Create Personalised Alerts
X

News








All Hazard Activity News

Clear

Eastern Green Link 2 – Offshore Geophysical Survey



The marine survey activities for EGL 2 are planned to commence from Peterhead, Scotland in December 2023 and continue in Scottish waters until approximately February 2024 before working south along the survey route to Bridlington. It is anticipated that the survey activities will commence from approximately 18th December 2023 in Peterhead and are due to be completed by the end of April 2024 in Bridlington.


Scottish Hydro Electric Transmission Plc and National Grid Electricity Transmission Plc are delivering the Eastern Green Link 2 (EGL 2) Project.

 

The EGL 2 project will play a vital role in achieving the UK and Scottish governments net zero targets and significantly increase the UK’s capacity for clean, green renewable power.

 

The survey works for EGL 2 precedes the installation of an electricity transmission link from the East coast of Scotland (Sandford Bay, Peterhead) to the East coast of England (South of Bridlington/ Flamborough Head) due to be completed in 2029.

 

The EGL 2 marine survey works are being carried out by GeoXYZ.

 

The area of work, pertaining to this Notice to Mariners (NtM) is illustrated in Figure 1 and Table 1, with the survey vessel contact details for each respective project found in Table 2. Contact details for the project Fisheries Liaison Officers are detailed below. The marine survey activities for EGL 2 are planned to commence from Peterhead, Scotland in December 2023 and continue in Scottish waters until approximately February 2024 before working south along the route shown in Figure 1 to Bridlington.

 

It is anticipated that the survey activities will commence from approximately 18th December 2023 and are due to be completed by the end of April 2024, subject to weather. The offshore works are to be conducted within the area shown by Figure 1 and coordinates detailed in Table 1.

 

The works consist of a detailed geophysical survey for the purposes of identifying potential unexploded ordnance. There are no intrusive works planned nor will there be any unexploded ordnance investigation or detonation works. The vessel will be towing equipment close to the seabed and will have restrictive maneuverability.

 

All vessels are requested to pass at a safe speed and distance, approximately 500 metres where possible, (COLREGs Rule 16 & 18) from the areas identified during marine survey operations. The survey vessel will be restricted in her ability to manoeuver and shall deploy towed sensors during geophysical survey operations only. The survey vessels will monitor VHF Channel 16 at all times. Mobile contacts for the vessels are listed at the end of this NtM.

See detailed map on our bulletin website
Show More

Buoyage Repair Campaign - Moray West Construction



This notice to mariners is to inform that Moray Offshore Windfarm (West) Limited (Moray West) has carried out repairs on the Moray West Construction Buoyage between 2 and 6 December 2023. Repairs have been carried out on the marker buoys of Site 1 and Special Mark MW1 has been re-deployed.


Marker buoys repair works

 

The scope of work includes the repair of unlit South Cardinal MW4, and the temporary removal of Special Mark MW1 from Site 1 to allow repairs of the data sensors. All marker buoys have been inspected, MW4 light replaced and MW1 has been re-deployed on Site.  

See detailed map on our bulletin website
Show More

Nearshore Water Sampling - Stromar Offshore Wind Farm



The survey vessel Seren Las will attend to a number of sampling stations along a single transect within the survey area presented. At each station water quality sampling will be undertaken.


Mariners are advised Stromar Offshore Wind Farm are undertaking nearshore water sampling during week commencing 11 December 2023 in the Moray Firth near Fraserburgh, Scotland. The survey works are expected to take between one and two days. The survey vessel Seren Las will attend to a number of sampling stations along a single transect.

See detailed map on our bulletin website
Show More

Bottom Mounted Passive Acoustic Monitoring deployment - Menter Môn Morlais



As part of the Marine Licence ORML1938 granted to Menter Môn Morlais, we are writing to you to notify you of the phase completion of scientific activity where notification is required on the below date: DATE: 06/12/2023


St Andrews University Sea Mammal Research Unit (SMRU) is conducting scientific research in the Morlais Demonstration Zone (MDZ). SMRU wishes to install equipment (Passive Acoustic Monitoring or PAM) on the seabed to gather acoustic data. This document provides information on the planned PAM deployments for the local fishing industry and other sea users in the area.

See detailed map on our bulletin website
Show More

Demarcation / Met-Ocean Buoys - Sofia Offshore Wind Farm



Mariners are advised that all Demarcation Buoys marking the perimeter of the Sofia Offshore Wind Farm array site and Met-Ocean Buoys deployed within the array site and along the Export Cable Route have now all been successfully deployed.


From around the 12th December 2023 for a period of approx.14 days (weather permitting), the Forth Warrior will service and inspect the installed buoyage within the Sofia Offshore Wind Farm Array and also within the Export Cable Route from Nearshore Marske by The Sea out to the SOWF Array itself.

 

The tables above above provide a summary of the locations where the Forth Warrior shall be operating during the campaign.

 

The Met-ocean Buoys in position at KP2 & KP130 on the Export Cable Route will be permanently recovered.

 

There will also be an additional three Met-ocean buoys installed within the Sofia Offshore Windfarm Array as outlined above.

 

The Forth Warrior will be working daylight hours only and shall be monitoring VHF 16 during the scope of the works and shall also be exhibiting the correct day shapes and night lights for a vessel restricted in ability to manoeuvre.

 

***NAVIGATIONAL WARNINGS 11th Sept 2023 and 21st October 2023***

 

Mariners are advised that Met Ocean Buoys at KP2 (Position 54° 36.508N x 000° 00.175W) and KP40 (Position: 54° 40.524' N x 000° 26.735' W) have been reported as off station.

 

The Metocean Buoys at KP2 and KP40 have been successfully recovered and are now in Hartlepool awaiting inspection and then reinstatement (date TBC).

 

As it is currently unknown if the mooring is attached to these buoys, please avoid the KP2 and KP40 coordinates highlighted within the table above by at least 100m until further notice.

 

Mariners are requested to refrain from entering and transiting through the construction area as demarcated by these demarcation buoys.

 

The table below provides a summary of each Cardinal and Special Mark Buoy deployed at the SOWF array, including target coordinates in WGS84 Degrees Decimal Minutes and a description of top mark and lantern characteristics. The Demarcation Buoys will be deployed for a period of approximately three years.  

Buoy ID Latitude Longitude Lantern Characteristics Lantern  Colour
North Cardinal N1 55° 08.133’ N 002° 09.518' E

VQ 0.5s

White
North Cardinal N2 55° 08.436’ N 002° 13.418’ E

Q 1s

White
East Cardinal E1 55° 06.480’ N 002° 16.929’ E  

Q(3) 10s

White
East Cardinal E2 55° 02.571’ N 002° 23.925' E

VQ(3) 5s

White
East Cardinal E3 54° 59.043’ N 002° 30.269’ E

Q(3) 10s

White
East Cardinal E4 54° 55.085’ N 002° 26.631’ E

VQ(3) 5s

White
East Cardinal E5 54° 51.523’ N 002° 20.709' E

Q(3) 10s

White
South Cardinal S1 54° 49.725’ N 002° 16.726' E

Q(6) + LFL 15s

White
West Cardinal W1 54° 51.829’ N 002° 12.194' E

Q(9) 15s

White
West Cardinal W2 54° 56.229’ N 002° 03.867' E

VQ(9) 10s

White
West Cardinal W3 55° 00.623’ N 001° 56.196' E

Q(9) 15s

White
West Cardinal W4 55° 04.648’ N 002° 02.498' E

VQ(9) 10s

White
Special Mark SP1 55° 02.741’ N 001° 59.756' E

FI Y 5s

Yellow
Special Mark SP2 55° 06.569’ N 002° 05.756' E

FI Y 5s

Yellow
Special Mark SP3 55° 04.525’ N 002° 20.428' E

FI Y 5s

Yellow
Special Mark SP4 55° 00.617’ N 002° 27.418' E

FI Y 5s

Yellow
Special Mark SP5 54° 56.871’ N 002° 29.602' E

FI Y 5s

Yellow
Special Mark SP6 54° 53.324’ N 002° 23.621' E

FI Y 5s

Yellow
Special Mark SP7 54° 54.030’ N 002° 08.026' E

FI Y 5s

Yellow
Special Mark SP8 54° 58.427’ N 001° 59.703' E

FI Y 5s

Yellow

 

The table below provides a summary of the Met-ocean Buoys deployed at the SOWF Array.

