RWE Renewables UK Wind Ltd at Rampion Windfarm would like to inform mariners that we are carrying out essential maintenance on the wind turbines, this is an updated asset list due to additional repairs being required. This work commenced on 20th May 2025 for 120 days, within the Rampion OWF Area, depending on weather conditions.
RWE Renewables UK Wind Ltd at Rampion Windfarm would like to inform mariners that we are carrying out essential maintenance on the wind turbines, this is an updated asset list due to additional repairs being required.
This work commenced on 20th May 2025 for 120 days, within the Rampion OWF Area, depending on weather conditions.
Start Date: Subject to weather 20th May 2025 For the safety of the working party and anyone in the vicinity of the works, mariners are requested to be vigilant if approaching any of the below listed locations and adhere to a 500m exclusion zone around any locations upon which repairs are being carried out.
See detailed map on our bulletin websitePlease be advised that Spectrum (on behalf of SEPD) will be undertaking a Geophysical Survey acrossa submarine electricity cable corridor in the west of Chichester Harbour. The works will utilise the following vessel to complete survey operations: Spectrum Nyquist The operations will commence during an appropriate weather window following 30/06/2025 and will take place intermittently over a period of 4 weeks, weather permitting
The operations will be undertaken by the Spectrum Nyquist pictured below. The vessels may not commence their activities at the same time but may operate simultaneously at times over the duration of the operation. The vessels may operate primarily from Cowes, Isle of Wight but may use other ports along the Solent coastlines, such as Yarmouth, Lymington, Portsmouth or Poole Harbour.
Survey Description
The survey operations will use the Spectrum Nyquist to acquire data from survey line plan within a corridor around the proposed cable route. An additional larger operational area around the survey area will be utilised for vessel manoeuvring. Other vessels should maintain an appropriate and safe distance of 500 m when passing the survey vessel(s) whilst undertaking operations and should pass at the lowest possible speed to avoid vessel wash effects. The vessel(s) will be working 12-hour operations and will display appropriate day shapes and lights during reduced visibility and night operations. The vessel(s) will also monitor VHF Channels 16 and 12.
Fisheries Liaison Officers
Fishing liaison for the operations will be co-ordinated by Brown & May Marine. For any commercial fishery queries please contact the Company Fishing Liaison Officers (CFLOs) Meg Kalafat at Meg.Kalafat@brownmay.com or +44 7702710176. The local Fishing Industries Representative (FIR) Ian White will also be in place to liaise with the vessels and fishing operations in the area. iannwhite@hotmail.co.uk or +44 7986774725
Legal Notice
Please be advised that this Notice to Mariners should be treated as official notice of the nature, duration and location of the works which are scheduled to take place. During the period of this notice, we request that you plan your activities around our short-term, temporary activities. Entry into the identified location in a manner that would constitute a hazard would be a breach of your duties of safe seamanship as described in the Convention on International Regulations for Preventing Collisions at Sea 1972 and/or the Merchant Shipping Act 1995 and may result in removal of the relevant equipment. Entry into the identified location in a manner that would constitute a hazard may constitute a breach of duty of care at common law, and a failure to protect submarine cables for successful seabed user co-existence
See detailed map on our bulletin websitePlease be advised that there is a section of exposed cable between 51° 21.0462' N, 2° 44.1482' E and 51°19.0035N, 2°46.4372E. Until burial is conducted, there will be a guard vessel (Defender) on site but please ensure vessels proceed with caution. For further information please do not hesitate to get in touch.
Please be advised that there is a section of exposed cable between 51° 21.0462' N, 2° 44.1482' E and 51°19.0035N, 2°46.4372E. Until burial is conducted, there will be a guard vessel (Defender) on site but please ensure vessels proceed with caution. For further information please do not hesitate to get in touch.
See detailed map on our bulletin websiteGreen Volt Offshore Wind Farm Limited will conduct a Geotechnical Survey within the Green Volt array area. The survey will be carried out by the Gardline vessel Horizon Prospector with mobilisation planned on the 1st July 2025 and the survey anticipated to last until the 31st August 2025. The vessel Ocean Vantage will also be on site to assist with CPTs.
This Notice is to inform that the Green Volt Offshore Windfarm Ltd will be carrying out a Geotechnical survey within the Green Volt array area. The survey will be carried out by the Gardline vessel Horizon Prospector with mobilisation planned for the 1 st July 2025 and the survey anticipated to last until the 31st August 2025. The Geotechnical survey will comprise of bore holes and seabed Cone Penetration Tests (CPT) during this period. The vessel Ocean Vantage will also be on site to assist with CPTs.
See detailed map on our bulletin websiteXOCEAN will be conducting a geophysical data survey for a proposed cable route between the Isle of Islay and West Kintyre. The survey, expected to start around 1st July 2025 and last 3-4 weeks (weather permitting), will utilise remotely piloted Uncrewed Surface Vessels (USVs). These USVs will operate out of Lagavulin Bay and will be equipped with both hull-mounted sensors and towed sensors (Sidescan Sonar & Magnetometer) to collect data near the seabed.
Survey Activities: XOCEAN is planning the collection of geophysical data using remotely piloted Uncrewed Surface Vessels (USVs) along a proposed cable route corridor from Isle of Islay to West Kintyre. The USVs are expected to operate out of Lagavulin bay for the full length of survey. A mix of USVs that use both hull mounted survey sensors (Multibeam Echosounders & Sub-Bottom Profilers) and also towed sensors (SideScan Sonar & Magnetometer) through the water in proximity of the seabed will be used. A crewed Support Vessel will be chartered throughout the survey to support the USVs with departures and arrivals from the port and assist in towing them back in if a technical issue occurs.
Dates/Duration: Operations are expected to commence around 1st July 2025. It is expected that the survey activities shall be completed within 3-4 weeks (subject to weather).
See detailed map on our bulletin website
All mariners and stakeholders are advised that unexploded ordnance mitigation and clearance works will commence within the Inch Cape export cable corridor, today Wednesday 18th June.
All mariners and stakeholders are advised that unexploded ordnance mitigation and clearance works will commence within the Inch Cape export cable corridor and wind farm site.
Whilst low order disposal techniques are preferred, high order disposal methodology may be used depending on the condition of individual items.
All mitigation and clearance activities will be conducted from the vessel 4-Winds which will utilise a support rigid inflatable vessel.
The 4-Winds will manage avoidance zones during disposal operations, informing any vessels in the vicinity of operations via VHF radio calls.
4-Winds is expected to commence confirmed unexploded ordnance clearance and mitigation activities today, 18th June
See detailed map on our bulletin websiteGeotechnical and Geophysical investigation on Talacre Beach comprising: o 1 borehole on Talacre Beach at location of HDD exit pit to approx. 30m depth. o Geophysical survey on Talacre Beach at location of HDD exit pit.
Geotechnical testing of the soils including (dependent on what is recovered):
o PSD.
o Atterberg.
o Shear box.
o Triaxial.
o Chemical testing.
Geophysics including:
o Electrical Resistivity.
o Electromagnetism
See detailed map on our bulletin websiteGeophysical UXO Survey between Scotland, Scrabster to Orkney.
NEXANS Orkney Link Pre-Lay Engineering Survey
Geophysical UXO survey will take place on or around 15th May – 15th July from vessel MV Ivero. The vessel will be operating Scotland and Orkney mainland, outside of main shipping channels. Ivero will be RESTRICTED in ability to manoeuvre operating towed survey sensors. Vessel will display RAMs day shapes and appropriate signals informing other vessels in the vicinity. During periods of poor weather, Ivero will port call in Scrabster in times when the vessel cannot remain at sea. The vessel will be listening on VHF Channels 12 and 16 for direct contact.
See detailed map on our bulletin website
During the recovery of a Seawatch Wind LiDAR Buoy (COWF-SWLB075) within the Caledonia Offshore Wind Farm, the mooring system’s clump weight detached and remains on site. Marine users towing demersal gear are advised to maintain a safe clearance distance (500m) from this location.
Clump weight is 2500kg, approximately 0.75m^3 and lies <1m on the seabed.
See detailed map on our bulletin websitePlease be advised of this notice advising mariners of the dredging and repair of Gwynt Y Mor export cable. The Capall Mara will carry out the dredging works and will be assisted by CTV Gladiator. The work will start last week of June/first week of July. The works are scheduled to mid of August subject to weather.
Please be advised of this notice advising mariners of the dredging and repair of Gwynt Y Mor export cable. The Capall Mara will carry out the dredging works and will be assisted by CTV Gladiator. The work will start last week of June/first week of July. The works are scheduled to mid of August subject to weather.
See detailed map on our bulletin websitePlease be advised that Spectrum (on behalf of SEPD) will be undertaking a Geophysical Survey across a submarine electricity cable corridor in the River Medina, Isle of Wight. The works will utilise the following vessel to complete survey operations: Spectrum Nyquist The operations will commence during an appropriate weather window following 30/06/2025 and will take place intermittently over a period of 4 weeks, weather permitting
The operations will be undertaken by the Spectrum Nyquist pictured below. The vessel may operate primarily from Cowes, Isle of Wight but may use other ports along the Solent coastlines, such as Yarmouth, Lymington, Portsmouth or Poole Harbour.
Survey Description
The survey operations will use the Spectrum Nyquist to acquire data from survey line plan within a corridor around the proposed cable route. An additional larger operational area around the survey area will be utilised for vessel manoeuvring. Other vessels should maintain an appropriate and safe distance of 500 m when passing the survey vessel(s) whilst undertaking operations and should pass at the lowest possible speed to avoid vessel wash effects. The vessel(s) will be working 12-hour operations and will display appropriate day shapes and lights during reduced visibility and night operations. The vessel(s) will also monitor VHF Channels 16 and 12
Fisheries Liaison Officers
Fishing liaison for the operations will be co-ordinated by Brown & May Marine. For any commercial fishery queries please contact the Company Fishing Liaison Officers (CFLOs) Meg Kalafat at Meg.Kalafat@brownmay.com or +44 7702710176. The local Fishing Industries Representative (FIR) Ian White will also be in place to liaise with the vessels and fishing operations in the area. iannwhite@hotmail.co.uk or +44 7986774725
Legal Notice
Please be advised that this Notice to Mariners should be treated as official notice of the nature, duration and location of the works which are scheduled to take place. During the period of this notice, we request that you plan your activities around our short-term, temporary activities. Entry into the identified location in a manner that would constitute a hazard would be a breach of your duties of safe seamanship as described in the Convention on International Regulations for Preventing Collisions at Sea 1972 and/or the Merchant Shipping Act 1995 and may result in removal of the relevant equipment. Entry into the identified location in a manner that would constitute a hazard may constitute a breach of duty of care at common law, and a failure to protect submarine cables for successful seabed user co-existence
See detailed map on our bulletin websitePlease be advised that Spectrum (on behalf of SEPD) will be undertaking a Geophysical Survey across submarine electricity cable corridors in the western Solent. The works will utilise the following vessels to complete survey operations: Spectrum 1 Spectrum Nyquist The operations will commence during an appropriate weather window following 30/06/2025 and will take place intermittently over a period of 8 weeks, weather permitting.
The operations will be undertaken by the Spectrum 1 and Spectrum Nyquist. The vessels may not commence their activities at the same time but may operate simultaneously at times over the duration of the operation. The vessels may operate primarily from Cowes, Isle of Wight but may use other ports along the Solent coastlines, such as Yarmouth, Lymington, Portsmouth or Poole Harbour.
Survey Description
The survey operations will use a combination of Spectrum 1 and Spectrum Nyquist vessels. These vessels will acquire data from survey line plan within a corridor around the proposed cable route. An additional larger operational area around the survey area will be utilised for vessel manoeuvring. Other vessels should maintain an appropriate and safe distance of 500 m when passing the survey vessel(s) whilst undertaking operations and should pass at the lowest possible speed to avoid vessel wash effects. The vessel(s) will be working 12-hour operations and will display appropriate day shapes and lights during reduced visibility and night operations. The vessel(s) will also monitor VHF Channels 16 and 12.
Fisheries Liaison Officers
Fishing liaison for the operations will be co-ordinated by Brown & May Marine. For any commercial fishery queries please contact the Company Fishing Liaison Officers (CFLOs) Meg Kalafat at Meg.Kalafat@brownmay.com or +44 7702710176. The local Fishing Industries Representative (FIR) Ian White will also be in place to liaise with the vessels and fishing operations in the area. iannwhite@hotmail.co.uk or +44 7986774725
Legal Notice
Please be advised that this Notice to Mariners should be treated as official notice of the nature, duration and location of the works which are scheduled to take place. During the period of this notice, we request that you plan your activities around our short-term, temporary activities. Entry into the identified location in a manner that would constitute a hazard would be a breach of your duties of safe seamanship as described in the Convention on International Regulations for Preventing Collisions at Sea 1972 and/or the Merchant Shipping Act 1995 and may result in removal of the relevant equipment. Entry into the identified location in a manner that would constitute a hazard may constitute a breach of duty of care at common law, and a failure to protect submarine cables for successful seabed user co-existence
See detailed map on our bulletin website
Please be advised that Spectrum (on behalf of SEPD) will be undertaking a Geophysical Survey across a submarine electricity cable corridor across Hole Bay, Poole Harbour. The works will utilise the following vessel to complete survey operations: Spectrum Nyquist The operations will commence during an appropriate weather window following 30/06/2025 and will take place intermittently over a period of 4 weeks, weather permitting.
The operations will be undertaken by the Spectrum Nyquist pictured below. The vessel may operate primarily from Cowes, Isle of Wight but may use other ports along the Solent coastlines, such as Yarmouth, Lymington, Portsmouth or Poole Harbour.
Survey Description
The survey operations will use the Spectrum Nyquist to acquire data from survey line plan within a corridor around the proposed cable route. An additional larger operational area around the survey area will be utilised for vessel manoeuvring. Other vessels should maintain an appropriate and safe distance of 500 m when passing the survey vessel(s) whilst undertaking operations and should pass at the lowest possible speed to avoid vessel wash effects. The vessel(s) will be working 12-hour operations and will display appropriate day shapes and lights during reduced visibility and night operations. The vessel(s) will also monitor VHF Channels 16 and 12
Fisheries Liaison Officers
Fishing liaison for the operations will be co-ordinated by Brown & May Marine. For any commercial fishery queries please contact the Company Fishing Liaison Officers (CFLOs) Meg Kalafat at Meg.Kalafat@brownmay.com or +44 7702710176. The local Fishing Industries Representative (FIR) Ian White will also be in place to liaise with the vessels and fishing operations in the area. iannwhite@hotmail.co.uk or +44 7986774725
Legal Notice
Please be advised that this Notice to Mariners should be treated as official notice of the nature, duration and location of the works which are scheduled to take place. During the period of this notice, we request that you plan your activities around our short-term, temporary activities. Entry into the identified location in a manner that would constitute a hazard would be a breach of your duties of safe seamanship as described in the Convention on International Regulations for Preventing Collisions at Sea 1972 and/or the Merchant Shipping Act 1995 and may result in removal of the relevant equipment. Entry into the identified location in a manner that would constitute a hazard may constitute a breach of duty of care at common law, and a failure to protect submarine cables for successful seabed user co-existence
See detailed map on our bulletin websitePlease be advised that Spectrum (on behalf of SEPD) will be undertaking a Geophysical Survey across a submarine electricity cable corridor in Poole Harbour. The works will utilise the following vessel to complete survey operations: Spectrum Nyquist The operations will commence during an appropriate weather window following 30/06/2025 and will take place intermittently over a period of 4 weeks, weather permitting.
The operations will be undertaken by the Spectrum Nyquist pictured below. The vessel may operate primarily from Cowes, Isle of Wight but may use other ports along the Solent coastlines, such as Yarmouth, Lymington, Portsmouth or Poole Harbour.
Survey Description
The survey operations will use the Spectrum Nyquist to acquire data from survey line plan within a corridor around the proposed cable route. An additional larger operational area around the survey area will be utilised for vessel manoeuvring. Other vessels should maintain an appropriate and safe distance of 500 m when passing the survey vessel(s) whilst undertaking operations and should pass at the lowest possible speed to avoid vessel wash effects. The vessel(s) will be working 12-hour operations and will display appropriate day shapes and lights during reduced visibility and night operations. The vessel(s) will also monitor VHF Channels 16 and 12
Fisheries Liaison Officers
Fishing liaison for the operations will be co-ordinated by Brown & May Marine. For any commercial fishery queries please contact the Company Fishing Liaison Officers (CFLOs) Meg Kalafat at Meg.Kalafat@brownmay.com or +44 7702710176. The local Fishing Industries Representative (FIR) Ian White will also be in place to liaise with the vessels and fishing operations in the area. iannwhite@hotmail.co.uk or +44 7986774725
Legal Notice
Please be advised that this Notice to Mariners should be treated as official notice of the nature, duration and location of the works which are scheduled to take place. During the period of this notice, we request that you plan your activities around our short-term, temporary activities. Entry into the identified location in a manner that would constitute a hazard would be a breach of your duties of safe seamanship as described in the Convention on International Regulations for Preventing Collisions at Sea 1972 and/or the Merchant Shipping Act 1995 and may result in removal of the relevant equipment. Entry into the identified location in a manner that would constitute a hazard may constitute a breach of duty of care at common law, and a failure to protect submarine cables for successful seabed user co-existence
See detailed map on our bulletin websitePlease be advised that Spectrum (on behalf of SEPD) will be undertaking a Geophysical Survey across a submarine electricity cable corridor across the Poole Harbour. The works will utilise the following vessel to complete survey operations: Spectrum Nyquist The operations will commence during an appropriate weather window following 30/06/2025 and will take place intermittently over a period of 4 weeks, weather permitting.
