited will deploy 2 x Measurement Systems to collect data located within a 1.5km x 2.5km area. Once deployed this Notice will be updated with as laid co-ordinates. The campaign is expected to last up to 2yrs.
The works will consist of the deployment of two seperate systems with buoys connected to a mooring line & chain anchored to the seabed with backup recovery line. Please ensure fishing gear is at a safe distance to avoid entanglement. Works will commence in October/November 2025 and the installation vessel will mobilise from Peterhead Port.
Note: this notice is a replacemnt for Notice ID5254 which was originally submitted 18th August 2025.
See detailed map on our bulletin websiteGreen Rebel, on behalf of Magnora Offshore Wind, has deployed a Floating LiDAR (FLS) System buoy and a Directional Wave Rider (DWR) buoy at the Talisk Offshore Wind site, approximately 30km north of the Isle of Lewis for a minimum period of 24 months. The deployment took place on 21 September 2024. Post deployment of the FLS and DWR, service activities be carried out onsite at approximately six-monthly intervals. Additional notice will be provided prior to service activities being undertaken.
Please be advised that the crew transfer vessel ‘NR Hunter’ is expected to mobilise in the port of Lowestoft Circa 15/08/2025
Crew Transfer Vessel NR Hunter will provide assistance during the construction phase of the East Anglia THREE Offshore Windfarm Array and will make regular transits between East Anglia THREE CDM and the ports of Lowestoft and Great Yarmouth. Outer Thames Estuary Special Protection Area (SPA): As required under Deemed Marine License Condition 13(1)(c)(v) to minimise disturbance to red throated diver in the Outer Thames Estuary Special Protection Area (SPA) during construction of East Anglia THREE, these areas shall as far as practicable be avoided during transits from 01st November to 31st March.
It is currently anticipated that weather permitting, operations will be carried out on a continuous basis (i.e. 24-hour working, seven days a week) ‘NR Hunter’ will remain on the project until construction is complete
See detailed map on our bulletin websiteDuring the recovery of a Seawatch Wind LiDAR Buoy (COWF-SWLB075) within the Caledonia Offshore Wind Farm, the mooring system’s clump weight detached and remains on site. Marine users towing demersal gear are advised to maintain a safe clearance distance (500m) from this location.
Clump weight is 2500kg, approximately 0.75m^3 and lies <1m on the seabed.
See detailed map on our bulletin websiteConstruction of the Princess Elisabeth Island. The exclusion zone around the construction site is marked by 4 cardinal buoys (ELI-N, ELI-E, ELI-S and ELI-W).
Transmission system operator Elia is building the Princess Elisabeth Island in the Belgian part of the North Sea. This artificial energy island is an extension of the electricity grid in the North Sea. It connects the future wind farms of the Princess Elisabeth Zone with the Belgian coast and creates new connections with neighbouring countries.
The energy island is built centrally in the Princess Elisabeth wind zone, approximately 45 km from the Belgian coast. Construction of the island will take several years. To ensure safety during the works, the Belgian government defined an exclusion zone within which only work vessels are allowed. This zone is marked by 4 cardinal buoys (ELI-N, ELI-E, ELI-S and ELI-W).
Seabed preparatory works took place in spring and summer 2024. The installation of the caissons started in April 2025 and will proceed untill autumn 2026. During the winter months, no installation works will take place. The exclusion area remains in force at all times.
More information about the Princess Elisabeth Island is available on the Elia website: https://www.elia.be/en/infrastructure-and-projects/infrastructure-projects/princess-elisabeth-island.
See detailed map on our bulletin websiteThis notice describes the current Dogger Bank A and B boundary demarcation buoys in the Southern North Sea
A total of 32 construction boundary demarcation buoys will remain in location until the windfarm construction activities have been completed and handed over to the Operations and Maintenance teams.
Once the permanent Aids to Navigation (AtoN) have been installed on the WTGs, Trinity House will approve the permanent AtoN and the boundary buoys will be removed.
If anyone finds a buoy that is off station or encounters a buoy location where it is not functioning or is missing, they should report this to the Dogger Bank Duty Marine Coordinator as soon as possible.
See detailed map on our bulletin websiteMariners are hereby advised that circa the 01/03/2025 the guard vessel Tess will commence guard duty operations at the East Anglia Three Offshore Windfarm area set out in section 2 of the attached Notice to Mariners.
The guard vessel ‘Tess’ will monitor vessel traffic in and around the East Anglia Three Offshore Windfarm 24hours a day, 7 days a week. The vessel will broadcast regular navigational warnings and will contact any non-project vessels they believe could cause potential hazards, risk of collision, or cause an interruption to project vessels or assets. She will be monitoring VHF Channel 16 and VHF DSC Channel 70 continuously throughout the operaton.
See detailed map on our bulletin websitePlease be advised from circa 1st November 2024 East Anglia Three Offshore Windfarm construction works will commence, subsea boulder and debris clearance operations will be the first construction activity as per the attached NTM document. Followed by Scour protection Installation circa 05th November 2024 as per NTM 050 in attachment.
East Anglia THREE will be a large offshore wind farm, located 69 km off the Norfolk coast. With a projected capacity of approximately 1400MW, the wind farm shall supply electricity to approximately one million UK homes. Onshore construction for the project started in July 2022.
By use of multiple specialized offshore vessels,1 Offshore Convertor station (OFCS) & 95 offshore wind turbine generators (WTGs) will be installed within the East Anglia Three site boundary along with the associated inter array and export cables. The generated power will be transmitted via an installed External Cable (EC) from the OFCS to a shore side substation located in Bramford.
See detailed map on our bulletin websiteTO DOWNLOAD THIS FILE, YOU MUST AGREE TO THE TERMS AND CONDITIONS "TERMS" NOTED AT THE FOOT OF THIS WEBSITE WHICH APPLY TO YOUR USE OF THIS WEBSITE AND TO USE OF THE FILE YOU HAVE CLICKED TO DOWNLOAD. IF YOU DO NOT AGREE TO THE TERMS, YOU WILL NOT BE ABLE TO DOWNLOAD THE FILE AND YOU SHOULD NOT USE THIS WEBSITE. TO CONFIRM YOUR ACCEPTANCE OF THE TERMS AND TO COMMENCE THE DOWNLOAD OF THE FILE, PLEASE CLICK THE "DOWNLOAD" CHECK BOX. IF YOU DO NOT AGREE TO THE TERMS, PLEASE CLICK THE "CANCEL" BUTTON. YOUR ATTENTION IS DRAWN TO CONDITION 3 NOTED BELOW WHICH FORMS PART OF THE TERMS IN RELATION TO OUR LIABILITY TO YOU.
Agree and download Cancel