 

Site Location Buoy Position Latitude Longitude Deployment Date Recovery Date
SOWF Array North 55° 5.392' N 002° 12.993' E June 2023 June 2026
SOWF Array South 54° 54.987' N 002° 15.585' E June 2023 June 2026
SOWF Array East 54° 58.160' N 002° 22.521' E Nov 2023 TBC
SOWF Array West 55° 01.528' N 002° 04.052' E Nov 2023 TBC
SOWF OCP 55° 00.439' N 002° 14.798' E Nov 2023 TBC

 

The table below provides a summary of the Met-ocean Buoys deployed alone the SOWF export cable route.

 

Site Location Buoy Position Latitude Longitude Deployment Date Recovery Date
Export Cable KP2 (from shore) 54° 36.508' N 1° 0.175' W June 2023 Oct 2023
Export Cable KP8 54° 36.584' N 0° 54.674' W June 2023 TBC
Export Cable KP40 54° 40.524' N 0° 26.735' W June 2023 TBC
Export Cable

KP130

54° 50.543' N 0° 54.689' E June 2023 Oct 2023
See detailed map on our bulletin website
Show More

Post-Lay Cable Burial Works - Sofia Offshore Wind Farm



All Mariners are advised that the Normand Pacific continues with post-lay cable burial works on the Sofia Export Cable. The exact finish dates will be dependent on the prevailing weather conditions and work progress.


The post-lay burial (PLB) vessel “Normand Pacific” will be present for the entire scope of works. The Normand Pacific will transit from Middlesborough Support Depot and remain on site for 24hr operations. The PLB vessel will make passage to and from the support depot as required based on operational constraints.

 

The Normand Pacific will firstly transit to approx. Kilometre Point (KP) 36 to perform post lay burial activities until KP 130, and then will transit to KP 3 to cover the remaining section, KP 3-36. During transit along the cable route the vessel will remain within the exclusion zone.

 

The PLB will be supported by those guard vessels outlined in the table above.  Guard vessels will remain be onsite 24 hours per day to monitor the export cable until circa Q1 - 2024.

 

Exclusion zone coordinates for the 2023 post-lay burial works are identified within the table above and remain the same for those during cable lay works as outlined in NtM 11 (rev 02).

 

The coordinates of the guard vessel locations for the post-lay burial works for Campaign 1 are detailed within the table above and attached NtM.

Please be aware that by virtue of mode of operation and the equipment deployed, the Normand Pacific will at times be Restricted in their Ability to Manoeuvre as defined under COLREGS (International Regulations for Preventing Collisions at Sea 1972 and shall be exhibiting the correct day shapes / lights for vessels restricted in ability to manoeuvre.

 

Mariners are requested to remain where possible 500m from vessels and equipment. Fishing vessels are requested to pass at a safe speed and distance and remain outside of the exclusion area identified. All vessels can be contacted on VHF 16 for further information as required reference proximity/nearby operations etc.

 

Mariners are advised of the following vessels operating at the Sofia Offshore Wind Farm (SOWF).

 

Vessel Name Vessel Type Length (m) Beam (m) Draft (m) Gross Tonnage (T) Call Sign MMSI Number
Normand Pacific Post-Lay Cable Burial Vessel 122 23 7.0 9778T LAXI7 257743000
Sancta Maria Guard Vessel 20.37 6 3.03 106 2FOV7 235093015
Inge Guard Vessel 29.7 6.2 3.1 192 YJSN5 577097000
Jason II Guard Vessel 26.02 6.01 3.21 127 MJFY4 232036020
Dolfijn Guard Vessel 27 6.2 3.1 99 YJQL8 576697000
Mary Ann Guard Vessel 32.7 7 3.6 53 YJTV2 577256000
Venus II Guard Vessel 24 7.4 3.15 145 HP9337 370046000
Walvis Guard Vessel 27 6.4 3.32 108 YJQG3 576448000
Flamingo Guard Vessel 31 7 3.5 159 YJVW2 576259000
Haulbowline Guard Vessel 22.3 7 2.7 88 MEZW9 232021354
Star of Hope Guard Vessel 23.9 7.2 3.4 101 MKDN2 232038483
Enterprise II Guard / Scout Vessel 26 9.2 4.7 421 MPFN7 232006130
Artemis Guard / Scout Vessel 3 6.3 3.2 75 2SNV 235006582
See detailed map on our bulletin website
Show More

Scour Protection Installation Works - Sofia Offshore Wind Farm



All Mariners are advised that the Braveness continued and completed scour protection works at various Wind Turbine Generator (WTG) locations within the Sofia Offshore Wind Farm Array. The Braveness has now departed site.


The Nordness will joining the campaign later in January 2024 until approximatelty 1st March 2024 and will be transiting to the site from ports located outside of the UK (The Netherlands and Norway).

 

Two layers (armour & filter) are foreseen to be installed for the scour protection: The armour layer will be installed at all 100 WTG locations and the filter layer will be installed at 88 of the WTG locations.

 

All Mariners are requested to remain outside the works area are identified within the table above and pass at a safe speed and distance. Mariners should be aware there will be a reduction in navigable depth of up to 9% at all 100 WTG locations following the installation of the scour protection.

 

Vessel information in relation to these scope of works are outlined below;

 

Vessel Name Vessel Type Length (m) Draught (m) Call Sign MMSI Number
Nordness Subsea Rock Installation Vessel 166.70 10.51 PHOG 244962000
Enterprise II Guard / Scout Vessel 26

4.7

MPFN7 232006130

 

See detailed map on our bulletin website
Show More

Sofia OWF - Rock Placement Works



All Mariners are advised that rock placement works for the Sofia Export Cable are expected to commence on or around 1st January 2024.


The dynamic positioning fall pipe vessel (DPFV) “Rockpiper” will be carrying out the entire scope of works. The Rockpiper will transit to / from Norway during this period. The vessel will be supported by the guard vessels, as outlined below.  Operations are expected to last into March 2024.

 

Exclusion zone coordinates for the rock placement works are identified within the above table and remain the same for those during cable lay and post-lay cable burial works as outlined in previous NtMs. The table below shows the coordinates of the guard vessel locations for the rock placement works for Campaign 1 (C1).

 

Please be aware that by virtue of mode of operation and the equipment deployed, the Rockpiper will at times be Restricted in their Ability to Manoeuvre as defined under COLREGS when carrying out the works.

 

The exact start and finish dates will be dependent on the prevailing weather conditions and work progress.

 

Mariners are requested to remain where possible 500m from vessels and equipment. Fishing vessels are requested to pass at a safe speed and distance and remain outside of the exclusion area identified. During these works the Rockpiper (DPFV) will have restricted manoeuvrability as it carries out the rock placement works. All vessels can be contacted on VHF 16 for further information as required reference proximity/nearby operations etc.

 

Please note that rock placement will cause a reduction of navigable depth but this is unlikely to exceed a 10% reduction. The actual positions of rock placement will be updated as part of the as-built information of the project.

 

The vessel will be monitoring channel VHF 16 and shall also be exhibiting the correct day shapes / lights for vessels restricted in ability to manoeuvre.

 

Mariners are advised of the following vessels operating at the Sofia Offshore Wind Farm (SOWF).

 

Vessel Name Vessel Type Length (m) Beam (m) Draft (m) Gross Tonnage (T) Call Sign MMSI Number
Rockpiper DPFV 158.6 36/40.5 9.4 30601 5BML3 209449000
Sancta Maria Guard Vessel 20.37 6 3.03 106 2FOV7 235093015
Inge Guard Vessel 29.7 6.2 3.1 192 YJSN5 577097000
Jason II Guard Vessel 26.02 6.01 3.21 127 MJFY4 232036020
Dolfijn Guard Vessel 27 6.2 3.1 99 YJQL8 576697000
Mary Ann Guard Vessel 32.7 7 3.6 53 YJTV2 577256000
Venus II Guard Vessel 24 7.4 3.15 145 HP9337 370046000
Walvis Guard Vessel 27 6.4 3.32 108 YJQG3 576448000
Flamingo Guard Vessel 31 7 3.5 159 YJVW2 576259000
Haulbowline Guard Vessel 22.3 7 2.7 88 MEZW9 232021354
Star of Hope Guard Vessel 23.9 7.2 3.4 101 MKDN2 232038483
Enterprise II Guard / Scout Vessel 26 9.2 4.7 421 MPFN7 232006130
Artemis Guard / Scout Vessel 3 6.3 3.2 75 2SNV 235006582
See detailed map on our bulletin website
Show More

Seawatch Wind Lidar Buoys - Caledonia Offshore Wind Farm



Deployment of two (2) Floating Seawatch Wind LiDAR buoys in the Moray Firth for the acquisition of Wind and Metocean Data for a period of 24 months.