The operations will be undertaken by the Spectrum Nyquist pictured below. The vessel may operate primarily from Cowes, Isle of Wight but may use other ports along the Solent coastlines, such as Yarmouth, Lymington, Portsmouth or Poole Harbour.
Survey Description
The survey operations will use the Spectrum Nyquist to acquire data from survey line plan within a corridor around the proposed cable route. An additional larger operational area around the survey area will be utilised for vessel manoeuvring. Other vessels should maintain an appropriate and safe distance of 500 m when passing the survey vessel(s) whilst undertaking operations and should pass at the lowest possible speed to avoid vessel wash effects. The vessel(s) will be working 12-hour operations and will display appropriate day shapes and lights during reduced visibility and night operations. The vessel(s) will also monitor VHF Channels 16 and 12
Fisheries Liaison Officers
Fishing liaison for the operations will be co-ordinated by Brown & May Marine. For any commercial fishery queries please contact the Company Fishing Liaison Officers (CFLOs) Meg Kalafat at Meg.Kalafat@brownmay.com or +44 7702710176. The local Fishing Industries Representative (FIR) Ian White will also be in place to liaise with the vessels and fishing operations in the area. iannwhite@hotmail.co.uk or +44 7986774725
Legal Notice
Please be advised that this Notice to Mariners should be treated as official notice of the nature, duration and location of the works which are scheduled to take place. During the period of this notice, we request that you plan your activities around our short-term, temporary activities. Entry into the identified location in a manner that would constitute a hazard would be a breach of your duties of safe seamanship as described in the Convention on International Regulations for Preventing Collisions at Sea 1972 and/or the Merchant Shipping Act 1995 and may result in removal of the relevant equipment. Entry into the identified location in a manner that would constitute a hazard may constitute a breach of duty of care at common law, and a failure to protect submarine cables for successful seabed user co-existence
See detailed map on our bulletin websitePlease be advised that Spectrum (on behalf of SEPD) will be undertaking a Geophysical Survey across a submarine electricity cable corridor in Haslar Lake. The works will utilise the following vessel to complete survey operations: Spectrum Nyquist The operations will commence during an appropriate weather window following 30/06/2025 and will take place intermittently over a period of 4 weeks, weather permitting.
The operations will be undertaken by the Spectrum Nyquist pictured below. The vessel may operate primarily from Cowes, Isle of Wight but may use other ports along the Solent coastlines, such as Yarmouth, Lymington, Portsmouth or Poole Harbour.
Survey Description
The survey operations will use the Spectrum Nyquist to acquire data from survey line plan within a corridor around the proposed cable route. An additional larger operational area around the survey area will be utilised for vessel manoeuvring. Other vessels should maintain an appropriate and safe distance of 500 m when passing the survey vessel(s) whilst undertaking operations and should pass at the lowest possible speed to avoid vessel wash effects. The vessel(s) will be working 12-hour operations and will display appropriate day shapes and lights during reduced visibility and night operations. The vessel(s) will also monitor VHF Channels 16 and 12.
Fisheries Liaison Officers
Fishing liaison for the operations will be co-ordinated by Brown & May Marine. For any commercial fishery queries please contact the Company Fishing Liaison Officers (CFLOs) Meg Kalafat at Meg.Kalafat@brownmay.com or +44 7702710176. The local Fishing Industries Representative (FIR) Ian White will also be in place to liaise with the vessels and fishing operations in the area. iannwhite@hotmail.co.uk or +44 7986774725
Legal Notice
Please be advised that this Notice to Mariners should be treated as official notice of the nature, duration and location of the works which are scheduled to take place. During the period of this notice, we request that you plan your activities around our short-term, temporary activities. Entry into the identified location in a manner that would constitute a hazard would be a breach of your duties of safe seamanship as described in the Convention on International Regulations for Preventing Collisions at Sea 1972 and/or the Merchant Shipping Act 1995 and may result in removal of the relevant equipment. Entry into the identified location in a manner that would constitute a hazard may constitute a breach of duty of care at common law, and a failure to protect submarine cables for successful seabed user co-existence
See detailed map on our bulletin website
Please be advised that Spectrum (on behalf of SEPD) will be undertaking a Geophysical Survey across a submarine electricity cable corridor in the Heavy Reach, Portsmouth Harbour. The works will utilise the following vessel to complete survey operations: Spectrum Nyquist The operations will commence during an appropriate weather window following 30/06/2025 and will take place intermittently over a period of 4 weeks, weather permitting.
The operations will be undertaken by the Spectrum Nyquist pictured below. The vessel may operate primarily from Cowes, Isle of Wight but may use other ports along the Solent coastlines, such as Yarmouth, Lymington, Portsmouth or Poole Harbour.
Survey Description
The survey operations will use the Spectrum Nyquist to acquire data from survey line plan within a corridor around the proposed cable route. An additional larger operational area around the survey area will be utilised for vessel manoeuvring. Other vessels should maintain an appropriate and safe distance of 500 m when passing the survey vessel(s) whilst undertaking operations and should pass at the lowest possible speed to avoid vessel wash effects. The vessel(s) will be working 12-hour operations and will display appropriate day shapes and lights during reduced visibility and night operations. The vessel(s) will also monitor VHF Channels 16 and 12
Fisheries Liaison Officers
Fishing liaison for the operations will be co-ordinated by Brown & May Marine. For any commercial fishery queries please contact the Company Fishing Liaison Officers (CFLOs) Meg Kalafat at Meg.Kalafat@brownmay.com or +44 7702710176. The local Fishing Industries Representative (FIR) Ian White will also be in place to liaise with the vessels and fishing operations in the area. iannwhite@hotmail.co.uk or +44 7986774725
Legal Notice
Please be advised that this Notice to Mariners should be treated as official notice of the nature, duration and location of the works which are scheduled to take place. During the period of this notice, we request that you plan your activities around our short-term, temporary activities. Entry into the identified location in a manner that would constitute a hazard would be a breach of your duties of safe seamanship as described in the Convention on International Regulations for Preventing Collisions at Sea 1972 and/or the Merchant Shipping Act 1995 and may result in removal of the relevant equipment. Entry into the identified location in a manner that would constitute a hazard may constitute a breach of duty of care at common law, and a failure to protect submarine cables for successful seabed user co-existence
See detailed map on our bulletin websitePlease be advised that Spectrum (on behalf of SEPD) will be undertaking a Geophysical Survey across a submarine electricity cable corridor in Poole Harbour. The works will utilise the following vessel to complete survey operations: Spectrum Nyquist The operations will commence during an appropriate weather window following 30/06/2025 and will take place intermittently over a period of 4 weeks, weather permitting.
The operations will be undertaken by the Spectrum Nyquist pictured below. The vessel may operate primarily from Cowes, Isle of Wight but may use other ports along the Solent coastlines, such as Yarmouth, Lymington, Portsmouth or Poole Harbour.
Survey Description
The survey operations will use the Spectrum Nyquist to acquire data from survey line plan within a corridor around the proposed cable route. An additional larger operational area around the survey area will be utilised for vessel manoeuvring. Other vessels should maintain an appropriate and safe distance of 500 m when passing the survey vessel(s) whilst undertaking operations and should pass at the lowest possible speed to avoid vessel wash effects. The vessel(s) will be working 12-hour operations and will display appropriate day shapes and lights during reduced visibility and night operations. The vessel(s) will also monitor VHF Channels 16 and 12.
Fisheries Liaison Officers
Fishing liaison for the operations will be co-ordinated by Brown & May Marine. For any commercial fishery queries please contact the Company Fishing Liaison Officers (CFLOs) Meg Kalafat at Meg.Kalafat@brownmay.com or +44 7702710176. The local Fishing Industries Representative (FIR) Ian White will also be in place to liaise with the vessels and fishing operations in the area. iannwhite@hotmail.co.uk or +44 7986774725
Legal Notice
Please be advised that this Notice to Mariners should be treated as official notice of the nature, duration and location of the works which are scheduled to take place. During the period of this notice, we request that you plan your activities around our short-term, temporary activities. Entry into the identified location in a manner that would constitute a hazard would be a breach of your duties of safe seamanship as described in the Convention on International Regulations for Preventing Collisions at Sea 1972 and/or the Merchant Shipping Act 1995 and may result in removal of the relevant equipment. Entry into the identified location in a manner that would constitute a hazard may constitute a breach of duty of care at common law, and a failure to protect submarine cables for successful seabed user co-existence
See detailed map on our bulletin websitePlease be advised that Spectrum (on behalf of SEPD) will be undertaking a Geophysical Survey across a submarine electricity cable corridor in the Beaulieu River. The works will utilise the following vessel to complete survey operations: Spectrum Nyquist The operations will commence during an appropriate weather window following 30/06/2025 and will take place intermittently over a period of 4 weeks, weather permitting
The operations will be undertaken by the Spectrum Nyquist. The vessel may operate primarily from Cowes, Isle of Wight but may use other ports along the Solent coastlines, such as Yarmouth, Lymington, Portsmouth or Poole Harbour.
The survey operations will use the Spectrum Nyquist to acquire data from survey line plan within a corridor around the proposed cable route. An additional larger operational area around the survey area will be utilised for vessel manoeuvring. Other vessels should maintain an appropriate and safe distance of 500 m when passing the survey vessel(s) whilst undertaking operations and should pass at the lowest possible speed to avoid vessel wash effects. The vessel(s) will be working 12-hour operations and will display appropriate day shapes and lights during reduced visibility and night operations. The vessel(s) will also monitor VHF Channels 16 and 12.
Fishing liaison for the operations will be co-ordinated by Brown & May Marine. For any commercial fishery queries please contact the Company Fishing Liaison Officers (CFLOs) Meg Kalafat at Meg.Kalafat@brownmay.com or +44 7702710176 The local Fishing Industries Representative (FIR) Ian White will also be in place to liaise with the vessels and fishing operations in the are - iannwhite@hotmail.co.uk or +44 7986774725
Legal Notice -
Please be advised that this Notice to Mariners should be treated as official notice of the nature, duration and location of the works which are scheduled to take place. During the period of this notice, we request that you plan your activities around our short-term, temporary activities. Entry into the identified location in a manner that would constitute a hazard would be a breach of your duties of safe seamanship as described in the Convention on International Regulations for Preventing Collisions at Sea 1972 and/or the Merchant Shipping Act 1995 and may result in removal of the relevant equipment. Entry into the identified location in a manner that would constitute a hazard may constitute a breach of duty of care at common law, and a failure to protect submarine cables for successful seabed user co-existence.
See detailed map on our bulletin websiteThe Offshore Service Vessel, MAINPORT GEO, will perform the Pre-Lay Grapnel Run operations in the South of Dogger Bank B OWF Inter Array Cable Array Area.
This campaign will commence around 26th of May 2025 and continue until approximately 31st of May 2025. The works will be continuous, 24 hours a day. Charts of the DBB array area are provided below.
The operations include a single pre-lay grapnel run over the centre of part of the array cable routes prior to IAC installation by means of a grapnel train to mitigate the risk of encountering subsea obstructions such as discarded fishing gear, wires, etc.
During operations, the MAINPORT GEO will be restricted in its ability to manoeuvre as defined under COLREGs (International Regulations for Preventing Collisions at Sea 1972) and will display the appropriate day shapes and lights. The vessel will also transmit an Automatic Identification System (AIS) message.
It is requested that all vessels maintain a minimum of 1.5Nm separation distance from the vessel and pass at reduced speed. Fishing gear or other equipment with seabed intervention should not be deployed when approaching the working corridor.
See detailed map on our bulletin websiteOffshore Construction of the Dogger Bank B Offshore Wind Farm commenced on the 21st of April 2023 with the installation of the OSP jacket foundation. This notice will be updated weekly, giving information on the progress and resources involved in the offshore project. The intention is to give an overview of activities and vessels involved. Should anyone have questions regarding the operations, we kindly ask you to put them forward well in advance.
Dogger Bank B Inter-Array Cable Termination and Testing
The SOV Grampian Derwent and Grampian Tees will continue with IAC Termination and Testing works. All works will be continuous, 24 hours a day. During operations, the Grampian Derwent will be restricted in their ability to manoeuvre as defined under COLREGs (International Regulations for Preventing Collisions at Sea 1972) and will display the appropriate day shapes and lights. The vessel will also transmit an Automatic Identification System (AIS) message.
PLGR
The Offshore Suport Vessel Mainport Geo will carry out Pre-Lay Grapnel Runs (PLGR) on the remaining IA Cables in DBB
See detailed map on our bulletin websiteFall Pipe Vessel (FPV) Rollingstone will continue with subsea rock installation at various locations on DBA
Rollingstone will start operations on 23rd of May 2025 and will perform rock placement during multiple load-outs, finishing her scope around 15th of June 2025. Work will be continuous, 24 hours a day.
During operations, Rollingstone will be restricted in their ability to manoeuvre, as defined under COLREGs (International Regulations for Preventing Collisions at Sea 1972) and will display the appropriate day shapes and lights. The vessel will also transmit an Automatic Identification System (AIS) message.
It is requested that all vessels maintain a minimum of 500m separation distance from the Rollingstone and pass at reduced speed.
See detailed map on our bulletin websiteOffshore Construction of the Dogger Bank C Offshore Wind Farm commenced on the 5th of October 2024. The development of the windfarm is made up of several elements - current ongoing elements are described below in the 'full notice' and in the attached file. This notice will be updated weekly, giving information on the progress and resources involved in the offshore project.
Monopile Installation
The Offshore installation vessel, HLV Seaway Strashnov, will install mono-pile foundations in the Dogger Bank C offshore windfarm construction area, commencing on the 22nd April 2025, continuing until approximately Q4 2025. The works will be continuous 24 hours a day.
The installed monopiles will be marked with temporary lighting with the following characteristics:
• Flashing (Fl) Yellow (Y) 2.5 seconds (s)
• IALA Availability Category 2 (not less than 99.0%)
• 360° visibility – up to two lights per structure may be used to achieve this
• At least 2 nm range.
During operations, the HLV Seaway Strashnov will be restricted in ability to manoeuvre as defined under COLREGs (International Regulations for Preventing Collisions at Sea 1972) and will display the appropriate day shapes and lights. The vessels will also transmit an Automatic Identification System (AIS) message.
OSP Commissioning works
The Dogger Bank C Offshore Substation Platform (OSP) will undergo a Commissioning phase within the Dogger Bank C construction area. The Jack up Vessel (JUV) HEA Hydra will jack up and connect to the DBC OSP by a fixed gangway. The HEA Hydra will remain on site during the Commissioning phase, acting as the accommodation platform and OSP emergency evacuation vessel.
The works will commence on approximately the 15th of May 2025, continuing until approximately 11th of September 2025. The works will be continuous 24 hours a day. A chart of the DBC construction area and the installation location is provided below.
During operations, a Statutory Safety zone of 500m radius will be in place around the HEA Hydra for the duration of the Commissioning phase of the DBC OSP. Vessels are requested to maintain a minimum safe passing distance of 1km from the HEA Hydra during the operation.
The Platform Supply Vessel (PSV) FS Balmoral will support the HEA Hydra, carrying out regular supply runs to the offshore site.
During the Commissioning phase, there will be a requirement for rope access works to be carried out to the external parts of the OSP and Jacket. During these Over the Side (OTS) works the Dogger Bank OWF Guard vessel Jacobus will act as the Emergency Response Rescue Vessel (ERRV).
See detailed map on our bulletin website
Mariners are advised that Orsted Hornsea Project Three (UK) Limited (hereafter ‘Orsted’) will be commencing seabed preparation works for Hornsea Project Three Offshore Wind Farm (‘Hornsea Three’), located within the UK Sector of the North Sea.
Seabed Preparation Survey:
Mariners are advised that Orsted have completed a bathymetric survey for the purpose of seabed preparation works for the Hornsea Three Export Cable Route (ECR), located within the UK Sector of the North Sea.
Boulder and Debris Relocation Works:
Mariners are advised that Orsted will be commencing boulder and debris relocation to support seabed preparation works for the Hornsea Three ECR on 15th June 2025.
See detailed map on our bulletin websiteOffshore Construction of the Dogger Bank A Offshore Wind Farm commenced on the 18th of March 2022. The development of the windfarm is made up of several elements - current ongoing elements are described below in the 'full notice' and in the attached file. This notice will be updated weekly, giving information on the progress and resources involved in the offshore project.
The development of the windfarm is made up of several elements - current ongoing elements include:
Construction Support Activities
The Offshore Construction Support Vessels Boreas Enabler, IWS Skywalker, IWS Starwalker, Grampian Tweed and Grampian Tyne will carry out construction support activities within Dogger Bank A construction site.
Wind Turbine Generator (WTG) Installation
The Jack-up WTG Installation Vessel, Voltaire, will install wind turbine generators (WTG) within the Dogger Bank A construction area. the Voltaire has completed scheduled maintenance and has returned to WTG Installation operations.
The works commenced on the 18th of July 2023, continuing until approximately Q4 2025. The works will be continuous, 24 hours a day. A running list of the completed WTG installations and the next locations to be installed is presented in the Installation progress table in the WNoO.
Rock Armour installation The fall pipe vessel, Rollingstone, will perform seabed rock armour installation at various WTG foundation locations in the DBA construction site. Work will start on approx. 24th May 2025.
See detailed map on our bulletin website
NEXANS on behalf of SSEN will be undertaking Geophysical Survey as part of the Orkney HVAC Project - between Warbeth, Orkney and Dounreay, Caithness.
The Geophysical UXO survey will take place on or around 15th May – 15th June from vessel MV Ivero. The vessel will be operating Scotland and Orkney mainland, outside of main shipping channels.
Ivero will be RESTRICTED in ability to manoeuvre operating towed survey sensors. Vessel will display RAMs day shapes and appropriate signals informing other vessels in the vicinity. During periods of poor weather, Ivero will port call in Scrabster in times when the vessel cannot remain at sea.
The vessel will be listening on VHF Channels 12 and 16 for direct contact.
See detailed map on our bulletin websiteMariners are advised that circa the 25/06/2025, Geosurveyor XI will conduct a Pre-Installation Survey Campaign within the East Anglia THREE Offshore Windfarm area
GeoXYZ will utilise the ‘Geosurveyor XI' to perform a Pre-Installation Survey within the East Anglia THREE Offshore Windfarm.
The vessel will conduct Multibeam Echo Sounder (MBES) and Side Scan Sonar (SSS) surveys of the WTG foundation locations where monopiles are not yet installed, at a radius of 170m.
The Geosurveyor XI will also conduct a Multibeam Echo Sounder survey along the Inter Array Cable route.
Geosurveyor XI is expected to mobilize from the port of ‘Lowestoft’ circa the 25/06/2025. It is anticipated that the campaign will last approximately 8 days, the end of the campaign will be communicated by closure of this notice to mariners.
See detailed map on our bulletin websitePlease find attached an updated Notice to Mariners (NtM_EGL2_PHN_001_20250520). The purpose of this (NtM) is to outline the working area for the survey vessels, as well as the scope of work.
Geophysical Survey (English Nearshore) |
From 28/05/2025 to 30/05/2025 (For Validus)
And
From 27/06/2025 to 11/07/2025 (For AMS Spirit)
|
Geophysical survey to evaluate underlying geology. The vessels will be towing a system of about 100m at or just below the surface. The survey will be running lines in the survey areas at about 3knots. |
Please find attached an updated Notice to Mariners (NtM_EGL2_PHN_002_20250611). The purpose of this (NtM) is to outline the working area for the survey vessels, as well as the scope of work.
Geophysical survey to evaluate the underlying geology. The vessels will be towing a system of about 100m at or just below the surface. The survey will be running lines in the survey areas at about 3knots.
From 22/05/2025 to 24/05/2025 (For Validus)
And
From 23/06/2025 to 09/07/2025 (For AMS Spirit)
|
Mariners are advised about Nearshore UXO Target investigation Diver works for the Eastern Green Link 2 Project.
The dive operations for EGL 2 are due to commence on 16th of June 2025. The works are to be conducted within the 6-off zones shown by Figure 1, and updated coordinates are detailed in Table 1, both given below. The works consist of Divers carrying out target investigation for the purposes of identifying potential unexploded ordnance. There will also be a small amount of debris recovery required depending on what is found during the investigations.
The work is estimated to take approximately 25 days, finishing on approximately the 11th of July 2025, subject to weather.
Works are being undertaken under an approved Marine Licence from the Marine Management Organisation (MMO) (L/2023/00211/2); the local MMO enforcement and compliance team are aware of the planned EGL2 survey work.
There will be no unexploded ordnance detonations performed; this is investigation works only. There will a Crew Transfer Vessel being utilised, shown in Table 2.
See detailed map on our bulletin website
From around 19th June 2025 for approx14 days (weather permitting), the Kingdom of Fife will commence service and inspection of the installed buoyage within the SOWF Array and within the Export Cable Route, as per the locations provided below. In addition, the Met-ocean Buoys in position at KP8 & KP130 on the Export Cable Route will be permanently recovered. Mariners are requested to refrain from entering and transiting through the construction area as demarcated by these demarcation buoys.
The Kingdom of Fife shall be monitoring VHF 16 during the scope of the works and shall also be exhibiting the correct day shapes and night lights for a vessel restricted in ability to manoeuvre.
The table below provides a summary of each Cardinal and Special Mark Buoy deployed at the SOWF array, including target coordinates in WGS84 Degrees Decimal Minutes and a description of top mark and lantern characteristics. The Demarcation Buoys will be deployed for a period of approximately three years.
Buoy | ID | Latitude | Longitude | Lantern Characteristics | Lantern Colour |
North Cardinal | N1 | 55° 08.133’ N | 002° 09.518' E |
VQ 0.5s |
White |
North Cardinal | N2 | 55° 08.436’ N | 002° 13.418’ E |
Q 1s |
White |
East Cardinal | E1 | 55° 06.480’ N | 002° 16.929’ E |
Q(3) 10s |
White |
East Cardinal | E2 | 55° 02.571’ N | 002° 23.925' E |
VQ(3) 5s |
White |
East Cardinal | E3 | 54° 59.043’ N | 002° 30.269’ E |
Q(3) 10s |
White |
East Cardinal | E4 | 54° 55.085’ N | 002° 26.631’ E |
VQ(3) 5s |
White |
East Cardinal | E5 | 54° 51.523’ N | 002° 20.709' E |
Q(3) 10s |
White |
South Cardinal | S1 | 54° 49.725’ N | 002° 16.726' E |
Q(6) + LFL 15s |
White |
West Cardinal | W1 | 54° 51.829’ N | 002° 12.194' E |
Q(9) 15s |
White |
West Cardinal | W2 | 54° 56.229’ N | 002° 03.867' E |
VQ(9) 10s |
White |
West Cardinal | W3 | 55° 00.623’ N | 001° 56.196' E |
Q(9) 15s |
White |
West Cardinal | W4 | 55° 04.648’ N | 002° 02.498' E |
VQ(9) 10s |
White |
Special Mark | SP1 | 55° 02.741’ N | 001° 59.265' E |
FI Y 5s |
Yellow |
Special Mark | SP2 | 55° 06.569’ N | 002° 05.756' E |
FI Y 5s |
Yellow |
Special Mark | SP3 | 55° 04.525’ N | 002° 20.428' E |
FI Y 5s |
Yellow |
Special Mark | SP4 | 55° 00.617’ N | 002° 27.418' E |
FI Y 5s |
Yellow |
Special Mark | SP5 | 54° 56.871’ N | 002° 29.602' E |
FI Y 5s |
Yellow |
Special Mark | SP6 | 54° 53.324’ N | 002° 23.621' E |
FI Y 5s |
Yellow |
Special Mark | SP7 | 54° 54.030’ N | 002° 08.026' E |
FI Y 5s |
Yellow |
Special Mark | SP8 | 54° 58.427’ N | 001° 59.703' E |
FI Y 5s |
Yellow |
The table below provides a summary of the Met-ocean Buoys deployed at the SOWF Array.
Site Location | Buoy Position | Latitude | Longitude | Deployment Date | Recovery Date |
Export Cable | KP8 | 54 36.584N | 000 54.674W | June 2023 | Will be recovered permanently |
Export Cable | KP130 | 54 50.543N | 000 54.689E | June 2023 | Will be recovered permanently |
SOWF | Array North | 55° 05.392' N | 002° 12.993' E | June 2023 | June 2026 |
SOWF | Array South | 54° 54.987' N | 002° 15.585' E | June 2023 | June 2026 |
SOWF | Array East | 54° 58.160' N | 002° 22.521' E | March 2024 | June 2026 |
SOWF | Array West | 55° 01.528' N | 002° 04.052' E | March 2024 | June 2026 |
SOWF | OCP | 55° 00.439' N | 002° 14.798' E | March 2024 | June 2026 |
See detailed map on our bulletin website
Mariners are advised that Seaway 7 have deployed a Wave Rider Buoy within the East Anglia THREE Offshore Windfarm Area
Seaway 7 deployed a Wave Rider Buoy on the 01/05/2025 within the boundary of the East Anglia THREE Offshore Windfarm Array during the Monopile Noise monitoring campaign as referenced in EA3 NTM 026 - 2025 Monopile Installation (Noise Monitoring Buoy Deployment). The Wave rider Buoy will remain on station until the end of the project.
The Wave Rider Buoy is equipped with a flashing yellow light and has a range of four nautical miles.
Recovery and/or periodic maintenance of the Wave Rider Buoy will be notified via future Notice to Mariners
See detailed map on our bulletin website
To support the development of the Mona Offshore Wind Project, Mona Offshore Wind Limited will undertake geophysical surveys within the proposed Mona Landfall Survey Area (Figure 1 of the attached NtM). Weather permitting, works will begin on 13 June 2025 and conclude with demobilisation on 19 June 2025, using the survey vessel Fugro Valkyrie (See Section 6 of the attached NtM for survey vessel details).
Survey scope: • Multibeam echosounder (MBES, hull-mounted): Norbit Winghead dual-head • Side-scan sonar (towed): Edgetech 4205 • Magnetometer (towed): Geometrics G-882 The vessel will operate around local tides, conducting 12-hour daily shifts and returning to Mostyn each day.
An Offshore Fisheries Liaison Officer (OFLO) will not be on board; however, the Project Fishing Industry Representative (FIR) and Company Fisheries Liaison Officer (CFLO) are available to address any enquiries. Contact details for the FIR and CFLO are provided below.
In addition to the main survey works, infield calibration activities will be undertaken by the survey vessel Fugro Valkyrie on Saturday 14 June and Sunday 15 June 2025. These calibration operations will occur outside of the proposed Mona Landfall Geophysical Survey Area, within two separate calibration areas shown in Figure 1.
Coordinates of these dedicated calibration area are provided in Table 2.
These calibration operations form part of standard survey preparation and will be completed ahead of the planned geophysical survey operations within the Mona Landfall Geophysical Survey Area.
See detailed map on our bulletin websitePlease be advised that Seiche Limited have performed a service on the 12 Passive Acoustic Monitoring (PAM) Stations that have been deployed on the seabed, in and at locations around the East Anglia THREE Offshore Windfarm area. An additional five Passive Acoustic Monitoring stations have also been deployed. As Detailed in NTM 035 - 2025
Service of the 12 Passive Acoustic Monitoring (PAM) stations that have been deployed on the sea bed, in and at locations around the East Anglia THREE Offshore Windfarm Area.
There is an exclusion zone of 250m around each PAM station, all marine traffic is advised to abide by the 250m safety zone and navigate with caution at all times.
An additional 5 PAM stations have been deployed in positions found in the attached NTM 035-2025.
For further information regarding PAM station , please see attached East Anglia Three Notice To Mariners 035 - 2025.
See detailed map on our bulletin websiteAll mariners are advised that nearshore export cable civils works will commence at the Inch Cape export cable landfall site today, 12th June. The tender Torc will proceed to the work site and deploy two demarcation buoys. The barge Cliodna will be towed from Leith to Cockenzie on Sunday or Monday.
The works will consist of the excavation of 2 cable trenches and the installation of 2 stainless steel export cable ducts, once the ducts are installed the trenches shall be backfilled. Two buoys shall be temporarily deployred to delineate the work site. These works shall include diving operations, please see attached Notice to Mariners for further information.
See detailed map on our bulletin websiteSeafox 7 remains jack up alongside and supporting the comissioning of the Offshore Converter Platform.
A scheduled service from an assigned pool of Platform Supply Vessels providing supplies to the Offshore Converter Platform & JUV until further notice. Those nominated vessels are:
All vessels will be arriving from non UK Ports throughout.
An eight legged jacket with 8 driven pin piles has been installed as a foundation for the OCP followed by the OCP itself.
The Sofia Offshore Wind Farm Boundary Co-ordinates where the works will take place are provided below. All non-project vessels are requested to remain outside this area.
Mariners are requested to remain where possible 500m from vessels. During these works, SOVs will have restricted manoeuvrability and shall also be exhibiting the correct day shapes/ lights and flag for vessels engaged in diving operations and restricted in ability to manoeuvre.
Emergency Response & Rescue Vessel
The EERV Putford Protector is supporting the commissioning phase of the Offshore Converter Platform, providing close standby cover as required during overside works.
Service Operation Vessels
The Service Operations Vessel (SOV) “Rem Power” & Daughter craft “Rem Transporter” continues to support the SOWF project throughout the construction of the offshore windfarm.
SOVs shall be transiting to / from the Sofia Array and the port of Blyth / Sunderland throughout this period.
Crew Transfer Vessel
The Crew Transfer Vessel (CTV) “MHO Balder” commence operations at the Sofia OWF.
All vessels can be contacted on VHF 16 for further information as required reference proximity / nearby operations etc.
See detailed map on our bulletin websiteGlobal Marine are due to conduct the installation of the Q&E South telecommunications cable from Newhaven UK to Cayeux-Sur-Mer, France. Subject to progress on the North route the cable lay operations are expected to commence from the UK end at the beginning of June. All operations, with the exception of work in French TW, expected to be completed by mid July 2025. Timings are dependent upon weather and other operational conditions. Further details can be found in the attached NtM.
The vessels will be limited in manoeuvrability therefore, vessels working in the area should proceed with caution and alert the vessel within 1NM from the cable ship during operations and all activity should remain clear 250m either side of the vessel, 500m corridor in total.
For a further breakdown of operations, please don't hesitate to get in touch.
See detailed map on our bulletin websiteMetocean instrumentation and a floating LiDAR system (FLS) will be demobilised from the Muir Mhòr Offshore Wind Farm Project site during June / July 2025. This is a preliminary notice and will be updated once vessel and port details are available. MARINE USERS are requested to maintain a safe clearance distance of 500m from all assets.
Moray Offshore Windfarm (West) Limited (Moray West) are planning to commence subsea Remotely Operated Vehicle (ROV) repairs on the export cable from OSP1
Please be advised that Moray Offshore Windfarm (West) Limited (Moray West) are planning to commence subsea Remotely Operated Vehicle (ROV) repairs on the export cable from OSP1, which is expected to take no longer than 3 days. The area of Operation is shown in Figure 1 below and will be carried out using the Deep Cygnus vessel. Work is scheduled to start in week 28 (7th July 2025), with operations dependent to weather conditions on site.
See detailed map on our bulletin websiteDuring unexploded ordnance identification and mitigation works, several items of confirmed unexploded ordnance have been located.
Several confirmed unexploded ordnance items have been located during unexpoloded ordnance identification and mitigation works.
Inch Cape will promulgate any relocation, or disposal plans in due course, if further information is required, please contact the Duty Marine Coordinator on the number above.
See detailed map on our bulletin websiteMariners are advised that Berwick Bank Offshore Wind Farm (BBOWF) will undertake further geophysical survey assessments within export cable route areas.
Whilst the vessel will tow survey equipment, BBOWF do not require fishing gear to be relocated and can operate around static fishing gear present within the survey area.
Survey Duration
The survey is anticipated to commence 26 May 2025 (+/- 2 days pending vessel availability), and will involve 7 days total of operational survey time. To account for weather delays and all eventualities we would like to extend the validity of this notice to 31 July 2025. The survey will be undertaken by an X-Ocean USV. A support vessel will escort the USV from the active ports to clear water. Please note that although the vessel is uncrewed, it will be piloted remotely using 360 degree cameras and other navigational aids. Vessel details are included within the attached Notice to Mariners document.
Survey Tasks
The surveys involve deployment of:
Multi Beam Echosounder;
Sub-bottom profiler;
Magnetometer;
Ultra-short Baseline; and,
Sub-bottom Profiler.
All mariners are advised to keep a safe clearance distance of no less than 500m from the vessel.
See detailed map on our bulletin websitePlease be advised that Galloper Windfarm will be carrying out full blade inspections of the wind turbines. The campaign will be using the OTS CTV, Captain P, across both the North and South Fields. The vessel will be operating during daytime only, commencing 1st July 2025 for 10 days – weather dependant. An Exclusion zone of 250 metres will be required whilst the work scope is underway. Vessel: Captain P call sign: 2FSO5
Please be advised Galloper Windfarm will be carrying out a bathymetric survey campaign as part of our planned maintenance and inspection programme. The campaign will be using the Njord Survey Vessel, M/V Northern Storm, across both the North and South Fields. The vessel will be operating during daytime only, commencing 30th June 2025 for approximately 10 days – weather dependent.
An Exclusion zone of 500 metres will be required around the vessel whilst the work scope is underway. Vessel : M/V Northern Storm Call Sign: MISA7
See detailed map on our bulletin websiteRWE Renewables UK Wind Ltd at Rampion windfarm would like to inform mariners that we are carrying out the essential works to replace a faulty cable within the Rampion OWF Area over the course of 21 days, depending on weather conditions. If works continue past this date, a supplementary Notice to Mariners will be released.
Works will be between turbine F04 and the Offshore Substation (OSS). Teams will mobilise on 17th June with works beginning 19th June. The work involves; de-burial and removal of existing cable, relaying of the new cable in the existing trench (or as close as practicable). The works are expected to take until the 10th of July depending on weather conditions. The current outline planning is as follows: Start Date: Subject to weather 17th June 2025.
For the safety of the working party and anyone in the vicinity of the works, mariners are requested to be vigilant if approaching the below listed locations and stay outside of 250m from the works operations at all times. Once the as-laid location of the cable is determined, it will be communicated to mariners through appropriate channels for updating on charts and plotters.
See detailed map on our bulletin website
This Notice is to inform that the Green Volt Offshore Windfarm Ltd will be carrying out a Geotechnical survey within the Green Volt array area. The survey will be carried out by the Gardline vessel Kommandor Susan with mobilisation planned for the 15th of April and the survey anticipated to last until the 25th of May. The Geotechnical survey will comprise of bore holes and Cone Penetration Tests (CPT) during this period.
This Notice is to inform that one of the Green Volt Offshore Windfarm Ltd floating metocean devices (Triaxys wave buoy) broke free from its moorings on 23rd July 2024 due to being dragged by a passing vessel. Marine users should be aware that the Triaxys wave buoy’s mooring system, including the two floats remain on site and unmarked. The buoy itself has been recovered and relocated. The coordinate provided is the the last known location of the mooring.
The mooring system consists of a 15 m rubber cord, a 60 mm polypropylene rope, two floats, another 80 m of polypropylene rope attached to bottom chains (see Figure 2). Marine users should maintain a recommended 500 metre safe clearance distance from the buffer area shown in Figure 1 due to the risk of snagging or propellor fouling. Updates will be issued via a revised Notice to Mariners when available.
UPDATE: Further updates on recovery attempts will be issued via a revised Notice to Mariners when available.