On the 3rd of June 2023, Fugro deployed two (2) Floating Seawatch LiDAR buoys within the Caledonia Offshore Wind Farm site for the acquisition of Wind and Metocean Data. The two buoys are intended to remain in-situ for a minimum period of 24 months.

*Primary buoy COWF-SWLB080 temporarily replayed by lit buoy during repair (as of 6th December)*

Mariners are advised to maintain a 500 m clearance from the deployed equipment.  Operations were completed by the Fishing vessel ‘MS Elisabeth’.

 

The buoys will remain in situ until June 2025, the exact removal date will depend on weather and be determined at a later stage. A separate NtM will be issued for the removal activity.

 

Details on the Seawatch Wind LiDAR (3.0) Buoys including navigational safety features and mooring layout design are provided in the attached NtM (V3). 

 

See detailed map on our bulletin website
Show More

Met Mast Special Mark light repair - Moray Offshore Windfarm (East) Limited



Please be advised that Moray Offshore Windfarm (East) Limited (Moray East) will undergo repairs to reinstate the light at the special mark buoy around the remaining subsea structure at the meteorological mast (Met Mast) on the 6th December 2023.


Please be advised that Moray Offshore Windfarm (East) Limited (Moray East) will undergo repairs to reinstate the light at the special mark buoy around the remaining subsea structure at the meteorological mast (Met Mast) on the 6th December 2023.

 

The works to repair the Met Mast Special Mark buoy light will be carried out by the Forth Jouster.

 

Please be aware that while navigating the area to keep an extra look out for the unlit Met Mast Special marker buoy during the hours of darkness and reduced visibility, until such a time as the buoy is repaired. Please also note that the Met Mast is currently marked by a virtual AtoN.

 

Please be aware that, during the survey activities, by virtue of its mode of operation the vessel will be Restricted in her Ability to Manoeuvre (RAM) as defined under COLREGs (International Regulations for Preventing Collisions at Sea 1972, Rule 3). Masters of vessels are therefore requested to maintain their vessels and gears at a minimum safe passing distance from the vessel of 500 metres when it is undertaking work and showing the appropriate shapes and lights in accordance with COLREGs Rule 27. In order to not compromise the safety of the Vessel, their crew, and their ability to undertake its contracted works, fishermen who have static fishing gears deployed within 500 m from the Met Mast location (see Table 1 and Figure 1) are requested to provide the coordinates of such deployed gears in DMS and details of whether the surface markers used are visible at all states of visibility to Alex Winrow-Griffin (Brown & May Marine) using the contact information below (Section 58 of the Merchant Shipping Act 1995). Fishermen who have static gears deployed beyond 12 nm are reminded that static gear must be marked in accordance with Commission Implementing Regulation (EU) No. 404/2011

See detailed map on our bulletin website
Show More

Construction of Wind Farm - Triton Knoll



Activities related to the development of the Triton Knoll wind farm continue, as detailed below. For background information visit: http://www.tritonknoll.co.uk. Mariners are advised that the asset installation phase of the Triton Knoll OWF is now complete.


Mariners are advised that the following vessels are expected to commence operations at the Triton Knoll Offshore Wind Farm (TKOWF) as outlined within recently issued NtM's

 

The Windcat 22 will replace the Windcat 11 temporarily, whilst the Windcat 11 goes for a refit. A further NtM will be issued once the Windcat 11 returns.

 

Vessel Name

Type

Call Sign

MMSI

IMO

Operating Port

Commence Date

Windcat 22 Crew Transfer Vessel 2CU59 235075935 - Grimsby

04/10/2023

 

Mariners are advised that the following vessels continue to be active at the Triton Knoll Offshore Wind Farm (TKOWF) as outlined within previously issued NtM's:

Vessel Name

Type

Call Sign

MMSI

IMO

Operating Port

Commence Date

Windcat 11 Crew Transfer Vessel 2BIS9 235066459 N/A Grimsby 14/12/2020
Esvagt Havelok Service Operations Vessel OYFR2 219026496 9878981 Grimsby 25/09/2021
Windcat 40 Crew Transfer Vessel MBCT7 232008399 - Grimsby 03/09/2023

 

All vessels can be contacted via VHF channel 16 when operational in field.

 

*** Note ***

 

All 90 WTG's have now been fully installed, whilst WTG commissioning and service continues.

All Export Cables are fully installed/buried and need to be deemed live/energised.

All Inter Array Cables are fully installed and buried and need to be deemed live/energised.

Whilst the main installation works have been completed, major construction commissioning works are continuing.

 

*** Note ***

 

Whilst TKOWFL is reopening the site to fishing from the 14th December 2021, TKOWFL kindly request that all fishermen intending to fish within the boundaries of the Triton Knoll wind farm, contact the Triton Knoll control room prior to entering and exiting the field, and inform them of their fishing intentions.

 

This precaution is requested to safeguard all vessels operational at the TKOWF site (including fishing vessels) and your cooperation, to ensure the safety of all parties is appreciated. The following contact details should be used when notifying the Triton Knoll control room of fishing activity:

 

Control Room Manager: Derek Whyte

Radio: VHF channel 16

Callsign: TK MCC

Phone: +44 1793 896250

Email: tkcr@rwe.com

 

*** Note ***

 

Application of Triton Knoll Wind Farm Safety Zones During Construction

The Secretary of State has granted the Application of Safety Zones on the Triton Knoll Wind Farm Project as follows:

  • 500m “rolling” safety zones around any structure where construction is being undertaken (as indicated by the presence of construction vessels).
  • 50m pre-commissioning safety zones surrounding partial structures or completed structures prior to commissioning.

Mariners are advised that all foundations monopiles have been installed and all inter-array and export cables have been installed.

 

Navigation Warning - 08th January 2021

 

Mariners are advised that the remnants of a Wave Rider Buoy sinker weight and partial rigging are located within the Triton Knoll Offshore Wind Farm Construction site at the following location;

 

53° 30.442N 000° 50.564E

 

It is advised that the partial rigging could potentially be floating up to 9.7m above the seabed, reducing the navigable safe water in the immediate area to 10m LAT.  Mariners are advised to avoid the indicated position by 250 metres.

 

Possible Dangers to Navigation - Properties of the polypropylene show that the rope is buoyant, this makes the line sensitive for thruster currents. Taking the site water depth into consideration (19.7m LAT) and the maximum expected height above seabed of the rope 9.7m the line is expected to be floating submerged at approximately -10m LAT. In addition, it is noted that over time sediments will be trapped between the fibres and the heavier rope may finally sink. The polypropylene rope may impose a risk to foul propellers / propulsion of vessels due to the buoyant nature of the rope. As the rope is submerged at a depth of ~-10m LAT the risk is considered minimum for vessels with a shallow draught (<5m) and medium for a vessel with a deeper draught (>5m). Over time sediments will be trapped between the fibres and the heavier rope may finally sink thereby reducing the risk to propellers/propulsion of vessels. The clump weight itself (chain) is expected to have sunk into the seabed and has no significant height above seabed. In addition, the edges of the clump weight are mostly rounded (chain), the risk the clump weigh imposes to fishing activities/gear is therefore considered to be minimal.

 

Navigation Warning - 16th March 2021

 

Mariners are advised that two UXO targets have been confirmed within the Triton Knoll Offshore Wind Farm Array.

 

Mariners are advised that the two confirmed targets are located within 20 metres water depth (LAT) and a 10 metre radius exclusion zone is required around each target.  The following table provides the coordinates and a description for each target.