See detailed map on our bulletin websiteThe Cable Laying Vessel (CLV) “Calypso” continues with Inter-Array Cable operations within the Sofia Offshore Windfarm Array. The exact finish date will be dependent on the prevailing weather conditions and work progress. Note: Vessel departed the project during this period and will be replaced by the “Boka Ocean” on or around the 10th June 2025. All Mariners are advised that the SOV “Dos Notus” is expected to commence infield operations later in June 2025.
The Subsea Viking continues supporting the Inter Array Cable Installation works via Survey, Cable Burial, Rock Bag Installation Works, as required.
Service Operation Vessels
The Service Operations Vessel (SOV) “Rem Power” & Daughter craft “Rem Transporter”, Acta Centaurus (W2W) and Vestri Enabler (W2W) continues to support to the SOWF project throughout the construction of the offshore windfarm.
SOVs Acta Orion and Olympic Orion continue to support Inter Array Cable / prepping and termination works.
All vessels can be contacted on VHF 16 for further information as required reference proximity / nearby operations etc.
Vessels shall be transiting to / from the Sofia Array and the ports of Blyth & Sunderland throughout this period.
Crew Transfer Vessel
The Crew Transfer Vessel (CTV) “MHO Balder” continues operations at the Sofia OWF.
Mariners are requested to remain where possible 500m from these vessels, as they will have restricted manoeuvrability and shall also be exhibiting the correct day shapes/ lights.
See detailed map on our bulletin websiteAll Mariners are advised that the SGRE Vessel “Wind Peak” continues Wind Turbine (WTG) Generator installation at the Sofia Array. The vessel will also be supported by ongoing commissioning activities carried out with the following SGRE Vessels: “IWS SeaWalker”, “FOB Swath 9” & “FOB Swath 10”.
The following table highlights WTG installation progress and next 7 day forecast.
Total WTGs Installed (100 in Total) |
WTGs Installed (Since Previous Update) | WTGs Location Forecast (Next 7 Days) |
18 | N09, S07 | U03, S05, Q05, T01, S01, N07 |
Vessels operational during these works are as follows:
Vessel Name | Vessel Type | Length (M) | Gross Tonnage | IMO | Call Sign | MMSI Number |
Wind Peak | WTG Installation Vessel | 150 | 34100 | 9957828 | OZVU2 | 219032994 |
IWS Seawalker | Service Operation Vessel | 90 | 6712 | 9968580 | LAVP8 | 257784000 |
FOB Swath 9 | Crew Transfer Vessel | 33 | 372 | 9920576 | OYKP2 | 219027989 |
FOB Swath 10 | Crew Transfer Vessel | 32 | 372 | 9920588 | OYMX2 |
219027988 |
The exact finish date will be dependent on the prevailing weather conditions and work progress. Mariners are requested to remain where possible 500m from Construction vessels when exhibiting the day shapes / night lights for vessels restricted in their manoeuvrability.
Service Operation Vessels
The Service Operations Vessels (SOV) “Rem Power” & Daughter craft “Rem Transporter” continues to support to the SOWF project throughout the construction of the offshore windfarm.
SOVs shall be transiting to / from the Sofia Array and the port of Blyth / Sunderland throughout this period.
All vessels can be contacted on VHF 16 throughout as required. All vessels shall be operating to / from the Port of Hull and will be operational 24 hours / day.
See detailed map on our bulletin website
The Wind Turbine Installation Vessel 'Aeolus' continues with Foundation Installation Works within the array site. The Noise Abatement (Big Bubble Curtain) Vessel “SAR Odin” continues supporting Aeolus foundation installation works. Mariners are advised that the Service Operations Vessel (SOV) “Dos Notus” are expected to commence infield operations in late June 2025.
Foundation Installation Works (Aeolus)
The Aeolus has commenced the Offshore Foundation Transport and Installation works within the Sofia Offshore Wind Farm Array. These works include the transport and installation operations of primary components, namely Monopiles, and secondary components, namely Main Access Platforms, Internal Platforms, Boat Landings and Upper Ladders.
Vessels shall be transiting to / from the Sofia Array and the ports of Blyth & Tyne throughout this period.
The following table highlights foundation installation progress and next 7 day forecast.
Total Foundations Installed (100 in Total) |
Foundations Installed Last 7 Days / (Date Fully Installed) | Foundation Installation Next 7 Day Forecast |
88 | G15, P15, E15 | U14, S13, K15 |
The Sofia Offshore Wind Farm Exclusion Zone coordinates, are shown below and included within the relevant NtM. Mariners are requested to remain outside this Exclusion Zone.
Vessels are requested to pass at a safe speed and distance and fishing vessels are advised to remain outside of the areas identified.
Service Operation Vessels
The Service Operations Vessels (SOV) “Rem Power” & Daughter craft “Rem Transporter”, Acta Centaurus (W2W) and Vestri Enabler (W2W) continues to support to the SOWF project throughout the construction of the offshore windfarm.
SOVs shall be transiting to / from the Sofia Array and the port of Blyth / Sunderland throughout this period.
Mariners are requested to remain where possible 500m from vessels. During these works, SOVs will have restricted manoeuvrability and shall also be exhibiting the correct day shapes/ lights and flag for vessels restricted in ability to manoeuvre.
Crew Transfer Vessel
The Crew Transfer Vessel (CTV) “MHO Balder” continues operations at the Sofia OWF.
All vessels can be contacted on VHF 16 for further information as required reference proximity / nearby operations etc.
See detailed map on our bulletin websiteSpectrum Vessel Service Limited in Conjunction with Atlantas Marine specialist ROV operators to conduct survey of the Thanet Windfarm Sub-station
The ROV utilised for the GVI survey shall be capable of acquiring the following sub–surface data: • High–definition video data; • Proximity CP readings using ROV mountable CP probe; • Direct CP readings using ROV mountable CP probe. The objectives of the GVI survey of the OSP is to determine the physical condition of the sub– surface elements of the structures. This will include an assessment of: • Any damage and deformation; • Any debris; • The condition of protective coatings; • The amount of marine growth; • A visual inspection and record of all subsea anodes attached to the jacket structure; • The level of cathodic protection (CP); • Seabed scour (where applicable).
The GVI survey shall evaluate the extent of corrosion, identify any damage and assess the overall integrity of the primary and secondary steelwork elements, covering the following jacket segments and other structural components: • Jacket members in splash zone • All horizontal, vertical, diagonal structural members • Installed Galvanic anodes • Structural clamps and connections • Mud mat and leg pile scour All items and components/elements below are to be covered under the scope of this survey: • Corrosion damage in terms of wear and rust • Localised corrosion damage in terms of pitting holes and major cracks • Member severance or missing members • Member buckling • Member denting or any other plastic deformation
• Inspection of all J tubes and risers • Partial or full detachment of anode–cast system from the structure • Missing or damaged anodes • Presence of debris trapped within the structural members of the foundation • Evidence of scour around the foundations and/or J tubes • Evident excessive marine growth attached to the structure • Gross paint coating damage; flaking, blistering, etc. in the painted tubular members (where possible due to the expected attachment of marine growth) The inspection of the selected areas shall include but not be limited to the following checks: • Gross extent of fatigue damage. • Visual signs of surface breaking cracks initiation and growth. • Length of surface–breaking fatigue cracks
As part of the planned geophysical survey within the Outer Thames Estuary, we are committed to ensuring the protection and preservation of the marine environment in line with relevant regulatory and environmental standards. The Outer Thames Estuary is a vital ecosystem supporting diverse marine life, including species of fish, seabirds, and marine mammals, as well as hosting sensitive habitats such as sandbanks and saltmarshes. Therefore, strict measures will be implemented to minimize any potential environmental impacts. Here are the key legislative frameworks impacting geophysical survey operations in the marine environment: 1. Marine and Coastal Access Act 2009 2. EU Habitats Directive (92/43/EEC) 3. EU Birds Directive (2009/147/EC) 4. Environmental Impact Assesment (EIA) Directive (2011/92/EU) 5. UK Wildlife and Countryside Act 1981 6. Marine Strategy Framework Directive (2008/56/EC) 7. Outer Thames Estuary Special Protection Area (SPA). 8. International Maritime Organization (IMO) Guidelines Practical considerations for compliance include: 1. Marine Licensing and Permits 2. Environmental Impact Assessments 3. Habitat and Species Protection 4. Stakeholder Engagement 5. Monitoring and Reporting 6. Training and Awareness Survey operations are subject to a robust regulatory framework designed to protect the marine environment and ensure sustainable use of resources. Compliance with these regulations requires careful planning, comprehensive impact assessments, and proactive
See detailed map on our bulletin website1. All mariners are to be advised that Jack up vessel Apollo will be carrying out lifting operations in the location listed below. These operations will take approximately 2 weeks depending on weather conditions.
Latitude Longitude
1.1.2 Schedule
DATE OF OPERATION START: 20/06/2025
TIMES OF OPERATION: 24hrs
LENGTH OF OPERATION: 2 weeks depending on weather
2 Jack up Operations / AOW NTM 041
2.1 Equipment
Work will be conducted from the Jack up vessel Apollo. Vessels are requested to remain 500m away from Apollo whilst she is deployed in the windfarm. Apollo will display the lights and shapes prescribed in the International Regulations for the Prevention of Collisions at Sea (COLREGS).
MMSI: 253586000
I.M.O: 9769764
L.O.A: 89.32m
BEAM: 42.00m
DRAFT: 8.00m
See detailed map on our bulletin websiteThe Offshore Service Vessel, MAINPORT GEO, will perform the Pre-Lay Grapnel Run operations in Dogger Bank C OWF Inter Array Cable Array Area.
This campaign will commence around 31st of May 2025 and continue until approximately 8th of June 2025. The works will be continuous, 24 hours a day. Charts of the DBC array area are provided below.
The operations include a single pre-lay grapnel run over the centre of part of the array cable routes prior to IAC installation by means of a grapnel train to mitigate the risk of encountering subsea obstructions such as discarded fishing gear, wires, etc.
During operations, the MAINPORT GEO will be restricted in its ability to manoeuvre as defined under COLREGs (International Regulations for Preventing Collisions at Sea 1972) and will display the appropriate day shapes and lights. The vessel will also transmit an Automatic Identification System (AIS) message.
It is requested that all vessels maintain a minimum of 1.5Nm separation distance from the vessel and pass at reduced speed. Fishing gear or other equipment with seabed intervention should not be deployed when approaching the working corridor.
See detailed map on our bulletin website
Mariners are advised that the Trinity House Buoy installation Vessel ‘Patricia’ will relocate and perform maintenance on the navigational buoys marking the boundary of the East Anglia Three Offshore Windfarm Array. All vessels are required to maintain a minimum of 500 metres safety distance from “THV Patricia” and navigate with caution at all times.
The confirmed relocation positions of EA3 Special 4 Buoy and EA3 West 2 Buoy will be notified via future Notice To Mariners. For further information regarding demarcation buoy relocation and maintenance, please see attached East Anglia THREE Notice To Mariner 034/2025: Aids to Navigation – Demarcation Buoy Relocation and Maintenance.
See detailed map on our bulletin websiteOn behalf of Inch Cape Offshore Wind Farm, N-Sea will conduct geophysical survey operations within the Inch Cape site and export cable route.
The geophysical survey vessel, Geo Ranger is expected to arrive in the survey arera on or around the 19th of February with operations expected to continue until the end of April 25. The vessel shall deploy towed survey equipment, mariners are requested to provide Geo Ranger with at least 1000m clearance during survey operations. The fishing vessel Solstice will conduct static fishing gear scouting in relevant survey boundary areas.
See detailed map on our bulletin websiteGlobal Marine are currently conducting the installation of the Q&E North telecommunications cable from Joss Bay, UK to Ostend, Belgium. The cable lay operations are currently ongoing with all operations expected to be completed by the end of June 2025. Timings are dependent upon weather and other operational conditions. Further details can be found in the attached NtM.
The vessels will be limited in manoeuvrability therefore, vessels working in the area should proceed with caution and alert the vessel within 1NM from the cable ship during operations and all activity should remain clear 250m either side of the vessel, 500m corridor in total.
For a further breakdown of operations, please don't hesitate to get in touch.
See detailed map on our bulletin websiteA offshore geotechnical survey within the proposed Morgan Offshore Wind Project (Generation Assets) and Mona Offshore Wind Project (see figure 1 and table 1 in the attached notice) is estimated to begin on the 2nd June 2025. The works will be undertaken by Fugro Synergy.
The survey involves the drilling, sampling and coring of boreholes throughout the array areas. The vessel will be stationary at each borehole location for up to 3 days to allow the samples and cores to be taken from the seabed. 24 hour and 7day lookaheads containing details of the positions of Fugro Synergy will be provided.
An Offshore Fisheries Liaison Officer (OFLO) will not be present on board the vessel during the survey but the project Fishing Industry Representative (FIR) and/or Company FLO (CLFO) can be contacted with any specific queries.
Contact details for the FIR and CFLO are provided in the attached notice.
See detailed map on our bulletin websiteUse of towed geophysical equipment to detect potential buried UXO.
Partrac Ltd., on behalf of Thistle Wind Partners, has deployed and is maintaining metocean equipment, a Seabed mooring, within the boundary of the proposed Ayre array area. The re-deploying of the metocean equipment is estimated to be carried out over one day from the 07th of May 2025, weather permitting, using the vessel, CTV Waterfall.
Partrac Ltd., on behalf of Thistle Wind Partners would like vessels to note that there is 100m HMPE recovery rope connected to the anchor weight which may be suspended in the water column. All vessels are to avoid the area. There will be an attempt to locate and recover the line and anchor.
The following equipment will be recovered, maintained, and redeployed on the site:
Maintenance activities will include but not be limited to:
All vessels are requested to maintain a 500m exclusion zone around the location.
See detailed map on our bulletin website
The Rock Placement Vessel 'Simon Stevin' completed Remedial Rock Placement works along the Sofia Export Cable from nearshore out to the array. All Guard Vessels operating on the cable route have departed the Sofia Offshore Wind Farm as of 26th May 2025. Post completion of rock placement works, a non-intrusive depth of cable burial survey works within the Sofia export cable corridor from Nearshore outwards towards the Sofia Offshore Array will be undertaken, date still to be confirmed.
Please note that rock placement will cause a reduction of navigable depth, but this is unlikely to exceed a 10% reduction. The actual positions of rock placement will be updated as part of the as-built information of the project.
All Mariners are advised that the 2 Export Cables & 1 Fibre Optic Cable (all bundled) have been installed into the HDD ducts at the Sofia HDD Landfall.
An MBES survey of the HDD trenches out to KP 3 was performed indicating the spoil heaps from 2023 back hoe excavation works have largely naturally dispersed. One spoil heap remains with a maximum height above the seabed of < 0.2 m and vessels are requested to leave a wide berth as identified for the nearshore exclusion boundary (HDD pits out to KP3) until further notice.
Fishing vessels are requested to pass at a safe speed and distance and remain outside of the exclusion area identified. All vessels can be contacted on VHF 16 for further information as required reference proximity/nearby operations etc.
The table below also provides the position and description of any equipment/asset/item that will remain in place following demobilisation of the Ievoli Ivory.
Location | Equipment and Description | Latitude | Longitude | Approximate Depth (LAT) |
A |
Concrete mattresses 3 of 5.95 m x 2.95 m x 0.30 m |
54°38.544’ N | 000°35.147’W | 55m |
B |
Concrete mattresses 1 of 5.95 m x 2.95 m x 0.30 m |
54°38.572’ N | 000°35.142’W | 55m |
C |
Concrete mattresses 2 of 5.95 m x 2.95 m x 0.30 m 1 of 5.55 m x 2.95 m x 0.50 m |
54°48.144’ N | 000°37.515’E | 74m |
See detailed map on our bulletin website
Arven Offshore Wind Farm will recover, service and re-deploy Passive Acoustic Monitoring (PAM) moorings in and around the Arven Offshore Wind Farm area to gather data on marine mammal activity.
Mariners are advised that NKT will conduct cable installation through Simultaneous Laying and Burial (SLB) along the East Anglia THREE export cable corridor. NKT will utilise the vessel ‘NKT VICTORIA’ for cable laying operations. All marine traffic is advised to maintain a 1000m safety zone around ‘NKT Victoria’ during operations and pass at a reduced speed.
Simultaneous Laying and Burial will be conducted between KP4.0 – KP148.0, inspection operations will be performed at third-party asset locations where applicable. During operations, NKT Victoria will have restricted manoeuvrability as defined under COLREGs (International Regulations for Preventing Collisions at Sea, 1972). The vessel will display appropriate day shapes and lights and will transmit an Automatic Identification System (AIS) message. ‘NKT Victoria’ will monitor VHF Channel 16 and VHF DSC Channel 70 continuously throughout the operation.
Victoria is expected to mobilise from the port of Karlskrona, Sweden on 14/06/2025. It is currently anticipated that weather permitting, works will be conducted on a continuous basis (i.e., 24-hour working, seven days a week).
See detailed map on our bulletin websiteThe Cable Lay Vessel (CLV) Viking Neptune will perform the inter array cable installation works with the commencement around 04th March 2025.
The works will continue over the winter. The vessel will further be assisted by the Walk to Work Vessel SUDRI ENABLER for the deployment of cable pull in teams. Shortly after the start of the cable installation, the Trenching Support vessel (TSV) C-INSTALLER will be mobilised to site for the burial of the installed cables. All works will be continuous, 24 hours a day. Charts of the DBB array area are provided below.
The cable lay vessel will deploy the inter array cable onto the seabed through her dedicated deck spread. The cable will remain exposed on the seabed till trenching works by C-INSTALLER are performed.
During operations, the VIKING NEPTUN, C-INSTALLER and SUDRI ENABLER will be restricted in their ability to manoeuvre as defined under COLREGs (International Regulations for Preventing Collisions at Sea 1972) and will display the appropriate day shapes and lights. The vessel will also transmit an Automatic Identification System (AIS) message.
See detailed map on our bulletin websiteFall Pipe Vessel (FPV) Flintstone will commence subsea rock installation at various locations on DBA
Flintstone will start operations on 07th of June 2025 and will perform rock placement during multiple load-outs, finishing her scope around 15th of July 2025. Work will be continuous, 24 hours a day.
During operations, Flintstone will be restricted in their ability to manoeuvre, as defined under COLREGs (International Regulations for Preventing Collisions at Sea 1972) and will display the appropriate day shapes and lights. The vessel will also transmit an Automatic Identification System (AIS) message.
It is requested that all vessels maintain a minimum of 500m separation distance from the Flintstone and pass at reduced speed.
See detailed map on our bulletin websiteNKT will carry out nearshore intervention works in support of the installation on the East Anglia Three Export Cable in the Export Cable Corridor in the vicinity of Bawdsey approximately 800 metres from shore. Locations for works are identified in section 2.1 of this document. Diving operations will be carried out onboard the vessel “Isle of Jura”, excavation operation will be carried out by the “Abeko Server 2”, and Survey works & Crew Change operations will be conducted by “Seafast Don”
Abeko Server 2 will be positioned at the HDD locations to begin seabed excavation for pit and trench creation and will carry out spoil management activities along the trench. The Abeko Server 2 will be manned 24 hours on site, with the Afon Alaw providing support for barge movements and towing as needed. During operations, the Abeko Server 2 will be restricted in its ability to manoeuvre as defined under COLREGs (International Regulations for Preventing Collisions at Sea 1972) and will display the appropriate day shapes and lights. The vessel will also transmit an Automatic Identification System (AIS) message. The Isle of Jura will deploy a four-point mooring spread, including chain clumps, ground and riser chains, mooring cans with yellow marker lights, and flashing sequences. An Alucat vessel will assist in connecting and disconnecting the Isle of Jura mooring lines to the mooring array.
See detailed map on our bulletin websitePartrac Ltd., on behalf of Thistle Wind Partners, has deployed and is maintaining metocean equipment (a Seabed mooring), within the boundary of the proposed Bowdun array area located off the east coast of Scotland.
The following equipment will be recovered, maintained, and redeployed on the site:
Maintenance activities will include but not be limited to:
All vessels are requested to maintain a 500m exclusion zone around the location.
See detailed map on our bulletin websiteJack Up onsite for major maintenance to be carried out at the noted locations throughout the wind Farm. During operations there will be a 500mtr exclusion zone around the location of the Jack Up.
Major component repairs are to be carried out on Beatrice Windfarn involving the use of a self propelled jack up (Blue Tern).
The work will be undertaken from the 30th of May lasting for approximately 8 weeks. The vessel will operate at six locations on the Beatrice Winfarm replacing the main bearings on WTG BE-A05, BE-D08, BE-F09, BE-F13 BE-G13 and BE-J10
See detailed map on our bulletin websiteThis is to raise awareness that the Construction Buoyage within the Moray Offshore Windfarm (West) Limited (Moray West) site will be removed in June or July 2025.
This is to raise awareness that the Construction Buoyage within the Moray Offshore Windfarm (West) Limited (Moray West) site will be removed in June or July 2025. This Notice supersedes the previous version which anticipated removal of the buoyage in April or May 2025. The Construction Buoyage currently remains in place, with this document highlighting the new removal dates.
See detailed map on our bulletin websiteMariners are advised that the Special Mark 2 (SP2) has been reported as unlit.
Partrac Limited (Buoyage Maintenance Contractor) are scheduled to be on location in the next couple of weeks, where this will be rectified.
Mariners are advised to give the location a wider berth until service and maintenanec works are complete.
See detailed map on our bulletin websiteRWE Renewables UK Wind Ltd at Rampion windfarm would like to inform mariners that we are carrying out the essential works to enable a cable replacement campaign within the Rampion OWF Area over the course of one to two weeks, depending on weather conditions. If works continue past this date, a supplementary Notice to Mariners will be released.
RWE Renewables UK Wind Ltd at Rampion windfarm would like to inform mariners that we are carrying out the essential works to enable a cable replacement campaign within the Rampion OWF Area over the course of one to two weeks, depending on weather conditions. If works continue past this date, a supplementary Notice to Mariners will be released.
Works will be at F04 and the Offshore Substation (OSS). Teams will mobilise on 2nd June with works in the water expected to start on 7th June. The work involves; removal of cable protection systems from F04 and the OSS and installation of lifting bags to enable cable recovery in a future campaign.
The current outline planning is as follows:
Start Date: Subject to weather 2 nd June 2025.
For the safety of the working party and anyone in the vicinity of the works, mariners are requested to be vigilant if approaching the below listed location and stay outside of 500m from the works operations at all times.
See detailed map on our bulletin websiteRemedial Rock Placement works along the Sofia Export Cable from nearshore out to the array are complete. All Guard Vessels operating on the cable route have departed the Sofia Offshore Wind Farm as of 26th May 2025. Post completion of rock placement works, a non-intrusive depth of cable burial survey works within the Sofia export cable corridor from Nearshore outwards towards the Sofia Offshore Array will be undertaken, date still to be confirmed.
*The height of external cable protection is expected to be 2.06 m between KP 163 & 164 (DBB cable crossing).The water depth at the crossing is 23.24m following rock placement this will result in a minimum under keel clearance of 21.18m and a water depth reduction of 8.9%*
*The height of external cable protection is expected to be 2.06 m between KP 165 & KP 166 (SEAL pipeline crossing). The water depth at the crossing is 24.37m, following rock placement this will result in a minimum under keel clearance of 22.3m and a water depth reduction of 8.4%.*
Fishing vessels are requested to pass at a safe speed and distance and remain outside of the exclusion area identified.
The table below details the coordinates of project infrastructure to remain on the seabed following the Ievoli Cobalt’s completion of works. The mattresses are not expected to reduce navigable depth by over 5%.
Location | Equipment and Description | Latitude | Longitude | Approximate Depth (LAT) |
A |
Concrete mattresses 1 of 5.95 m x 2.95 m x 0.30 m |
54° 52.070520N | 001° 25.687020E | 23m |
B |
Concrete mattresses 2 of 5.95 m x 2.95 m x 0.30 m 1 of 5.55 m x 2.95 m x 0.50 m |
54° 51.943620N | 001° 27.690900E | 24m |
Green Volt Offshore Wind Farm Limited will conduct a Geophysical Survey within the Offshore Wind Farm Site. The survey will be carried out by the Ramform Vanguard with mobilisation planned on the 25th May 2025 and is expected to be on location for approximately 4 weeks.
Green Volt Offshore Windfarm Limited (GVOWL) will be carrying out a geophysical survey within the Offshore Wind Farm Site. The survey will be carried out by the Ramform Vanguard with mobilisation planned on the 25th May 2025 and is expected to be on location for approximately 4 weeks. During operations, the survey equipment will have a layback from the vessel of approximately 250m. Any vessels transiting or fishing within the area shown in Figure 1 should be aware of this extended layback and contact the vessel on channel 16 for further updates on deployed survey equipment.
Deployment of the geophysical survey equipment will occur during transit on the way to the survey area. There will be an SFF services OFLO onboard the vessel to assist with any offshore fishing communications during the campaign, including communications on the area of deployment to reduce risks of interactions with other sea users.
See detailed map on our bulletin websitePlease be advised that A-2-Sea Solutions Ltd (on behalf of Transmission Investment) will be undertaking a pre-construction landfall and marine site investigation survey across the proposed LirIC Interconnector (LirIC) Project’ cable route.
Marine Survey operations be conducted by the MINTAKA 1 and the White Ribbon Nearshore vessel and shall consist of Geophysical data acquisition using hull mounted and towed sensors. This is followed by a Benthic environmental campaign consisting of video imagery and in-situ grab sampling operations. Other vessels should maintain an appropriate and safe distance of 500 m when passing the Mintaka 1 and FPV Morven vessel(s) whilst undertaking operations and should pass at the lowest possible speed to avoid vessel wash effects. The vessel(s) will be working 24-hour operations and will display appropriate day shapes and lights during reduced visibility and night operations. The vessel(s) will also monitor VHF Channels 16 and 12.
See detailed map on our bulletin websiteMetocean instrumentation and a floating LiDAR system (FLS) have been deployed within the boundary of the proposed Muir Mhòr Offshore Wind Farm Project site. MARINE USERS are requested to maintain a safe clearance distance of 500m from all assets. August 2024: replacement of northern guard buoy & FLS completed end Aug 2024, deployed from Peterhead Port. All AIS & marine safety information remain unchanged from the original Dec 2022 notice.
All instrumentation is deployed at a single deployment location within the project site. The purpose of the instrumentation is to gather Metocean and wind data to inform the proposed Muir Mhor Offshore Wind Farm Project.
All instrumentation was deployed by Green Rebel from the Port of Aberdeen to the site in February 2023 via the vessel BB Ocean (IMO 9196503, MMSI 258825000).
The FLS mooring comprises of a surface visible buoy moored to the seabed via a two-point mooring system constructed using a combination of rope and chain. Two guard buoys are located at approximately 30m from the main FLS buoy in a North/South orientation, with the mooring spread covering an approximate 315m radius. There is also a seabed frame for current measurements contained within the overall deployment footprint, approximately 30m East of the main FLS buoy. Note: there are 2x orange polyform marker buoys located above the northern anchor position (detailed below) which will be removed during the first planned maintenance visit.
The FLS light characteristics are Fl (5) Y 20s with 5nm range. The guard buoys’ light characteristics are FI Y 5s with 3nm range and include a yellow St. Andrew’s Cross topmark. The FLS is designated as “Muir Mhor Floating Lidar” on AIS, with MMSI number 992351400.
Details of the surface visible buoy, guard buoys, seabed frame and mooring arrangement are provided in the attachments.
MARINE USERS are requested to maintain a safe clearance distance of 500m from all assets.
See detailed map on our bulletin websiteAs part of the annual operations and maintenance of assets, geophysical surveys will be taking place within the Moray Offshore Windfarm (West) Limited (Moray West) site.
As part of the annual operations and maintenance of assets, geophysical surveys will be taking place within the Moray Offshore Windfarm (West) Limited (Moray West) site. The geophysical survey scope will include Multibeam Echosounder (MBES) of all buried inter array, interconnector and export cables, and MBES at a 300m2 area around all 60 monopiles.If any anomalies are identified, Side Scan Sonar (SSS) with USBL will be employed for further investigation along small parts of the cable routes. Survey equipment will be hull mounted with the exception of small areas where the SSS with USBL will be used, and this equipment will be towed.
See detailed map on our bulletin websiteMariners are advised that Hornsea Three is conducting a potential UXO (pUXO) inspection campaign, in relation to the Hornsea Three Generation Assets (array area).
Mariners are advised that, as of 2nd May 2025, Hornsea Three have identified and confirmed 13 pUXOs as cUXOs within the Hornsea Three array area, the coordinates of which are provided in Table 1 and shown in Figure 1. All vessels are requested to maintain the required safe distance (500m) as defined from the coordinates set out in Table 1 and Figure 1. The EOD works for the Hornsea Three array area, are expected to be undertaken in a separate campaign commencing in Q3 2025.
See detailed map on our bulletin websiteDuring unexploded ordnance identification and mitigation works, an item of unexploded ordnance has been discovered off Gullane Bay, East Lothian. This large item is located at the coordinates shown below in table 1 and fig 1. Inch Cape Notice to Mariners 06-25 refers.
During unexploded ordnance identification and mitigation works, an item of unexploded ordnance has been discovered off Gullane Bay, East Lothian. This large item is located at the coordinates shown below in table 1 and fig 1.
Inch Cape Offshore Wind has placed a 150m avoidance zone around the item and will promulgate any relocation, or disposal plans in due course, if further information is required, please contact the Duty Marine Coordinator, contact details in the attached notice to mariners
See detailed map on our bulletin websiteExternal Blade repair campaign across 7 location in N & S Galloper Windfarm
External Blade repair campaign across 7 location in N & S Galloper Windfarm
See detailed map on our bulletin websitePlease be advised that the EA3 West Cardinal No 2 Buoy deployed in position ‘52°37.466‘N 002°44.872‘E’ is currently out of position by 4 cables to the NE. The current position of the buoy is 52° 37.781’N 002°45.340’E. Please also be advised that the EA3 East Cardinal No3 Buoy is Unlit in position 52° 32.917’N 002° 51.558’E
The Guard Vessel Tess will announce hourly Security messages on VHF CH16.
Repairs are to be organized via Trinity House.
Any notifications of repairs will follow in a future Notice to mariners.
For further information please reffer EA3 NTM 031-2025 Navigation Light failure and Out of position Buoy
See detailed map on our bulletin websiteMariners are advised that NKT will conduct route clearance, inspection and mattress laying operations along the East Anglia Three export cable corridor utilising the vessel 'Trym'.
Route clearance of out of service cables, boulders and debris will be performed between KP4 -KP148 of the East Anglia Three Export Cable Route & within the boundary of the EA3 windfarm array. Inspection operations will be performed at third-party asset locations.
Mattress placement at third-party asset crossing locations will be performed at 7 locations between KP25 – KP42 of the EA3 Export cable route
A Pre-Lay Grapnel Run will be performed between KP4 – KP148
During periods of operation, vessel Trym will be restricted in her ability to manoeuvre. All vessels are requested to keep a minimum safe distance of 1000m from the vessel and pass at a reduced speed, fishers are requested not to deploy gear within the 500m fishing gear exclusion zone. For further information, please see attached East Anglia Three Notice To Mariners 030-2025.
See detailed map on our bulletin websiteGalloper Windfarm NTM O&M 01-2025 ROV Subsea Campaign - ROV Inspections of foundations across 28 WTG locations
The trenching support vessel, North Sea Enabler, will perform post-lay burial works of the Dogger Bank C export cable at the Offshore Substation Platform (OSP) location in the Southern North Sea, after late pull-in works have been completed
Permanent protection of the cable will be achieved insofar as possible by post-lay burial (trenching) operations, however alternative methods of protection, such as rock-bags or rock berms, may be required where burial is not possible at the OSP.
The works will be undertaken approximately between 09th of June 2025 and 12th of July 2025. The work will be continuous, 24 hours a day. Coordinates and chart of the route are provided below.
During post-lay burial operations, North Sea Enabler will be restricted in its ability to maneuver as defined under COLREGs (International Regulations for Preventing Collisions at Sea 1972) and will display the appropriate day shapes and lights. The vessel will also transmit an Automatic Identification System (AIS) message.
In the period between late pull-in operations until the cable has been permanently protected by means of burial or rock placement, the cable may be locally exposed on the seafloor and the construction working corridor will remain closed for any static fishing, anchoring or use of other equipment with seabed intervention. During this time the cable is sensitive to any external impact and constitutes a snagging risk for anchoring, fishing gear or other equipment with seabed intervention.
See detailed map on our bulletin websiteThe offshore site survey of the proposed Morgan (Generation Assets) and Mona Offshore Wind Projects array areas, to be carried out by the Ocean Observer.
The offshore site survey of the proposed Morgan (Generation Assets) and Mona Offshore Wind Projects array areas, to be carried out by the Ocean Observer (detail in section 6 of the attached notice).
The vessel will be making a crew change in the next few days in Liverpool. The vessel is then expected to transit to the Morgan licence area on the 25th May 2025 to commence Geotechnical survey activities. The survey involves shallow geotechnical surveys using Cone Penetration Testing (CPT) and Vibrocores (VC).
Following Geotechnical surveys in the Morgan licence area, the vessel will transit to the Mona licence area to continue Geotechnical surveys. A further Notice to Mariners will be issued in advance of this activity.
Regular lookaheads of the vessel position will be provide by the project FIR.
The project Fishing Industry Representative (FIR) and/or Company FLO (CLFO) can be contacted with any specific queries. Contact details for the FIR and CFLO are provided in this notice.
See detailed map on our bulletin websiteMariners are advised about Marine Survey Works for the Eastern Green Link 5 Project. The EGL 5 marine survey works are being carried out by ‘Fugro’ with the Vessel MJM Enterprise. The survey will include environmental work to collect sediment samples underwater video footage and water samples for subsequent analysis.
The EGL 5 project will play a vital role in achieving the UK and Scottish Government’s net zero targets and significantly increase the UK’s capacity for clean, green renewable power. The project comprises a 2GW, 525kV High Voltage Direct Current (HVDC) connection between an offshore Scottish and Southern Electricity Networks – (SSEN) Transmission’s licensed area to the National Grid Electricity Transmission (NGET) Lincolnshire Connection Node, comprising ~525km of HVDC cable offshore, ~10km HVDC cable onshore and a HVDC converter station.
The EGL 5 marine survey works are being carried out by ‘Fugro’ with the Vessel MJM Enterprise. The survey will include environmental work to collect sediment samples underwater video footage and water samples for subsequent analysis.
The area of work, pertaining to this Notice to Mariners (NtM) is illustrated in Figure 1 and Table 1, with the survey and updated support vessel contact details found in Tables 2 and 3. Contact details for the project’s Fisheries Liaison Officers are detailed below. The marine survey activities for EGL 5 will commence from the 28 th May 2025. The survey is due to be completed in approximately 30 days, subject to weather. The survey will be able to operate around static fishing gear. Therefore, fishing gear clearance is not being requested.