 

Description of Target Latitude Longitude

Water Depth

(LAT) Metres

Required Exclusion

Zone (Metres Radius)

Archaeological - The item is thought to be an air-delivered bomb.  It appears to be in a stable condition and is resting on the seabed.  Marine growth and concretion cover the body, indicating it has been in situ for a significant duration. The tail section of the bomb is missing, which is typical of unexploded bombs from WWII found in these circumstances and there is a significant hole in the case. The dimensions and characteristics gathered are consistent with a 500kg German bomb. Considering the state of the bomb the Net Explosive Quantity of the bomb is likely to be <5kg. 53°31'50.249"N 00°47'45.908"E 20 10
Archaeological - The item is thought to be an air-delivered bomb.  It appears to be in a stable condition and is resting on the seabed.  Marine growth and concretion cover the body, indicating it has been in situ for a significant duration. The tail section of the bomb is missing, which is typical of unexploded bombs from WWII found in these circumstances and there is a significant hole in the case. The dimensions and characteristics gathered are consistent with a 500kg German bomb. Considering the state of the bomb the Net Explosive Quantity of the bomb is likely to be <5kg. 53°31'49.895"N 00°47'45.115"E 20 10
See detailed map on our bulletin website
Show More

Boulder\Debris Relocation Campaign - Dogger Bank B + C



The Offshore Supply Vessel, OLYMPIC ELECTRA, will perform boulder clearance operations within Dogger Bank B and C Array Areas and the Dogger Bank C Export Cable Route.


The works will be performed in a single campaign, commencing on the 01st September 2023 and continuing until approximately 30th December 2023. The works will be continuous, 24 hours a day. Charts of the DBB Array / DBC Array and Export Cable Route areas including are provided below.

 

The operations include the relocation and/or removal of subsea obstructions such as boulders and debris by means of a subsea grab mounted on a Utility ROV (UTROV). During operations, the OLYMPIC ELECTRA will be restricted in its ability to manoeuvre as defined under COLREGs (International Regulations for Preventing Collisions at Sea 1972) and will display the appropriate day shapes and lights. The vessel will also transmit an Automatic Identification System (AIS) message. It is requested that all vessels maintain a minimum of 500m separation distance from the Offshore Supply Vessel and pass at reduced speed

See detailed map on our bulletin website
Show More

Diving Works - Moray West Nearshore Export Cable Installation



As part of the installation works of two offshore export cables for Moray West Offshore Wind Farm, Moray West and their contractor Nexans intend to undertake diving works near Portsoy bay. This includes the post-cable installation works on the HDD duct (offshore) exit and removal of concrete mattresses, rock bags and marker buoy that are already installed at the nearshore area.


Work on the duct and surrounding area will be undertaken by divers connected to diving support vessel C-Odyssey operated by Leask Marine. During diving operations this vessel will be positioned via a four-point anchor mooring spread. For diving vessel moorings, for the avoidance of any fishing gear or buoyed items posing risk of wire entanglement based on anchor positions.

 

Moray West intends to commence diving works no earlier than 16th of October 2023. This diving campaign is expected to reach completion late November 2023.

 

The above dates include some estimated/expected weather delays, however, this activity may be subject to further extension of works. Scope of work to include deployment of the diving vessel four-point mooring system to support two HDD duct ends post-cable installation works at nearshore, utilising the diving vessel C-Odyssey (supported by C-Defender vessel) and will remain in place until all nearshore diving works are complete.

 

Please be aware that, during the diving work activities, by virtue of its mode of operation the Dive vessel C-Odyssey and support vessel C- Defender will be Restricted in her Ability to Manoeuvre (RAM) and will also display appropriate day shapes while diving operations are taking place as defined under COLREGs (International Regulations for Preventing Collisions at Sea 1972, Rule 3). Masters of vessels are therefore requested to maintain their vessels and gears at a minimum safe passing distance from the vessel of 500 metres when it is undertaking work and showing the appropriate shapes and lights in accordance with COLREGs Rule 27 In order to not compromise the safety of the C-Odyssey and C- Defender and their crew, and the ability to undertake its contracted works.

See detailed map on our bulletin website
Show More

Offshore Construction - Dogger Bank A Offshore Wind Farm



Offshore Construction of the Dogger Bank A Offshore Wind Farm commenced on the 18th of March 2022. The development of the windfarm is made up of several elements - current ongoing elements  are described below in the 'full notice' and in the attached file. This notice will be updated weekly, giving information on the progress and resources involved in the offshore project.


The development of the windfarm is made up of several elements - current ongoing elements include:

 

The Offshore installation vessel, HLV Seaway Strashnov has completed installation of all 95 monopile foundations, within the Dogger Bank A construction area.  

 

The installed monopiles will be marked with temporary lighting with the following characteristics:

 

•           Flashing (Fl) Yellow (Y) 2.5 seconds (s)

•           IALA Availability Category 2 (not less than 99.0%)

•           360° visibility – up to two lights per structure may be used to achieve this

•           At least 2 nm range.

 

The HLV Alfa Lift will continue TP installation in the Dogger Bank construction area.

 

Following Storm Babet the temporary lighting on all 38 installed monopiles is currently inoperative (NtM LF500013-MIP-DOG-NOT-0026 NtM-DBA Monopiles unlit refers)

 

Construction Support Activities

 

The Offshore Construction Support Vessels, VOS Start, Edda Sphynx, Edda Boreas, Grampian Tyne, Grampian Derwent and Norside Cygnus will carry out construction support activities within Dogger Bank A construction site.

 

The works will be performed in a single campaign, commencing on the 6th of November 2022 and continuing until approximately 30th September 2023. The works will be continuous, 24 hours a day.

 

IAC Installation and Post-lay Burial Operations

The Cable Lay Vessel Viking Neptun has completed the 2nd Inter Array Cable lay campaign this week. The Cable burial vessel Livingstone will continue to bury the surface laid IA Cables. The Norside Cygnus continueswith Termination and Testing of cables.

 

During operations, the Livingstone and Norside Cygnus  will be restricted in their ability to manoeuvre as defined under COLREGs (International Regulations for Preventing Collisions at Sea 1972) and will display the appropriate day shapes and lights. The vessels will also transmit an Automatic Identification System (AIS) message. 

 

Wind Turbine Generator (WTG) Installation

The Jack-up WTG Installation Vessel, Voltaire, will install wind turbine generators (WTG) within the Dogger Bank A construction area.

 

The works will commence on the 18th of July 2023, continuing until approximately Q2 2024.  The works will be continuous, 24 hours a day.  A running list of the completed WTG installations and the next locations to be installed is presented in the Installation progress table below.

See detailed map on our bulletin website
Show More

Monopiles Unlit - Dogger Bank A Offshore Windfarm



Dogger Bank A Offshore Windfarm has installed all 95 Foundation Monopiles (MP). Transition Pieces (TP) have been installed at 57 of these locations and Wind Turbine Generators (WTG) have been installed at 6 locations. Prior to TP installation, the installed Monopiles are marked with temporary lighting


UPDATE: 34 monopiles remain unlit. Monopiles P41 and P42 are now fitted with a Transition Piece.

P32 and D01 - lights have been replaced. 

 

During Storm Babet, the temporary navigation lights on all 38 of the MPs were damaged and the lights are inoperative. Table 2 below provides coordinates of the monopile locations where temporary navaids are missing or damaged. Figure 3 shows a monopile without a TP installed and with a temporary navaid in place.

 

A programme to repair and replace the temporary navigation lights is being undertaken. Once all are restored an update will be published and this NtM witdrawn.

 

The DBA Guard vessels will broadcast a safety message alerting vessels of this hazard.

 

All vessels are requested to navigate with particular caution in the vicinity of the Dogger Bank A construction site and where possible are requested to remain outside the construction site boundary

See detailed map on our bulletin website
Show More

Site Investigation Survey - Norfolk Windfarm Boreas, Vanguard West, Vanguard East



Please be advised of this notice advising mariners of the site investigation survey of the Norfolk Boreas, Vanguard East and Vanguard West windfarms and export cable. The Noordhoek Pathfinder and Geo Ranger will be completing survey operations in UK waters. The surveys started in March 2023 and are scheduled to last until the end of April 2024 (subject to weather and additional scopes).


Show More

FLidar buoy deployment and Trawl Resistant Bottom Mounted operations - NAREC met mast



EOLOS intends to deploy a Floating Lidar buoy (FLS200) unit E17 for the completion of a pre-validation campaign. The buoy will be installed near the NAREC met mast for the duration of (approximately) 1 month until a third party confirms that the validation is completed. As part of the deployment activities, EOLOS will deploy and retrieve several times a Trawl Resistant Bottom Mounted (TRBM) to practice the operational aspects of such operations.