All vessels are requested to pass at a safe speed and distance, approximately 500 metres where possible (COLREGs Rule 16 & 18) from the areas identified during marine survey operations. The survey vessel will be restricted in her ability to manoeuvre and shall deploy towed sensors during geophysical survey operations only. The survey vessels will monitor VHF Channel 16 at all times. Mobile contacts for the vessels are listed at the end of this NtM
See detailed map on our bulletin websitePlease be advised that NKT will be deploying Guard Vessels along the East Anglia THREE Offshore Export Cable Corridor as detailed in Section 2.2 of the attached document for protection of the pre lay matrasses and to protect the cable bundle from the start of cable lay until the cable is adequately protected by means of trenching or rock placement.
The primary purpose of the guard vessels is to protect the exposed cable along the East Anglia 3 Export Cable corridor by monitoring and issuing warnings to marine traffic operating within 6Nm of the construction area with a Closest Point of Approach (CPA) < 1.5Nm. More specifically, the focus will be on those vessels with potential to be engaging in bottom contact activities such as fishing and anchoring, as these activities pose a risk not only to the exposed cable bundle but also to the vessels themselves. The guard vessels will be clearly marked and display a highly visible "GUARD" sign on each side. Exchange of vessels on site will ensure the relevant section of cable is never left unguarded. In sections where cable protection has been completed, guard vessels will be released, and sections will be opened up for fishing or use of other of equipment with seabed intervention. This may not necessarily be in a sequential order from shoreside outwards
See detailed map on our bulletin websiteThis updated Notice to Mariners (NtM) is related to the Landfall Preparation Works for the NeuConnect Interconnector. Installation works are now complete between KP 0.4 (51°27.9768'N 000°42.9291'E) and KP 2 (51°28.6756'N 000°43.7398'E). Due to restrictions of tide and weather windows, all operations are anticipated to require 24-hour working. A post-landing survey to define the scope of remedial works will be undertaken following cable landing operations, commencing from the 23 October 2024.
Survey Vessel (MV Fenny) will conduct bird surveys for Dudgeon and Sheringham Offshore Windfarms.
In 2025, four surveys are planned between May and July. These trips include two consecutive survey days with two days for travel to and from the survey area from a Dutch port. These trips are planned to take place on: • 19-22 May (survey days 20, 21) • 2-5 June (survey days 3, 4) • 16-19 June (survey days 17, 18) • 30 June - 3 July (survey days 1, 2) And a reserve week is planned as 7-10 July (survey 8, 9).
See detailed map on our bulletin websitePlease be aware that a geophysical and geotechnical cable route survey will be undertaken between the Castlefreke area in County Cork on the south coast of Ireland and the shelf break. The survey will be conducted by the following vessels: Ocean Invincible (Call sign C6ZI6) and the Ams Panther (Call sign 2EHC2). The work will begin 12 May and is expected to last 5 weeks.
The vessels carrying out the work will be towing survey equipment and will be limited in their ability to manouvre. Other vessels are kindly requested to give this operation a wide berth with regard to both vessels and gear. The vessels will display the appropriate lights and shapes and will maintain a listening watch on VHF Channel 16.
See detailed map on our bulletin website
Activities related to the development of the Triton Knoll wind farm continue, as detailed below. For background information visit: http://www.tritonknoll.co.uk.
NtM 002-2025 - Blade Inspections
Mariners are advised that on or around the 23rd April 2025 (weather depending), the Cardinal P will conduct a series of internal turbine inspections. During the blade inspections, the vessel will be tied off in close proximity to the Turbines being inspected (within the 50m zone).
This work will also involve external ROV inspection of 2 locations and will also be close proximity work to these locations (within the 50m zone) which is expected to start in June 2025 (dates to be confirmed.
NtM 003-2025 & NtM 004-2025 - Jack Up Operations
Mariners are advised that the Jack Up Vessel 'Wind Discovery' is expected to commence operations at the Triton Knoll OWF site conducting a series of construction activities. During these works there will be a 500m exclusion zone around each asset when worked upon. The Wind Discovery will be supported by the Arabella Jane.
This campaign will be completed in 2 phases as follows:
Phase 1: 28th April - 14th May 2025
Phase 2: 17th June – 30th June 2025
NtM 005-2025 - Drone Inspections
Mariners are advised that the Master P is expected to commence operations at the Triton Knoll OWF conducting Drone Inspections on all assets. Whilst drone inspections are being conducted, the Master P will be tied off near the asset and within the 50m zone.
NtM 007-2025 - Cable Protection System (CPS) Stabilisation Campaign The campaign will commence on 27th May 2025 for approximately 50 days (weather depending), including visits to port to reload.
Rock bags will be placed at intervals or adjacent to each other, as required, along selected exposed cable lengths at each of the fixed structure (WTG and OSP) locations across the site, taking approximately 6 hrs at each location. A 500m clearance to the vessel and all fixed structure locations whilst major maintenance works are being undertaken is required. The vessel will be operating 24/7.
Mariners are advised that the following vessels continue to be active at the Triton Knoll Offshore Wind Farm (TKOWF) as outlined within previously issued NtM's:
Vessel Name |
Type |
Call Sign |
MMSI |
IMO |
Operating Port |
Commence Date |
Windcat 11 | Crew Transfer Vessel | 2BIS9 | 235066459 | N/A | Grimsby | 14/12/2020 |
Esvagt Havelok | Service Operations Vessel | OYFR2 | 219026496 | 9878981 | Grimsby | 25/09/2021 |
Njord Amundsen | Support Vessel | ZDSO3 | 236112802 | 1036355 | Grimsby | 10/05/2024 |
Cardinal P | Support Vessel | 2FKK9 | 235092017 | - | Grimsby | 23/04/2025 |
Wind Discovery | Jack Up Vessel | OUHH2 | 219034268 | 9530096 | Grimsby | 28/04/2025 |
Arabella Jane | Support Vessel | MOYS2 | 232054276 | 1036707 | Grimsby | 28/04/2025 |
Master P | Support Vessel | 2HEO7 | 235103033 | - | Grimsby | 30/04/2025 |
Purus Chinook | Service Offshore Vessel | MPJQ7 | 232055578 | 1032701 | Hull | 11/05/2025 |
Ndeavor | Multi Purpose Vessel | 5BVG3 | 209852000 | 9650212 | Great Yarmouth | 27/05/2025 |
All vessels can be contacted via VHF channel 16 when operational in field.
Mariners are advised of works planned in and around the Triton Knoll Offshore Wind Farm in 2025 as referenced in NtM 001-2025, weather and work progress, vessel availability dependant.
*** Note ***
All 90 WTG's have now been fully installed, whilst WTG commissioning and service continues. All Export Cables are fully installed/buried and need to be deemed live/energised. All Inter Array Cables are fully installed and buried and need to be deemed live/energised. Whilst the main installation works have been completed, major construction commissioning works are continuing.
*** Note ***
Whilst TKOWFL is reopening the site to fishing from the 14th December 2021, TKOWFL kindly request that all fishermen intending to fish within the boundaries of the Triton Knoll wind farm, contact the Triton Knoll control room prior to entering and exiting the field, and inform them of their fishing intentions.
This precaution is requested to safeguard all vessels operational at the TKOWF site (including fishing vessels) and your cooperation, to ensure the safety of all parties is appreciated. The following contact details should be used when notifying the Triton Knoll control room of fishing activity:
Control Room Manager: Derek Whyte Radio: VHF channel 16 Callsign: TK MCC Phone: +44 1793 896250 Email: tkcr@rwe.com *** Note ***
Application of Triton Knoll Wind Farm Safety Zones During Construction The Secretary of State has granted the Application of Safety Zones on the Triton Knoll Wind Farm Project as follows:
|
Mariners are advised that all foundations monopiles have been installed and all inter-array and export cables have been installed.
Navigation Warning - 08th January 2021
Mariners are advised that the remnants of a Wave Rider Buoy sinker weight and partial rigging are located within the Triton Knoll Offshore Wind Farm Construction site at the following location;
53° 30.442N 000° 50.564E
It is advised that the partial rigging could potentially be floating up to 9.7m above the seabed, reducing the navigable safe water in the immediate area to 10m LAT. Mariners are advised to avoid the indicated position by 250 metres.
Possible Dangers to Navigation - Properties of the polypropylene show that the rope is buoyant, this makes the line sensitive for thruster currents. Taking the site water depth into consideration (19.7m LAT) and the maximum expected height above seabed of the rope 9.7m the line is expected to be floating submerged at approximately -10m LAT. In addition, it is noted that over time sediments will be trapped between the fibres and the heavier rope may finally sink. The polypropylene rope may impose a risk to foul propellers / propulsion of vessels due to the buoyant nature of the rope. As the rope is submerged at a depth of ~-10m LAT the risk is considered minimum for vessels with a shallow draught (<5m) and medium for a vessel with a deeper draught (>5m). Over time sediments will be trapped between the fibres and the heavier rope may finally sink thereby reducing the risk to propellers/propulsion of vessels. The clump weight itself (chain) is expected to have sunk into the seabed and has no significant height above seabed. In addition, the edges of the clump weight are mostly rounded (chain), the risk the clump weigh imposes to fishing activities/gear is therefore considered to be minimal.
Navigation Warning - 16th March 2021
Mariners are advised that two UXO targets have been confirmed within the Triton Knoll Offshore Wind Farm Array.
Mariners are advised that the two confirmed targets are located within 20 metres water depth (LAT) and a 10 metre radius exclusion zone is required around each target. The following table provides the coordinates and a description for each target.
Description of Target | Latitude | Longitude |
Water Depth (LAT) Metres |
Required Exclusion Zone (Metres Radius) |
Archaeological - The item is thought to be an air-delivered bomb. It appears to be in a stable condition and is resting on the seabed. Marine growth and concretion cover the body, indicating it has been in situ for a significant duration. The tail section of the bomb is missing, which is typical of unexploded bombs from WWII found in these circumstances and there is a significant hole in the case. The dimensions and characteristics gathered are consistent with a 500kg German bomb. Considering the state of the bomb the Net Explosive Quantity of the bomb is likely to be <5kg. | 53°31'50.249"N | 00°47'45.908"E | 20 | 10 |
Archaeological - The item is thought to be an air-delivered bomb. It appears to be in a stable condition and is resting on the seabed. Marine growth and concretion cover the body, indicating it has been in situ for a significant duration. The tail section of the bomb is missing, which is typical of unexploded bombs from WWII found in these circumstances and there is a significant hole in the case. The dimensions and characteristics gathered are consistent with a 500kg German bomb. Considering the state of the bomb the Net Explosive Quantity of the bomb is likely to be <5kg. | 53°31'49.895"N | 00°47'45.115"E | 20 |
10 |
RWE Renewables UK Wind Ltd at Rampion Windfarm would like to inform mariners that we are carrying out essential maintenance on the wind turbines. This work is due commence on 20th May 2025 for 90 days, within the Rampion OWF Area, depending on weather conditions. The work involves; Essential external blade repairs on 8 WTG’s. Technicians will be carrying out essential repair works via external rope access which pose a material risk of snagging on passing vessels.
Fugro will commence geotechnical site investigations at the proposed Dogger Bank South Offshore Wind Farm (DBS) from around the 21st May 2025 until approximately end of September 2025. The exact start and finish dates will be dependent on the prevailing weather conditions and work progress.
Geotechnical survey operations on the proposed Dogger Bank South site will be undertaken using the following vessels and their expected start and finish dates.
Vesse | Start | Finish |
Fugro Revelation | 21/05/2025 | 02/07/2025 |
Fugro Scout | 14/07/2025 | 06/10/2025 |
RS Alegranza | 31/07/2025 | 28/09/2025 |
As the vessels will be conducting geotechnical drilling operations using a dynamic positioning system, it is requested that all vessels operating within this area keep their distance, maintaining at least a 500 m exclusion zone, and pass at minimum speed to reduce vessel wash.
A continuous listening watch will be conducted on VHF Channel 16 by all survey vessels.
Operations will be conducted on a 24-hour basis.
See detailed map on our bulletin websiteA UXO was found and is currently sitting in position 51'57.924'N 001'56.122'E as per NTM. This is inside the Greater Gabbard windfarm - we have no plans to remove/ move/ detonate. This has been surveyed and the risk of detonation is low however we would advise a 500m Exclusion zone
Mariners are advised that SSE Renewables will be undertaking a benthic survey within a prospective offshore export cable route associated with Berwick Bank Offshore Wind Farm.
It should be noted that SSE Renewables are not requesting fishers to relocate gear - on this occasion the vessels will work around any gear on location. The survey work is being undertaken by Natural Power, utilising the Windcat 20 as the survey vessel (please see the updated notice to mariners attachment which provides further vessel details).
Once mobilised the survey will have a four day total duration. To allow for weather delays the expected completion date of the subtidal benthic survey will be 07 April 2025, however to allow for weather downtime, this notice will remain in effect until 31 August 2025.
During the survey campaign, the vessel will deploy an underwater drop down video/camera and mini Hamon grab to gather data on the ecology of the seabed. No towed gear operations will be taking place. The vessel will be generally unrestricted in its movements and will adhere to normal navigation protocol.
Updated Notice Information - 16 April 2025
Following completion of drop down video survey, the survey team will return to undertake grab sampling on Friday, 18 April 2025 depending on weather suitability. The vessel will be Gaoth Na Mara, please see the updated notice to mariners for further details.
See detailed map on our bulletin website
The OSV Nautilus will be conducting pre-lay operations on the proposed NeuConnect route within UK waters
This entails 4 key types of activity which includes:
1. Mattress Installation,
2. Route Clearance,
3. Debris / boulder removal
4. Pre-Lay Grapnel Run (PLGR)
Please see attached Notice to Mariners for more information.
See detailed map on our bulletin websiteMariners are advised that a survey vessel and equipment will be used in the West of Orkney Windfarm OAA (Offshore Agreement Area). The Geotechnical Survey will be carried out by Geo using survey vessel Connector (Call Sign: OYOJ2).
• This survey shall take place from 12th of May 2025 to 3rd July 2025
Construction of the Princess Elisabeth Island. The exclusion zone around the construction site is marked by 4 cardinal buoys (ELI-N, ELI-E, ELI-S and ELI-W).
Transmission system operator Elia is building the Princess Elisabeth Island in the Belgian part of the North Sea. This artificial energy island is an extension of the electricity grid in the North Sea. It connects the future wind farms of the Princess Elisabeth Zone with the Belgian coast and creates new connections with neighbouring countries.
The energy island is built centrally in the Princess Elisabeth wind zone, approximately 45 km from the Belgian coast. Construction of the island will take several years. To ensure safety during the works, the Belgian government defined an exclusion zone within which only work vessels are allowed. This zone is marked by 4 cardinal buoys (ELI-N, ELI-E, ELI-S and ELI-W).
Seabed preparatory works took place in spring and summer 2024. The installation of the caissons started in April 2025 and will proceed untill autumn 2026. During the winter months, no installation works will take place. The exclusion area remains in force at all times.
More information about the Princess Elisabeth Island is available on the Elia website: https://www.elia.be/en/infrastructure-and-projects/infrastructure-projects/princess-elisabeth-island.
See detailed map on our bulletin websiteOn behalf of Dogger Bank Windfarm, SMRU Consulting Ltd will carry out underwater noise monitoring between March and July 2025 during mono-piling operations to install foundation monopiles within and in the vicinity of the Dogger Bank C offshore wind farm construction area.
A total of 30 (thirty) sets of Passive Acoustic Monitoring (PAM) moorings have been deployed across an area approximately encompassing the Dogger Bank C array area boundary plus a 40km buffer, indicative coordinates are included below. The PAM moorings will remain in place for approximately 4 months before being recovered in July 2025.
See detailed map on our bulletin websiteThe Jack-up WTG Installation Vessel, Voltaire, will install wind turbine generators (WTG) within the Dogger Bank A construction area.
The works will commence on the 05th of July 2023, continuing until approximately Q2 2024. The works will be continuous, 24 hours a day. A chart of the DBA construction area boundary coordinates and a table of WTG location coordinates is provided below. A running list of the completed WTG installations and the next locations to be installed is presented in the Weekly Notice of Operations.
During operations, the Voltaire will be restricted in its ability to manoeuvre as defined under COLREGs (International Regulations for Preventing Collisions at Sea 1972) and will display the appropriate day shapes and lights. The vessel will also transmit an Automatic Identification System (AIS) message.
During operations, a Statutory Safety zone of 500m radius will be in place around the Voltaire during the installation of WTGs. The safety zone will be monitored by a guard vessel. The primary response will be to warn passing traffic of the ongoing works and any active safety zones, and to alert any vessels where an infringement may occur or has occurred.
See detailed map on our bulletin websiteThe Offshore installation vessel, HLV Seaway Strashnov and the HLV Seaway Strashnov will install wind turbine foundations in the Dogger Bank C offshore windfarm construction area.
The works will commence on the 22nd April 2025, continuing until approximately Q4 2025. The works will be continuous 24 hours a day. A chart of the DBC construction area is provided below. A running list of the next locations to be installed, mono-piled locations and completed foundations are presented in the Weekly Notice of Operations.
The installed monopiles will be marked with temporary lighting with the following characteristics:
• Flashing (Fl) Yellow (Y) 2.5 seconds (s)
• IALA Availability Category 2 (not less than 99.0%)
• 360° visibility – up to two lights per structure may be used to achieve this
• At least 2 nm range.
The temporary lighting will be removed prior to the installation of the transition piece and subsequent completion of the foundation
During operations, the HLV Seaway Strashnov and HLV Seaway Alfa Lft will be restricted in ability to manoeuvre as defined under COLREGs (International Regulations for Preventing Collisions at Sea 1972) and will display the appropriate day shapes and lights. The vessels will also transmit an Automatic Identification System (AIS) message.
During operations, a Statutory Safety zone of 500m radius will be in place around the HLV Seaway Strashnov and HLV Seaway Alfa Lift. The safety zones will be monitored by a guard vessel. The primary response will be to warn passing traffic of the ongoing works and any active safety zones, and to alert any vessels where an infringement may occur or has occurred.
See detailed map on our bulletin websiteThe Dogger Bank C Offshore Substation Platform (OSP) will undergo a Commissioning phase within the Dogger Bank C construction area. The Jack up Vessel (JUV) HEA Hydra will jack up and connect to the DBC OSP by a fixed gangway. The HEA Hydra will remain on site during the Commissioning phase, acting as the accommodation platform and OSP emergency evacuation vessel
The works will commence on approximately the 15th of May 2025, continuing until approximately 11th of September 2025. The works will be continuous 24 hours a day. A chart of the DBC construction area and the installation location is provided below.
During operations, a Statutory Safety zone of 500m radius will be in place around the HEA Hydra for the duration of the Commissioning phase of the DBC OSP. Vessels are requested to maintain a minimum safe passing distance of 1km from the HEA Hydra during the operation.
The Platform Supply Vessel (PSV) FS Balmoral will support the HEA Hydra, carrying out regular supply runs to the offshore site.
During the Commissioning phase, there will be a requirement for rope access works to be carried out to the external parts of the OSP and Jacket. During these Over the Side (OTS) works the Dogger Bank OWF Guard vessel Jacobus will act as the Emergency Response Rescue Vessel (ERRV).
See detailed map on our bulletin websiteThe area of planned activity will be over one area within the Beatrice Windfarm between WTG’s BE- F06 & BE-G07 (OTM1) which is detailed below. Work will be undertaken on the inter-array cable between these locations. BE-F06 58°14.168'N 002°54.169'W BE-G07 58°15.004'N 002°52.834' W
Major Maintenance works will be carried out to replace an inter-array cable on Beatrice Windfarm involving the use of a cable repair vessel (North Sea Enabler). This work will be undertaken from the 14th of May lasting until July 31st. The vessel will operate at one area on the Beatrice Windfarm.
Work will involve the removal of the existing inter-array cable and replacement. The cable will be laid within the existing trench as far as reasonably practicable using a control flow excavator. It is expected that the trench will naturaully backfill, and caution should be excersised during this time over the area. Further details will be provided at a later date regarding a guard vessel over the exposed cable.
See detailed map on our bulletin websiteIdentification of pre-surveyed potential UXO along the Norfolk Vanguard West Export Cable corridor and Windfarm array by vessel N-Sea Pathfinder. A Work-Class ROV will be utilised to dive, dredge and identify Magnetic anomalies along the Norfolk Vanguard West cable corridors.
Please be advised that Aspect Land & Hydrographic Surveys Ltd (on behalf of SHEPD) will be undertaking subsea surveys in the Outer Hebrides marine area. Please refer to Figure 1 that highlights the survey area. The surveys are scheduled to commence on the week commencing Monday 12th May 2025, and be completed by August 2025.
Please be advised that Aspect Land & Hydrographic Surveys Ltd (on behalf of SHEPD) will be undertaking subsea surveys in the Outer Hebrides marine area. Please refer to Figure 1 that highlights the survey area. The surveys are scheduled to commence on the week commencing Monday 12th May 2025, and be completed by August 2025.
Given the different conditions and water depths anticipated at each site, a range of vessels will be available for the project.
Start dates and anticipated durations listed against each individual location in the attached NtM.
LOCATION DETAILS
The survey corridor is noted in the attached NtM for information. Equipment calibration operations may take place out with the defined corridor and these areas will be chosen so as not to interfere with fishing / marine traffic activity.
VESSEL DETAILS
The vessels conducting these works will be restricted in their ability to manoeuvre and will display the appropriate lights and shapes.
Other vessels are requested to pass at a safe speed and provide a minimum clearance of 500m (COLREGs Rule 16 & 18) during marine operations.
All vessels will monitor VHF Channel 16 throughout survey operations. Mobile contacts for the vessels are listed at the end of the attached NtM.
See detailed map on our bulletin websiteMariners are advised that SSE Renewables will be returning to Berwick Bank Wind Farm area to undertake further Geotechnical survey work. The survey will be within the proposed Berwick Bank Wind Farm site boundary.
Overview
Mariners are advised that SSE Renewables will be returning to Berwick Bank Wind Farm area to continue Geotechnical survey work. The survey will be within the proposed Berwick Bank Wind Farm site boundary (see Figure 1 within the attached notice to mariners, respective co-ordinates are listed in Table 1).
It should be noted that SSE Renewables are not expecting fishers to relocate gear - on this occasion the vessel(s) will aim to work around any gear on location. A scouting/guard vessel will operate ahead of the survey vessel/s to ensure that this can be achieved.
The survey work is being undertaken by Fugro and will be conducted by multiple vessels. The scouting/guard vessel will be the Courage or the GV Reaper.
Updated Information - 08 April 2025
The Gargano is due to complete Cone Penetration Testing operations on the site by 13 April 2025. The Quest vessel, owned by Fugro, will commence a borehole campaign on the site starting 21 April 2025 at the earliest. The guard vessels will continue to be either the Courage or the Reaper alternating approximately every 21 days. Please see the attached Notice to Mariners for the vessel details.
Update Information - 24 April 2025
The Gargano (operated by Fugro) completed Cone Penetration Testing operations on 12 April 2025. The Quest vessel, operated by Fugro, will commence a borehole campaign on the site starting 25 April 2025 at the earliest. A third vessel operated by Fugro, named RS Alegranza (formerly Wind of Pride) will support on the survey campaign for up to one week on site, commencing work on 30 April 2025 at the earliest.
The guard vessels will continue to be either the Courage or the Reaper alternating approximately every 21 days. Please see below for vessel details. We would like to extend the validity of this notice until 30 September 2025.
See detailed map on our bulletin website
Hazards remain as identified by a cable route maintenance survey in 2023 that detected sections of cable with intermittent exposures and potential free spans in the UK sector of the IFA 2000 Interconnector. These exposures were found across all four cables west of 001° 17.2’E . The licence application process for cable protection was initiated with the MMO in 2023. Cable protection operations can only commence with MMO licence in place. Fishing vessels are reminded to keep clear of this area.
The exposures are present intermittently across all four cable routes as shown below/on the map.
Application for licence to remediate exposures has been submitted. Fishermen are requested to stay well clear.
See detailed map on our bulletin websiteThis notice describes the current Dogger Bank A and B boundary demarcation buoys in the Southern North Sea
A total of 32 construction boundary demarcation buoys will remain in location until the windfarm construction activities have been completed and handed over to the Operations and Maintenance teams.
Once the permanent Aids to Navigation (AtoN) have been installed on the WTGs, Trinity House will approve the permanent AtoN and the boundary buoys will be removed.
If anyone finds a buoy that is off station or encounters a buoy location where it is not functioning or is missing, they should report this to the Dogger Bank Duty Marine Coordinator as soon as possible.
See detailed map on our bulletin websiteMariners are advised that pre-sweeping activities will be taking place along the NeuConnect cable route. Works will be undertaken by Pre-Sweeping subcontractor Rohde Nielsen. The planned operations will be conducted by the vessels: • Njord R (TSHD) • Ask R (TSHD) • USS 202 (ROUV survey vessel)
Mobilisation of the Njord R, Ask R and USS 202 is anticipated from 24 April 2025 on site to commence pre-sweeping activities from 28 April 2025 onwards. The full scope of works are anticipated to take 5-6 months (weather dependent). Work is carried out from KP 78.9 (51º 48.2’ N 01º 38.0’ E) to KP 199.1 (52º 23.6’ N 02º 45.9’ E). Pre-sweeping activities between KP 78.9 to KP 145 are anticipated to be completed between 28 of Apr and beginning of June (weather dependent, it can take longer).
All vessels involved in operational activities will exhibit appropriate lights and day-time shapes prescribed by the International Regulations for Preventing Collisions at Sea, relative to operations. The vessel will also transmit an Automatic Identification System (AIS) message.
See detailed map on our bulletin websiteThe EGL5 marine survey works are being carried out by ‘XOcean’ with Remotely Operated Vessels XO06, XO16, XO17, XO19, XO23, X026, XO27, and support vessels ‘Elysse II’, and ‘RLM CERBERUS’. The survey will include non-intrusive geophysical work to collect bathymetric data, seabed imagery and sub-bottom imaging. The survey vessels shall be unmanned vessels/ uncrewed surface vessels and will be able to operate around static fishing gear. Therefore, fishing gear clearance is not being requested.
Mariners are advised about Marine Survey Works for the Eastern Green Link 5 Project (EGL5).
EGL5 Project will play a vital role in achieving the UK and Scottish Government’s net zero targets and significantly increase the UK’s capacity for clean, green renewable power.
The project comprises a 2GW, 525kV High Voltage Direct Current (HVDC) connection between offshore Scottish and Southern Electricity Networks – (SSEN) Transmission’s licensed area to the National Grid Electricity Transmission (NGET) Lincolnshire Connection Node. This comprises ~585km of HVDC offshore cable and in Lincolnshire, ~10km HVDC onshore cable and an HVDC converter station.
The EGL5 marine survey works are being carried out by ‘XOcean’ with Remotely Operated Vessels (ROV’s) XO06, XO16, XO17, XO19, XO23, X026, XO27, and support vessels ‘Elysse II’, and ‘RLM CERBERUS’. The survey will include non-intrusive geophysical work to collect bathymetric data, seabed imagery and sub-bottom imaging.
The area of work pertaining to this Notice to Mariners (NtM) is illustrated in Figure 1 and Table 1, with the survey and updated support vessel contact details found in Tables 2 and 3. Contact details, including the project’s Fisheries Liaison Officers are detailed below.
The marine geophysical survey activities for EGL 5 will commence from the 23rd April 2025. The survey is due to be completed by the end of June 2025, subject to weather.
The survey vessels shall be unmanned vessels/ uncrewed surface vessels (USVs) and will be able to operate around static fishing gear. Therefore, fishing gear clearance is not being requested.
All vessels are requested to pass at a safe speed and distance, approximately 500 metres where possible (COLREGs Rule 16 & 18) from the areas identified during marine survey operations. The survey vessels shall operate without any towed equipment and remain fully manoeuvrable during survey activities The survey vessels will monitor VHF Channel 16 at all times. Mobile contacts for the vessels are listed at the end of this NtM.
See detailed map on our bulletin website
During the campaign to lay and bury the Dogger Bank B export cable, it has been necessary to install rock berm protection over the cable in locations where it has not been possible to trench bury the cable.
Rock berm installation has been installed to an average height of approximately 1.6m above seabed level, which represents and average reduction in depth at Lowest Astronomical Tide (LAT) of approximately 6%.
See detailed map on our bulletin websiteThe offshore geotechnical survey of the proposed Mona Offshore Wind Project and Morgan Offshore Wind Project (Generation Assets) is currently paused due to a technical fault. The vessel is expected to be in port until ~23rd of April after which it will return to the Morgan array area. This will delay the survey works, which are now expected to be completed in early October (~10th October). The survey was previously expected to end ~30th September 2025.
The survey involves the drilling, sampling and coring of boreholes throughout the two Array Areas. The vessel will be stationary at each borehole location for 1 to 3 days, depending on borehole depth, to allow the samples and cores to be taken from the seabed. 24 hour and 7-day lookaheads will be provided, containing details of the positions of Horizon Geodrill.
An Offshore Fisheries Liaison Officer (OFLO) will not be present on board the vessel during the survey, but the project Fishing Industry Representative (FIR) and/or Company FLO (CLFO) can be contacted with any specific queries.
Contact details for the FIR and CFLO are provided in attached.
See detailed map on our bulletin websiteAll metocean equipment was removed by Partrac Ltd on 5 November 2024, with the exception of the Floating LiDAR (FLiDAR), which remains active on site.
The remaining FLiDAR is scheduled for removal in November/December 2025, inclusive of any delays due to adverse weather conditions. An accurate removal date, along with vessel details for the operation, will be provided in the next update in due course.
See detailed map on our bulletin website
After each TP has been installed by the Jack-up Vessel (JUV), Seaway Ventus, Contractor shall perform the TP Completions Scope with the Norside Supporter (CSV), with a delayed start from Seaway Ventus. CSV shall operate on a single 12-hour shift for the duration of the project. ETA For works is Circa 25/04/2025.Bolting and Grouting operations will be conducted by the Norside Supporter within the East Anglia THREE offshore windfarm area.
Norside Supporter Will be Bolting and Grouting 95 monopiles and transition pieces at the WTG locations set out in section 2.2 of this document. It is currently anticipated that weather permitting, offshore works will be carried out on a continuous basis (i.e. 24-hour working, seven days a week)
See detailed map on our bulletin websitePlease be advised that Partrac Ltd have completed maintenance on the Northern weather monitoring buoy, installed within the East Anglia Three Offshore Wind Farm Area.
Positions for both North & South weather buoys are identified in the attached Notice To Mariners 005 -2025. There will be periodic maintenance for both weather buoys during construction of EA3.
There is an exclusion zone of 100m around the weather buoys, mariners are advised to abide by the 100m safety zone and navigate with caution at all times.
See detailed map on our bulletin websitePlease be advised that Moray Offshore Windfarm (East) Limited (Moray East) are planning to undertake geophysical surveys within the site boundary. Survey operations will be carried out by the Geosurveyor XI which is expected to arrive at site circa 18th April for 1 day then 1st June for 41 days. The geophysical survey scope will include Multibeam Echosounder (MBES), Side Scan Sonar (SSS) of all buried cables and a 300m2 area around jackets shown in the coordinates of the work site boundary.
Please be advised that Moray Offshore Windfarm (East) Limited (Moray East) are planning to undertake geophysical surveys within the site boundary (Table 1 and Figure 1). Survey operations will be carried out by the Geosurveyor XI which is expected to arrive at site circa 18th April for 1 day then 1st June for 41 days (inclusive of weather downtime). The survey will take place within the red boundary in Figure 1.
The geophysical survey scope will include Multibeam Echosounder (MBES), Side Scan Sonar (SSS) of all buried cables and a 300m2 area around jackets shown in The coordinates of the work site boundary are presented in the below Table 1.
Table 1: Moray East Site boundary
Coordinates |
|||
Easting |
Northing |
Latitude |
Longitude |
515330.83 |
6464697.91 |
58° 19.378' N |
2° 44.296' W |
525198.17 |
6453175.00 |
58° 13.141' N |
2° 34.265' W |
525337.48 |
6443784.17 |
58° 8.080' N |
2° 34.184' W |
505117.13 |
6436034.64 |
58° 3.946' N |
2° 54.796' W |
509820.00 |
6445320.00 |
58° 8.945' N |
2° 49.990' W |
507393.03 |
6452043.96 |
58° 12.571' N |
2° 52.451' W |
512568.09 |
6458210.62 |
58° 15.887' N |
2° 47.147' W |
Geosurveyor XI |
|
Call Sign: |
2GRS3 |
MMSI: |
235099951 |
On Board Contact: |
+31 681131956 +32 485740290 |
Onshore Representative: |
John Elcoat +44 07356 224547 |
|
Please be aware that, during the survey activities, by virtue of its mode of operation the vessel (Geosurveyor XI) will be Restricted in her Ability to Manoeuvre (RAM) as defined under COLREGs (International Regulations for Preventing Collisions at Sea 1972, Rule 3). Masters of vessels are therefore requested to maintain their vessels and gears at a minimum safe passing distance from the vessel of 500 metres when it is undertaking work and showing the appropriate shapes and lights in accordance with COLREGs Rule 27.
In order to not compromise the safety of the Survey Vessel, their crew, and their ability to undertake its contracted works, fishermen who have static fishing gears deployed within 500 m from the WTG where survey activities are planned (see Table 1 and Figure 1) are requested to provide the coordinates of such deployed gears in DMS and details of whether the surface markers used are visible at all states of visibility to Alex Winrow-Griffin (Brown & May Marine) using the contact information below (Section 58 of the Merchant Shipping Act 1995).
Fishermen who have static gears deployed beyond 12 nm are reminded that static gear must be marked in accordance with Commission Implementing Regulation (EU) No. 404/2011 (https://www.gov.uk/guidance/marking-of-fishing-gear-retrieval-and-notification-of-lost- gear#marking-of-fishing-gear)
The following contact can provide more information if required. Please note that specific queries can also be addressed to the relevant vessel or shore-based representative.
CONTACT DETAILS |
|
Marine Coordination Centre 24/7 Peter Garden – Lead Marine Coordinator Email peter.garden@oceanwinds.com Tel : +44 07884630427 |
For fisheries related matters Alex Winrow-Giffin – Brown and May Marine Ltd. Email: alex@brownmay.com Tel : +44 1379 872148 / +44 7760 160039 |
As part of the annual operations and maintenance of assets, general visual inspection of the asset foundations and geophysical surveys will be taking place within the Moray Offshore Windfarm (West) Limited (Moray West) site
As part of the annual operations and maintenance of assets, general visual inspection of the asset foundations and geophysical surveys will be taking place within the Moray Offshore Windfarm (West) Limited (Moray West) site.
Asset foundation inspections will be carried out by the Manor Vulcan which is expected to arrive at site circa 9th April for 1 day, returning on 12th June for 78 days
Scope of work includes the General Visual Inspection (GVI) of Wind Turbine Generator and Offshore Substation Platform foundation assets across the site including the transition piece, monopile, cable protection system and scour protection. The inspections shall be carried out through use of an Unmanned Aerial Vehicle (UAV) for above water works and a Remotely Operated Vehicle (ROV) for below water works. The work will be performed from the Manor Vulcan.
See detailed map on our bulletin websiteFaults with NAV Aids and lighting
AIS - no AIS data for HS1, HS2, HS4 and HS5 - fault finding and repair to be conducted at earliest opportunity.
HS1 and HS4 - Nav aid lighting on the WTGs is faulty - fault finding and repair to be conducted at earliest opportunity.
HS1 has fault aviation lighting - fault finding and repair to be conducted at earliest opportunity.