Show More

Topside Installation Works OSP1 and OSP2 - Moray Offshore Windfarm (West) Limited



This notice to mariners is to inform that Moray Offshore Windfarm (West) Limited (“Moray West”) will be commencing Offshore Substation installation works at the Moray West Offshore Wind Farm (Windfarm Marine Licence MS-00009774) from 26 November 2023. The work comprises of J tube cage installation, OSP-TP, and Topside installation at Monopile locations E06 (OSP #1) and M11 (OSP #2).


The works are anticipated to commence on 26 November 2023, and the duration of the works is forecasted to be completed by mid/ end January 2024. The exact duration and completion date will depend on the weather and progress of the works

See detailed map on our bulletin website
Show More

Cable installation Campaign OEC-2 and OEC-1 – Edda Fjord Trenching Vessel December 2023



This notice to mariners is to inform that Moray Offshore Windfarm (West) Limited (Moray West) are planning to introduce a second trenching vessel (Edda Fjord) to commence offshore export cable trenching operations circa 10th December 2023.


The ‘Edda Fjord’ vessel is expected to arrive on site circa 10th December 2023 to support ‘Nexans Skagerrak’ vessel to complete offshore export cable (OEC) trenching works over pre-laid offshore export cables OEC-2 and OEC-1. The overall duration is expected to be approximately 2 months.

 

Any sections of the routes where the cables require remedial rock protection will be performed during a separate remedial campaign. This will be subject to a separate NtM when details on remedial campaign(s) are known. 

See detailed map on our bulletin website
Show More

Offshore Export Cable Routes–Cable installation Campaign OEC2 & OEC1-Moray Offshore Windfarm West



This notice to mariners is to inform that Moray Offshore Windfarm (West) Limited (Moray West) are planning to commence offshore export cable laying and trenching operations (using two separate vessels) circa 13th October 2023.


The ‘Nexans Skagerrak’ vessel is expected to arrive on site on 13rd October 2023 to complete offshore export cable (OEC) installation works including cable pull in at landfall, cable lay, repair joint, cable wet storage on OEC2 and cable trenching works on OEC2 and OEC1. The overall duration is expected to be approximately 3 months. The ‘Nexans Aurora’ vessel is expected to arrive on site on 1 st November 2023 to complete cable installation works including cable pull in at landfall, cable lay, cable wet storage on OEC1. The overall duration is expected to be approximately 1 month.

 

Please be aware that, during the Cable lay and trenching work activities, by virtue of its mode of operation the ‘Nexans Skagerrak’ and ‘Nexans Aurora’ vessels will be Restricted in their Ability to Manoeuvre (RAM) and will also display appropriate day shapes while conducting Cable lay and trenching operations are taking place as defined under COLREGs (International Regulations for Preventing Collisions at Sea 1972, Rule 3)

See detailed map on our bulletin website
Show More

Geophysical Survey - National Grid - Sea Link - Aldeburgh, Suffolk and Pegwell Bay, Ramsgate, Kent



Geophysical survey, in 5 distinct areas in offshore and coastal waters between Aldeburgh, Suffolk and Pegwell Bay, Ramsgate, Kent. The survey is being undertaken on behalf of National Grid’s Sea Link Project, a proposed HVDC electricity transmission connection between the two locations. Operations are expected between November 2023 and January 2024.


 

 

Geophysical surveys utilising towed sensors, used in offshore areas and coastal sea waters between Aldeburgh, Suffolk and Pegwell Bay, Ramsgate, Kent.  The survey is being undertaken on behalf of National Grid’s Sea Link Project, a proposed HVDC electricity transmission connection between the two locations.  The geophysical survey work will be carried out by Next Geosolutions using survey vessels Shore Presence and Shore Possibility.  Forecasted survey start dates for each area are shown below and are subject to change. 

  • Area 1 – 1st November 2023 

  • Area 2 – 10th November 2023 

  • Area 3 – 1st December 2023 

  • Area 4 – 8th December 2023 

  • Area 5 – 15th December 2023 

Surveys are expected to be completed by early January 2024.  All vessels shall pass at a safe speed and distance, whilst fishing vessels are asked to remain at a safe distance (approximately 500 metres where possible) (COLREGs Rule 16 & 18) from the areas identified during marine survey operations. The aforementioned survey vessels will be restricted in her ability to manoeuvre and shall deploy towed sensors during geophysical survey operations only. The survey vessels will monitor VHF Channel 16 at all times. Mobile contacts for the vessels are listed at the end of this NtM. 

See detailed map on our bulletin website
Show More

Notice to Mariners - Norfolk Vanguard West



Geotechnical vessels will be operating in the Norfolk Vanguard West Offshore Wind Farm site. A total of 78 x borehole locations will be visited by the vessels.


Show More

Cable Landfall and Cable Lay Works - Sofia Offshore Wind Farm



All Mariners are advised that all works to reinstate the HDD trenches out to KP3 are suspended until Q2 – 2024. This means that the spoil heaps from 2023 back hoe excavation works will now remain in situ over the Winter 2023 / Spring 2024, although a level of natural backfill is expected over this period.


The 2 Export Cables & 1 Fibre Optic Cable (all bundled) have been installed into the HDD ducts at Landfall (Marske by The Sea). 

 

Guard vessels will remain be onsite 24 hours per day to monitor the export cable until circa Q1- 2024.

 

Exclusion zone coordinates for 2023 cable pull-in and cable lay works are detailed within the table above and attached Notice to Mariners (NtM).

 

The coordinates of the guard vessel locations for the cable pull-in and cable lay works for Campaign 1 are detailed within the table above and attached NtM.

 

Mariners are requested to remain where possible 500m from the vessels and leave a wide berth during the installation operations. Fishing vessels are requested to pass at a safe speed and distance and remain outside of the exclusion area identified.

 

Vessels will be monitoring VHF 16 during the scope of the works and shall also be exhibiting the correct day shapes/ lights and flag for vessels engaged in diving operations and restricted in ability to manoeuvre.

 

Special Marker Buoys (SMB) will be in place to mark the HDD works area and will remain in place until completion of the export cable landing activities. The locations of these SMBs are detailed in the above table and attached NtM.

 

***Within the working area there may be a temporary reduction in navigable depth up to 2m due to excavated material being placed in spoil heaps***

 

***Please note that the Ocean Energy (Multicat) has recovered 3 of the 4 (A / B / D) anchors from the seabed nearshore HDD Pits and only one anchor remains in situ on the seabed at the HDD Pit in position “C”***

 

The Ocean Energy (Multicat) may attempt to recover the remaining anchor (C) from the seabed nearshore HDD Pits.

 

Mariners are advised of the following vessels commencing operations at Sofia Offshore Wind Farm (SOWF).

 

Vessel Name Vessel Type Length (m) Beam (m) Draft (m) Gross Tonnage (T) Call Sign MMSI Number
Sancta Maria Guard Vessel 20.37 6 3.03 106 2FOV7 235093015
Inge Guard Vessel 29.7 6.2 3.1 192 YJSN5 577097000
Jason II Guard Vessel 26.02 6.01 3.21 127 MJFY4 232036020
Dolfijn Guard Vessel 27 6.2 3.1 99 YJQL8 576697000
Mary Ann Guard Vessel 32.7 7 3.6 53 YJTV2 577256000
Venus II Guard Vessel 24 7.4 3.15 145 HP9337 370046000
Walvis Guard Vessel 27 6.4 3.32 108 YJQG3 576448000
Flamingo Guard Vessel 31 7 3.5 159 YJVW2 576259000
Haulbowline Guard Vessel 22.3 7 2.7 88 MEZW9 232021354
Star of Hope Guard Vessel 23.9 7.2 3.4 101 MKDN2 232038483
Enterprise II Guard / Scout Vessel 26 9.2 4.7 421 MPFN7 232006130
Artemis Guard / Scout Vessel 23 6.3 3.2 75 2SNV 235006582

 

The table below also provides the position and description of any equipment/asset/item that will remain in place following demobilisation of the Ievoli Ivory.

 

Location Equipment and Description Latitude Longitude Approximate Depth (LAT)
A

Concrete mattresses

3 of 5.95 m x 2.95 m x 0.30 m

54°38.544’ N 000°35.147’W 55m
B

Concrete mattresses

1 of 5.95 m x 2.95 m x 0.30 m

54°38.572’ N 000°35.142’W 55m
C

Concrete mattresses

2 of 5.95 m x 2.95 m x 0.30 m

1 of 5.55 m x 2.95 m x 0.50 m

54°48.144’ N 000°37.515’E 74m
See detailed map on our bulletin website
Show More

Vessel Traffic Survey - Thistle Wind Partners proposed Ayre (NE2) Offshore Wind Farm



Please be advised that KMS Karelle will be undertaking a Vessel Traffic Survey of the proposed Ayre (NE2) Offshore Wind Farm lease option areas, on behalf of Thistle Wind Partners (TWP). The purpose of this Notice to Mariners (NtM) is to outline the working area for the survey vessel at the location, as well as their scope of work. The survey will utilise the vessel KMS Karelle.


A marine vessel traffic survey is due to be undertaken for the proposed Ayre Offshore Windfarm project. The survey will be undertaken from one survey vessel, KMS Karelle, and will involve the collection of data of detected vessels and marine users through use of onboard radar, AIS and visual survey methods.

 

The survey will collect data within a proposed vessel roaming area within the project array area. 

 

The survey vessel will roam and/or remain nominally static within the area for approximately 14 days depending on weather conditions. The survey may be extended beyond 14 days depending on weather conditions, at which point further notification will be provided. Dates may be subject to change. The survey vessel will operate on a 24hr basis and display appropriate navigational lights at all times during operations.

See detailed map on our bulletin website
Show More

Shetland Renewables Project - Yell HVAC



Mariners are advised that SSEN will be conducting seabed sampling in Yell Sound as part Shetland Renewables Project.


Marine operations will commence no earlier than Thursday 23rd November, for a duration of approximately three weeks. Operations will be conducted from the vessel Roman Rebel. During operations the Roman Rebel will deploy sampling and video recording equipment to the seabed. The vessel will be operating in DP Mode.

 

The operation will be carried out continuously, 24 hours a day. The vessel will display the appropriate day shapes/signals, and during reduced visibility, the appropriate lights required by the IRPCS. Additionally, the vessel will actively transmit an AIS signal. A continuous listening watch will be maintained on VHF Channel’s 16, 14 and DSC. The requested safety zone around the vessel while working is 1 nm, and is at the discretion of the Captain.

 

Vessel Contact Details Roman Rebel Vessel Call Sign: 2ICA5 MMSI: 235108458 IMO: 9714824 Owner: Green Rebel - 021 245 5222 Vessel email: roman.rebel@greenrebel.ie Vessel Phone: +353 860607349.

 

Coordinates of survey area are detailed below.

 

See detailed map on our bulletin website
Show More

Floating LiDAR Buoys - Campion Wind



Mariners are advised that Campion Wind Limited will be extending the mobilisation of one of its FLiDAR Buoys (SWLB060) as part of its metocean Campaign to the 30th September 2024. Please maintain a 500 m clearance from the deployed equipment.


Mariners are advised that CampionWind Limited (a 50/50 Joint Venture company between ScottishPower Renewables UK Limited and Shell New Energies Holding Limited) will be extending the mobilisation of one of its FLiDAR Buoys (SWLB060) as part of its metocean Campaign to the 30th September 2024.

 

The FLiDAR Buoy will be monitored remotely so that in the event of a mooring failure, a team can be mobilised to carry out recovery and re-deployment activities. The Seawatch FLiDAR Buoy is yellow in colour and will exhibit a navigation light according to IALA standards: five (5) flashes at one (1) Hertz, every twenty (20) seconds (Fl (5) Y 20s). The ranges for the light on the Buoy is 5 nautical miles.

 

The FLiDAR Buoys location is outlined below and displayed within the Notice to Mariners (provided as an attachment to this notice). This location is within the CampionWind offshore wind farm array area, off the east coast of Scotland.

 

CampionWind will not seek to submit an updated AIS licence to support this extended mobilisation as the existing AIS Licence (1280449/3) is valid until September 2027.

 

See detailed map on our bulletin website
Show More

Commencement of Works Offshore Substation Installation - Moray Offshore Windfarm (West) Limited



This notice to mariners is to inform that Moray Offshore Windfarm (West) Limited (“Moray West”) will be commencing Offshore Substation installation works at the Moray West Offshore Wind Farm (Windfarm Marine Licence MS-00009774) from 26 November 2023. The work comprises of J tube cage installation, OSP-TP, and Topside installation at Monopile locations E06 (OSP #1) and M11 (OSP #2).


The scope of work includes the installation of 2x J-Tube cages (JTC), 2x OSP-TPs and 2x Topsides. The installation of the offshore substations will be carried out with the dynamically positioned installation vessels Bokalift1.   

 

Please be aware that, during the offshore substation installation works, the Bokalift 1, by virtue of its mode of operation the vessel, will be Restricted in its Ability to Manoeuvre (RAM). Masters of vessels are requested to maintain their vessels and gears at a minimum safe passing distance from the vessel of 500 meters when it is undertaking work and showing the appropriate shapes and lights in accordance with COLREGs Rule 27 (International Regulations for Preventing Collisions at Sea 1972, Rule 3).

See detailed map on our bulletin website
Show More

Inter Array Cable Installation - Dogger Bank A



The Cable Lay Vessel (CLV) VIKING NEPTUN will conduct Inter Array Cable laying operations in the Dogger Bank A OWF. Offshore Support vessels Olympic Taurus and Norside Cygnus will assist with cable installation and termination works.


The Offshore Support vessels Olympic Taurus and Norside Cygnus will continue with pull in preparation works and the terminations and testing works until approximately 31st of December 2023. The VIKING NEPTUN will commence the 2nd phase of cable lay works on the 1st of November 2023. The works will be continuous, 24 hours a day. A chart of the DBA cable array area is provided below.

The walk to work vessel will deploy and pick up tower teams on the different foundations to support the cable pull in and the cable installation finalization works. The cable lay vessel will deploy the inter array cable onto the seabed through her dedicated deck spread.

 

During operations, the Olympic Taurus, Norside Cygnus and VIKING NEPTUN will be restricted in their ability to manoeuvre as defined under COLREGs (International Regulations for Preventing Collisions at Sea 1972) and will display the appropriate day shapes and lights. The vessel will also transmit an Automatic Identification System (AIS) message. It is requested that all vessels maintain a minimum of 1.5Nm separation distance from the vessels and pass at reduced speed. Fishing gear or other equipment with seabed intervention should not be deployed when approaching the working corridor.

See detailed map on our bulletin website
Show More

Foundation Installation Campaign - Dogger Bank A



The Offshore installation vessel, HLV Seaway Strashnov, and the Heavy Lift Crane Vessel, Seaway Alfa Lift will install offshore wind turbine foundations, within the Dogger Bank A construction area.


The works  will commenced on the 26th of September 2022, continuing until approximately Q1 2024 The works will be continuous 24 hours a day.  A running list of the next locations to be installed and completed foundation locations are presented in the Weekly Notice of Operations.

 

The installed monopiles are marked with temporary lighting with the following characteristics:

 

•           Flashing (Fl) Yellow (Y) 2.5 seconds (s)

•           IALA Availability Category 2 (not less than 99.0%)

•           360° visibility – up to two lights per structure may be used to achieve this

•           At least 2 nm range.

 

During operations, the HLV Seaway Strashnov and the Seaway Alfa Lift will be restricted in ability to manoeuvre as defined under COLREGs (International Regulations for Preventing Collisions at Sea 1972) and will display the appropriate day shapes and lights. The vessels will also transmit an Automatic Identification System (AIS) message.

 

During operations, a Statutory Safety zone of 500m radius will be in place around the HLV Seaway Strashnov and the Seaway Alfa Lift during the installation of foundations.  The safety zones will be monitored by a guard vessel. The primary response will be to warn passing traffic of the ongoing works and any active safety zones, and to alert any vessels where an infringement may occur or has occurred.

See detailed map on our bulletin website
Show More

Inter Array Cable Post Lay Burial - Dogger Bank A Offshore Wind Farm



The Multi-Purpose Offshore Vessel, Livingstone, will resume Inter Array Cable Post-Lay Burial operations in Dogger Bank A Offshore Windfarm Area.