See detailed map on our bulletin websiteA geophysical survey is due to commence within the MachairWind Offshore Windfarm area. This survey will be undertaken by Sulmara from the Port of Larne with an earliest commencement date of the 15th April 2025 and expected completion date of the end of July 2025, weather dependent. The MV Mainport Edge (Call Sign: V7A7352) will be used and will deploy towed, hull-mounted equipment, and drop-down cameras. Mariners are requested to maintain a distance of 500 metres from the survey vessel.
The geophysical survey will be undertaken within the Survey Area, with a 1.5 km buffer around it to allow the survey vessel to turn between survey lines (please refer to the map in the ‘Activity Area’ section below which displays both the Survey Area and 1.5 km buffer).
The MV Mainport Edge will use a range of acoustic and sonar sensors to investigate the seafloor and sub-surface, these will either be attached to the hull of the survey vessel or towed by the survey vessel for the duration of the geophysical survey.
The MV Mainport Edge will transmit regular automatic transmission system messages during the geophysical survey.
See detailed map on our bulletin websiteRecent surveys have discovered 2 exposures on an HVDC cable in the Thames Estuary.
Please be advised that the crew transfer vessel ‘NR Rebellion’ is expected to mobilise in the port of Lowestoft circa 01/04/2024
Crew Transfer Vessel NR Rebellion will provide assistance during the construction phase of the East Anglia Three Offshore Windfarm Array and will make regular transits between East Anglia Three CDM and the ports of Lowestoft and Great Yarmouth. Outer Thames Estuary Special Protection Area (SPA) As required under Deemed Marine License Condition 13(1)(c)(v) to minimise disturbance to red throated diver in the Outer Thames Estuary Special Protection Area (SPA), during construction of EA3. It is anticipated that vessels which are transiting to Lowestoft and Great Yarmouth ports, such as for crew transfer operations, will transit through and/or in proximity to the Outer Thames Estuary SPA. These areas shall be as far as practicable be avoided during transit from 01st November to 31st March
See detailed map on our bulletin websiteOuter Dowsing Offshore Wind Farm 2025 Offshore Geotechnical Borehole Survey
Outer Dowsing Offshore Wind (a joint venture between TotalEnergies, Corio Generation and Gulf Energy) are conducting a 3.5 month offshore geotechnical survey between 28th April and 08th August 2025 using the vessel Dina Polaris call sign: CQOF. The survey vessel shall be conducting geotechnical boreholes at various locations within the proposed offshore wind farm area. The vessel will typically spend one to two days static at each sample location within the area so please allow a safe distance.
Company: Outer Dowsing Offshore Wind
Contractor: Geoquip Marine Operations AG
Survey Vessel: Dina Polaris
Survey Vessel call sign: CQOF
Earliest Start date: 28th April 2025
Latest Finish date: 8th August 2025
See detailed map on our bulletin websiteAll mariners and stakeholders are advised that seabed preparation activities will commence within the Inch Cape Offshore Wind Farm and export cable corridor.
On behalf of Inch Cape Offshore Ltd, N-Sea will commence seabed preparation activities within the wind farm site boundary and its export cable corridor on or around the 30th of March 2025.
Seabed preparation will include the relocation of any boulders and the identification and mitigation of any unexploded ordnance (UXO) which may affect the installation of offshore structures, inter-array cables and export cables.
The boulder relocation vessel, FS Aries is expected to arrive at the work site on or around the 30th of March with the UXO identification & mitigation vessel,
4-Winds arriving on or around the 4th of April.
Works are expected to be completed by November 2025.
See detailed map on our bulletin websiteAll Mariners are advised that the Nearshore vessel Seafast Don (Call-Sign MMMD6) and MV Survey Vessels Vos Gorgeous (Call-Sign 2HEN8) and Ocean Marlin (Call-Sign LAWV8) will be performing a programme of survey works off the coast of East Anglia operated by Sulmara Subsea Limited on behalf of their client, Scottish Power Renewables.
The survey work consists of 3 different phases with all 3 vessels mobilising at different periods and will operate simultaneously however the total expected duration for all the works with all 3 vessels is approx. 100 days. Operations will comprise the following phases:
- Phase 1 – Nearshore and Offshore Surveys comprising a towed array of hydrographic survey equipment approx. 150m in length within the boundary coordinates outlined within this notice. This phase is expected to last approx. 74 days in total.
- Phase 2 – Environmental Survey within the same boundary coordinates at the later end of the period comprising various stationary elements. This phase follows on from Phase 1 and is expected to last approx. 12-15 days in total.
- Phase 3 – ROV survey within the same boundary coordinates at the later end of the period – most likely to be the same vessel as in Phase 2. This phase follows on from Phase 2 and is expected to last approx.. 14-18 days in total.
Both offshore vessels will operate 24hrs whilst the nearshore vessel will operate 12hr days exclusively within the 12nm zone.
See detailed map on our bulletin websiteMariners are advised that the Jack Up Vessel Seaway Ventus will commence monopile and transition piece installation operations within the East Anglia THREE offshore windfarm area circa the 27/03/2025. Operations will be conducted by Seaway 7 and the main working area will be inside the CDM Zone of the wind farm array.
Seaway Ventus will install 95 monopiles and transition pieces at the WTG locations set out in attached East Anglia Three Notice To Mariners 012 /2025. During the monopile and transition piece installation campaign, all vessels are requested to keep a 500m safety distance from the Seaway Ventus. It is currently anticipated that weather permitting, offshore works will be carried out on a continuous basis (i.e. 24-hour working, seven days a week)
During operations, the ‘Seaway Ventus’ will have restricted manoeuvrability as defined under COLREGS (International Regulations for Preventing Collisions At Sea, 1972). They will display the appropriate day shapes and lights and will transmit an Automatic Identification System (AIS) message.
See detailed map on our bulletin websiteMariners are advised that Fraunhofer IWES has deployed a Floating Lidar System (FLS) next to the NOAH (National Offshore Anemometry Hub), 3NM off Blyth. The ODAS buoy was moored on the 1st November 2024 and is now expected to stay at its deployed position until August 2025.
Additional vessel and manpower working within Sheringham Shoal Windfarm.
Sheringham Shoal windfarm will be undertaking additional works outside of scheduled maintenance commencing 20th March 2025. This work will involve the retrofit of the Push on Plates (PoPs) on 80 WTGs and the 2 Offshore Substations to allow “Walk to Work” operations to be completed via Service Operation Vessel (SOV).
The project is expected to last for approximately 16 weeks and will require 1 additional CTV vessel to be present in the windfarm for this period. However, there should be some expectation of weather delays therefore some contingency should be applied to the planned dates.
The Crew Transfer Vessel (CTV) Manor Victor is contracted for normal service operations will support in the field with crew transfers and additional transport.
The additional work scope and vessel should not cause any impact to local vessels or activities, but normal due care should be taken within the boundary of the windfarm due to increased vessel activity and work on turbines and offshore sub stations.
See detailed map on our bulletin websiteMariners are advised that Orsted Hornsea Project Four (UK) Limited (hereafter ‘Orsted’) located within the UK Sector of the North Sea, off the coast of East Yorkshire. will be commencing a scope of geophysical survey works in late March/April 2025.
The geophysical survey will include Multibeam Echosounder (MBES)/ Backscatter, Side Scan Sonar (SSS), Magnetometer (MAG), Innomar sub-bottom profilers (SBPs) and an Ultra-short baseline (USBL) acoustic positioning system will be used to calculate the position of underwater targets.
The geophysical survey works will be conducted by the following 3 survey vessels. “Ocean Endeavour”, “Titan Endeavour”, and “Ocean Researcher” as well as one support vessel “GV Jacoba”. The mobilisation of the first geophysical vessel will start 14th March 2025 and the survey operation will commence from around 1st April 2025. The works are expected to last approximately 180 days, including weather downtime. The exact survey dates are subject to mobilisation time, weather and work progress.
See detailed map on our bulletin websiteMariners are hereby advised that circa the 01/03/2025 the guard vessel Tess will commence guard duty operations at the East Anglia Three Offshore Windfarm area set out in section 2 of the attached Notice to Mariners.
The guard vessel ‘Tess’ will monitor vessel traffic in and around the East Anglia Three Offshore Windfarm 24hours a day, 7 days a week. The vessel will broadcast regular navigational warnings and will contact any non-project vessels they believe could cause potential hazards, risk of collision, or cause an interruption to project vessels or assets. She will be monitoring VHF Channel 16 and VHF DSC Channel 70 continuously throughout the operaton.
See detailed map on our bulletin websitePlease be advised from circa 1st November 2024 East Anglia Three Offshore Windfarm construction works will commence, subsea boulder and debris clearance operations will be the first construction activity as per the attached NTM document. Followed by Scour protection Installation circa 05th November 2024 as per NTM 050 in attachment.
East Anglia THREE will be a large offshore wind farm, located 69 km off the Norfolk coast. With a projected capacity of approximately 1400MW, the wind farm shall supply electricity to approximately one million UK homes. Onshore construction for the project started in July 2022.
By use of multiple specialized offshore vessels,1 Offshore Convertor station (OFCS) & 95 offshore wind turbine generators (WTGs) will be installed within the East Anglia Three site boundary along with the associated inter array and export cables. The generated power will be transmitted via an installed External Cable (EC) from the OFCS to a shore side substation located in Bramford.
See detailed map on our bulletin websiteThis notice is to advise that Green Rebel has installed one (1) Floating LiDAR System (FLS) buoy at the OREC National Offshore Anemometry Hub (NOAH), approximately 3 nautical miles off the coast of Blyth, Northumberland for a minimum period of 6-months.
During 14th January recovery ops, the seabed mounted echosounder and clump weight could not be located/recovered. A search was carried out across ~500m x 400m around deployed position with high resolution echosounder but could not locate items; these may have been dragged to another location. Remains of the anchor (chain links) for FLiDAR 1 could also not be found/recovered. These items are presumed lost but could potentially be a snag risk to fishermen, however do not pose a risk to navigation.
Echosounder and clump weight
A seabed mounted frame (1.6 x 1.6 m x 0.8 m, 350 kg) with echosounder inside was deployed in approx. 91 m water depth on 19th July 2024. The frame was connected with a ground line to a mooring weight/anchor (2,000 kg), which was attached to a standard spherical blue surface marker buoy with a riser to mark its position. The surface marker buoy was not visible at time of recovery operations so is thought to have broken free from the clump weight.
Photos of the echosounder frame, clump weight and surface marker buoy are attached.
The frame was designed to be overtrawlable however the clump weight was not so could pose a snag hazard.
FLiDAR 1 anchor
In April 2024, the FLiDAR buoy broke its mooring; the clump weight for this was made up of several ~1m long lengths of heavy chain bound together with a smaller chain (photo of similar set-up attached as an example). The buoy and mooring were recovered, and subsequent inspection onshore showed that the chain binding the links of heavy chain had come apart as the FLiDAR was dragged, leaving the heavy chain lengths on the seabed. These are expected to have sunk into the seabed sediment and/or have dispersed from original location. Consequently, these links of chain are not considered to pose a snag risk.
Locations of these items are in table below but note that these are deployed locations and they could have moved/been dragged from these points.
Lost item |
|
Latitude |
Longitude |
FLiDAR 1 anchor |
DMS |
57°36′28.8” N |
1°13′37.2” W |
|
DDM |
57°36.480′ N |
1°13.620′ W |
Echosounder |
DMS |
57°36′17.7” N |
1°13′36.5” W |
|
DDM |
57°36.295′ N |
1°13.609′ W |
Echosounder clump weight |
DMS |
57°36′19.6” N |
1°13′37.9” W |
|
DDM |
57°36.326′ N |
1°13.631′ W |
See detailed map on our bulletin website
During a routine inspection of the export cables (ECR A & ECR B) , two sections of the cables were found to be partially exposed through the boulder field. This may constitute a hazard to activities such as fishing and anchoring
It is requested that mariners avoid activities which are likely to disturb the seabed within a 500m Radius of this location until the exposed export cable has been re-investigated. A further Notice to Mariners will be issued to confirm the course of action we will be taking to rectify this. Please note that the standard safety rules apply when fishing in or near wind farms and associated cables. All mariners are requested to make themselves aware of their obligations for conducting activities over buried and protected cables under International and UK Cable (Sub-sea) Protection Legislation.
Mariners are reminded to navigate with caution and keep continued watch on VHF Ch. 12 / 16 when navigating the area. The Marine Coordination Centre will be responsible for monitoring and policing the Safety Zone and can be contacted directly for advice. Further information on the risks to fishing adjacent to subsea cables can be found in Weblinks: www.kis-orca.eu https://www.seafish.org/article/kingfisher-bulletin
See detailed map on our bulletin websiteGalloper Windfarm, RWE - NTM: GWFL-O&M 03-2020 v2 Risk of cable exposure within the Galloper Windfarm
Please be advised that the subsea survey carried out in 2020, identified seven cable routes with 10 exposures in total. The below table provides the locations of the identified exposures.
As cable exposure is a known risk at Galloper and across the offshore wind industry, we would remind Mariners of the safety information found on the KIS-ORCA website ‘The risks of fishing near cables and renewable energy structures. To avoid crossing cables when towing equipment follow the cable corridors- locations of the cables can be found on the Galloper awareness charts via KIS-ORCA.
See detailed map on our bulletin websiteGalloper Windfarm, RWE - NTM: GWFL-O&M 03-2020 v2 Risk of cable exposure within the Galloper Windfarm
Please be advised that the subsea survey carried out in 2020, identified seven cable routes with 10 exposures in total. The below table provides the locations of the identified exposures.
As cable exposure is a known risk at Galloper and across the offshore wind industry, we would remind Mariners of the safety information found on the KIS-ORCA website ‘The risks of fishing near cables and renewable energy structures. To avoid crossing cables when towing equipment follow the cable corridors- locations of the cables can be found on the Galloper awareness charts via KIS-ORCA.
See detailed map on our bulletin websiteAEC-1 Cable System break has been repaired but the Post Repair Inspection and Burial (PRIB) operation has not been completed. Hence, a section of approx. 1.5km of cable is sensitive to any external impacts and constitutes a snagging risk for anchoring, fishing gear or other equipment with seabed intervention. Please keep a distance of 500m.
Mariners are advised that Orsted Hornsea Project Four (UK) Limited (hereafter ‘Orsted’) will be commencing a scope of geotechnical survey works in February 2025. The surveys are being undertaken to perform geotechnical seabed investigations, including undertaking boreholes and CPT’s, for the Hornsea Project Four Offshore Wind Farm (‘Hornsea Four’) project, located within the UK Sector of the North Sea, off the coast of East Yorkshire.
The geotechnical survey works will be conducted by the following 3 survey vessels. “Connector”, “Geoquip Saentis”, and “Geoquip Seehorn” as well as one support vessel “GV Independent”, starting from 10th February 2025. The works are expected to last approximately 170 days, including weather downtime. The exact survey dates are subject to mobilisation time, weather and work progress.
Hornsea Four does not request any fishing gear to be cleared as the proposed activities intend to work around any fishing gear encountered. If gear is directly obstructing a sample location, Orsted may request gear relocation though this will be avoided where possible.
The contents of this notice are based upon our current understanding of Hornsea Four’s requirements
See detailed map on our bulletin websiteThe Service Operations Vessel, (SOV) Edda Boreas, will carry out Balance of Plant (BoP) and Asset Preservation operations within Dogger Bank A construction site. The works will be performed in a single campaign, commencing on the 6th of November 2022 and continuing until approximately Q3 2025. The works will be continuous, 24 hours a day.
The operations will include visual inspections and maintenance at installed WTG foundation locations. During operations, the Edda Boreas will be restricted in its ability to manoeuvre as defined under COLREGs (International Regulations for Preventing Collisions at Sea 1972) and will display the appropriate day shapes and lights. The vessel will also transmit an Automatic Identification System (AIS) message. It is requested that all vessels maintain a minimum of 500m separation distance from the Offshore Supply Vessel and pass at reduced speed. Fishing gear or other equipment with seabed intervention should not be deployed when approaching the working area.
See detailed map on our bulletin websiteGreen Rebel, on behalf of Magnora Offshore Wind, has deployed a Floating LiDAR (FLS) System buoy and a Directional Wave Rider (DWR) buoy at the Talisk Offshore Wind site, approximately 30km north of the Isle of Lewis for a minimum period of 24 months. The deployment took place on 21 September 2024. Post deployment of the FLS and DWR, service activities be carried out onsite at approximately six-monthly intervals. Additional notice will be provided prior to service activities being undertaken.
Research Buoy Confirmation of Deployment Notification - Morlais Demonstration Zone.
Arven Offshore Wind Farm has deployed Passive Acoustic Monitoring (PAM) moorings in and around the Arven Offshore Wind Farm area to gather data on marine mammal activity.
TO DOWNLOAD THIS FILE, YOU MUST AGREE TO THE TERMS AND CONDITIONS "TERMS" NOTED AT THE FOOT OF THIS WEBSITE WHICH APPLY TO YOUR USE OF THIS WEBSITE AND TO USE OF THE FILE YOU HAVE CLICKED TO DOWNLOAD. IF YOU DO NOT AGREE TO THE TERMS, YOU WILL NOT BE ABLE TO DOWNLOAD THE FILE AND YOU SHOULD NOT USE THIS WEBSITE. TO CONFIRM YOUR ACCEPTANCE OF THE TERMS AND TO COMMENCE THE DOWNLOAD OF THE FILE, PLEASE CLICK THE "DOWNLOAD" CHECK BOX. IF YOU DO NOT AGREE TO THE TERMS, PLEASE CLICK THE "CANCEL" BUTTON. YOUR ATTENTION IS DRAWN TO CONDITION 3 NOTED BELOW WHICH FORMS PART OF THE TERMS IN RELATION TO OUR LIABILITY TO YOU.
Agree and download Cancel