This campaign will commence on the 26th of November 2023 and continue until approximately 31st of December 2023. The works will be continuous, 24 hours a day. Charts of the DBA array area are provided below.

 

The operations include the post lay burial operations for part of the array cable routes, by means of jetting and mechanical cutting in order to protect the inter-array cables.

 

During operations, the Livingstone will be restricted in its ability to manoeuvre as defined under COLREGs (International Regulations for Preventing Collisions at Sea 1972) and will display the appropriate day shapes and lights. The vessel will also transmit an Automatic Identification System (AIS) message. 

 

It is requested that all vessels maintain a minimum of 1.5Nm separation distance from the TSV and pass at reduced speed. Fishing gear or other equipment with seabed intervention should not be deployed when approaching the working corridor.

See detailed map on our bulletin website
Show More

Underwater Noise Monitoring of Monopile Installation - Moray Offshore Windfarm (West) Limited



This notice to mariners is to inform that Moray Offshore Windfarm (West) Limited (Moray West) will deploy Autonomous Recording Units (ARUs) from a vessel in the Moray West Wind Farm site. Moray West will carry out underwater noise measurements using the ARUs during the early stages of the monopile installation campaign. The vessel is expected to commence works on site on 02 October 2023, with ARUs remaining in the water until approximately the end of December


Autonomous Recording Units (ARUs) will be deployed prior to and during the monopile installation works on seabed moorings, at approximately 750m and 2km from the monopile installation locations. A maximum of eight ARUs will be deployed at once, with five being collected and redeployed elsewhere where needed. There will be a total of 13 ARU deployment locations.

See detailed map on our bulletin website
Show More

Metocean Buoy Deployments - Ossian Offshore Wind Farm



Partrac Ltd. deployed FLS200 Floating LiDAR buoys at two sites within the Ossian Floating Offshore Wind Farm off the East coast of Scotland in August 2022. Partrac recovered the Floating LiDAR Buoy from Site 1 for servicing onshore, and the LiDAR Buoy at Site 3 remains on station at Ossian. Partrac is planning to redeploy the LiDAR Buoy at Site 1, and service the Buoy at Site 3, from 23 November 2023. The works are estimated to be carried out over two days, weather permitting.


FLOATING LIDAR BUOY The floating LiDAR buoys deployed at sites 1 and 3 record meteorological data and are anchored to the seabed by means of a mooring chain and a ground weight. The buoy has dimensions of 4m x 4m, and when deployed the tallest mast on the buoy sits approx. 4m above the water line. The lantern has a flash sequence Fl (5) Y 20s. Please maintain a 500m exclusion around each buoy.

See detailed map on our bulletin website
Show More

Metocean Equipment - Spiorad na Mara



Spiorad na Mara Ltd deployed an array of metocean equipment, including one floating LiDAR (FLIDAR) buoy, over a period of 24 months, and two Datawell Waverider buoys and one Seabed mooring for 12 months within the Spiorad na Mara offshore wind farm site.


Show More

Project Marine Survey Operations - Eastern Green Link 3 / 4



Mariners are advised that a nearshore marine geophysical survey is planned for the Eastern Green Link 3 and 4 (EGL3 /4) projects. The marine survey activities for EGL 3 / 4 are planned to commence mid- August 2023 and are expected to complete around the end of December 2023.


Eastern Green Link 3 is a HVDC electricity transmission interconnector between Scotland and England, a joint venture between National Grid and Scottish & Southern Electricity Transmission (SSEN).

 

Eastern Green Link 4 is a HVDC electricity transmission interconnector between Scotland and England, a joint venture between National Grid and Scottish Power.

 

The EGL 3 / 4 projects will play a vital role in achieving the UK and Scottish governments net zero targets and significantly increase the UK’s capacity for clean, green renewable power.

 

The area of work, pertaining to this Notice to Mariners (NtM) for EGL 3 / 4, is illustrated in Figure 1 and Table 6, with the survey vessel contact details for the project found in Table 1 and Table 2. Contact details for the project Fisheries Liaison Officers are detailed below.

 

The non-intrusive geophysical survey works are being carried out by Next Geosolutions.

 

The vessels used will be: DEEP Seapal, Deep SV Miranda and DEEP Breaker.

See detailed map on our bulletin website
Show More

Project Marine Survey Geotechnical Operations - Eastern Green Link 3



Mariners are advised that a marine geotechnical survey is planned for the Eastern Green Link 3 (EGL3) project. The marine survey activities for EGL 3 are planned to commence late-November 2023 and are expected to complete mid-late January 2024. The offshore geophysical works for EGL3 are now complete.


Eastern Green Link 3 is a HVDC electricity transmission interconnector between Scotland and England, a joint venture between National Grid and Scottish & Southern Electricity Transmission (SSEN).

 

The EGL 3 project will play a vital role in achieving the UK and Scottish governments net zero targets and significantly increase the UK’s capacity for clean, green renewable power.

 

The EGL 3 marine geotechnical survey works consist of shallow cone penetration tests (CPTs) and vibrocores (VCs) to a maximum of 6 m below seabed at approximate 1 km intervals.

 

The area of work, pertaining to this Notice to Mariners (NtM) for EGL 3, is illustrated in Figure 1, with the survey vessel contact details for the project found in Table 1. Note, centreline co-ordinates are provided on the associated Kingfisher notice.

 

Contact details for the project Fisheries Liaison Officers are detailed below.

 

The geotechnical survey works are being carried out by Next Geosolutions using the following vessel:

 

Ievoli Grey (IMO 9608788; MMSI 247325100; Call Sign IBCM).

 

Vessels are requested to pass at a safe speed and distance and fishing vessels are advised to remain a safe distance, approximately 550m (0.3 nautical miles) from the areas identified. During these works the vessel will have restricted manoeuvrability as it completes its work scope.

 

VHF CH 16 will be monitored at all times and will be used to contact the coastguard in the event of an emergency.

See detailed map on our bulletin website
Show More

Array Boulder Clearance and Pre-trenching Works - Sofia Offshore Wind Farm



All Mariners are advised that that the ASSO Subsea vessel “TSV Aethra” continues with boulder clearance and pre-trenching works within the Sofia Offshore Wind Farm Array.


The works are scheduled to be deployed during four visits to site (from Port of Blyth). Vessels are requested to leave a wide berth during the installation operations of at least 0.5 Nm.

 

The length of the boulder clearance and pre-trenching activities will vary depending on the execution progress, and details of any changes will be confirmed in further Notice to Mariners to be issued during the course of the project.

 

The table above provides the coordinates of the total working area of the boulder clearance and pre-trenching works at the SOWF array. 

 

The TSV Aethra shall be monitoring VHF 77 during the scope of the works and shall also be exhibiting the correct day shapes and night lights for a vessel restricted in ability to manoeuvre.

 

**Note: In the exclusion zone, temporary reduction by approx. 1 meter in navigable depth might be created from the pre-plough spoil heaps.

 

Vessel Name Vessel Type Length Beam Draft Gross Tonnage Call Sign MMSI Number
TSV Aethra Boulder Clearance and Pre-Trenching Vessel 94.10m 22m 7.1m 7,082 SVDM6 241831000
Enterprise II Guard / Scout Vessel 26.00m 9.2m 4.7m 421 MPFN7 232006130

 

See detailed map on our bulletin website
Show More

Missing Passive Acoustic Monitoring Equipment in East Anglia THREE Windfarm



Please be advised that Seiche is missing 4 Passive Acoustic Monitoring (PAM) Stations that had been deployed on the seabed at locations in and around the East Anglia THREE Offshore Windfarm Area in July 2023.


Missing Passive Acoustic Monitoring Equipment in East Anglia THREE Offshore Windfarm

 

• Seiche Limited

 

• Passive Acoustic Monitoring at the East Anglia Three Offshore Windfarm

 

Date of issue: 31 Oct 2023

 

Please, be advised that Seiche is missing 4 Passive Acoustic Monitoring (PAM) Stations that had been deployed on the seabed at locations in and around the East Anglia THREE Offshore Windfarm Area in July 2023.

 

The following map shows all mooring locations, including the missing locations: EA3_01, EA3_06, EA3_08 and EA3_12:

     

The table below shows the original locations of these 4 PAM stations:

 

Below are pictures that show the equipment attached to the PAM stations:

 

If you find, or found, something similar to this equipment in your catch, please, contact us on:

 

E-mail: environmental@seiche.com

 

Tel: +44 (0) 1409 404050 Web: https://www.seiche.com

 

Or

 

Fisheries Liaison Officer (FLO):

 

Name: Jonathan Keer // Freya Sandison Email: jonathan@brownmay.com Telephone: +44 (0) 7850 604851

 

Date Deployed Location Number Latitude Longitude
13 July 23 EA3_01 52° 39.751 N 002° 50.894' E
14 July 23 EA3_06 52° 29.221' N 002° 33.559' E
15 July 23 EA3_08 52° 19.723' N 002° 21.599' E
14 July 23 EA3_12 52° 17.566' N 002° 52.293' E

 

See detailed map on our bulletin website
Show More

SHEPD Subsea Inspections - Orkney Islands



UPDATE: Survey operations for the project have been postponed until early 2024. An update on new survey dates for the remaining six cables will be issued in due course.


Please be advised that Aspect Land & Hydrographic Surveys Ltd (on behalf of SHEPD) will be undertaking subsea inspections of several cables across the Orkney Islands. The inspection works will be centred on a 50m cable corridor, defined by the start and end coordinates listed in this notice.

See detailed map on our bulletin website
Show More

SSEN Transmission Spittal to Peterhead Cable Route Seabed Survey – Vessel – Marine Sensor -South



Mariners are advised of marine survey activities in the North Sea and outer Moray Firth between the 21 November 2023 and the 22 December 2023. The vessel shall be operating with restricted movement, and/or over the side equipment deployed to the seabed. Keep well clear of the vessel while under survey operations.


Show More

Metocean Survey - Salamander Offshore Wind Farm



Update: Metocean buoy and two FLiDAR buoys successfully deployed within the Salamander Offshore Array Area on 10th November 2023 – as laid coordinates below. Buoys will remain in situ for min. 12 months. Marine users are advised to maintain a safe clearance distance of 500m from the buoys.


Planned deployment within the Salamander Offshore Array Area consists of:

  • 2x Fugro Sea-watch LiDAR Buoys (SWLB079 and SWLB086)
  • 1x Fugro Wavescan Metocean Buoy (WS164) with a Nortek Signature 250 kHz Acoustic Doppler Current Profiler (ADCP) on the keel weight.

Illustrative figures showing the buoy dimensions and general mooring arrangement are provided in the attached NtM.

 

Once in the water the top of the tallest mast is around 4 meters above the sea level. The buoys' drifting radius is approximately 240 m from their deployment positions. 

 

The buoys are fitted with the following navigational safety features:

  • Buoys painted yellow in colour;
  • Yellow St Andrews Cross;
  • Passive radar reflector (Mobri S-4);
  • AIS AtoN (with MMSI numbers: 992351428, 992351430, 992351429); and
  • Marine lantern (with flash character Fl (5) Y 20s - 5 yellow flashes every 20 seconds) with a range of 4 nautical miles.
See detailed map on our bulletin website
Show More

Export Cable Trenching Trials - Dogger Bank C Export Cable



The cable laying vessel, NKT Victoria, will perform trenching trial operations between KP103 – KP105, KP108.975 - KP111.575 and KP132.500 - KP137.450 approximately


The trenching trials will commence on the 26 November for approx. 3 weeks. The work will be continuous, 24 hours a day. Coordinates and chart of the location are provided below.

 

At each trial location, the proposed sequence of activities includes:

 

  • Pre-Lay Survey of selected site;
  • Demonstration of cable burial;
  • As-Buried Survey; and
  • Recover cable back to NKT Victoria.

 

All equipment used for the trials will be removed upon completion of the test.

 

During operations the NKT Victoria will be restricted in its ability to manoeuvre as defined under COLREGs (International Regulations for Preventing Collisions at Sea 1972) and will display the appropriate day shapes and lights. The vessel will also transmit an Automatic Identification System (AIS) message.

 

It is requested that all vessels maintain a minimum of 1.5Nm separation distance from NKT Victoria and pass at reduced speed. Fishing gear or other equipment with seabed intervention should not be deployed when approaching the working area.

 

An Offshore Fisheries Liaison Officer will be onboard NKT Victoria to provide support and coordination to fishing vessels, please see contact details below

See detailed map on our bulletin website
Show More

Subsea Route Survey: Coll - Tiree



Please be advised that Briggs Marine Contractors (on behalf of SHEPD) have completed a subsea route survey within the corridor identified in the attached Notice to Mariners (NtM). Survey operations are now complete and fishing gear clearance is no longer required.


Show More

Reduction to Charted Depth - Dogger Bank A Export Cable



During the campaign to lay and bury the Dogger Bank A export cable, it has been necessary to install rock berm protection over the cable in locations where it has not been possible to trench bury the cable. In the section of cable shown below, the rock berm installation has been installed to a maximum height of approximately 0.6m above seabed level. In these locations, this represents a reduction in depth at Lowest Astronomical Tide (LAT) of approximately 5%.


Show More

Greenlink Interconnector Trenching - S.E Ireland, from Great Island, County Wexford to S.W Wales



Greenlink Interconnector Ltd. is developing an electricity interconnector between the South-east of Ireland, from Great Island, County Wexford to South-west Wales, at Pembroke, Pembrokeshire. Offshore cable installation is complete from the Freshwater West to the median line between Wales and Ireland. The cable now be protected with trenching activities performed along the route by Helix Robotics Solution on behalf of Jan De Nul Luxembourg S.A. using the trenching support vessel Grand Canyon


The operations will be performed by Grand Canyon III (Call Sign: LACJ8 / IMO N° 9695963 / MMSI N° 257010590), a DP2 offshore support vessel presented in below Figure 4-1. The vessel has a length of 127 m and a breadth of 25 m. The draft is approximately 6.5 m.

 

The vessel will have the trenching vehicle deployed either over the side or the stern, or an ROV for survey activities deployed over the side. During these operations, it will be restricted in manoeuvrability. All vessels operating within this area are requested to keep a 0.5 nm distance and pass at minimum speed to reduce vessel wash. The vessel will always be listening to VHF channel 16 and can set any other channel as required

 

 

See detailed map on our bulletin website
Show More

FLS2 Redeployment - West of Orkney Windfarm



OWPL have successfully redeployed the FLS2 device on the 9 May 2023 at its previous location (coordinates are detailed in this update). Project is still running to May 2024


OWPL have redeployed the FLS2 at its previous location. (DDM = 58° 48.7157' N, 4° 20.64135' W, DMS = 58° 48' 42.94" N, 4° 20' 38.48" W). Both the FLS2 and the wave buoy are part of continued metocean survey works which are continuing through to October 2023.

 

Onshore FLO: phone: +44 (0) 7926 418 820, email: OWPLFisheries@xodusgroup.com;

See detailed map on our bulletin website
Show More

MBES Surveying Array Area - Dogger Bank A & B



The Dogger Bank D project will be carrying out an MBES geophysical survey within Dogger Bank A (DBA) and Dogger Bank B (DBB) Array Areas using remotely piloted uncrewed surface vessels (USVs).


The USVs will be mobilised from Scarborough Harbour where each USV will be escorted out of the harbour limits, before transiting to the survey area. Survey Operations will be continuous 24hrs a day. Although vessels are uncrewed, they are managed remotely continuously using 360-degree cameras and other sensors. 

 

The works will commence on the 13th of November 2023, continuing until 15th December when all locations have been surveyed. The works will be continuous, 24 hours a day. A chart of the DBA / DBB Array Areas and bounding coordinates is provided below.   

  

It is requested that all vessels maintain a minimum of 500m separation distance from the USVs and pass at reduced speed.  

See detailed map on our bulletin website
Show More

Metocean Survey - West of Orkney Offshore Windfarm



This ongoing survey takes place between 14 October 2022 and has been extended until 31 May 2024; There are 3 days of service visits scheduled during a suitable weather window between 10/11/2023 to 31/12/2023


Contact details:

  • Onshore FLO: phone: +44 131 385 7374 or +44 1224 219 932, email: OWPLFisheries@xodusgroup.com;
  • Offshore: T: +44(0)1856 851966 (office) M: +44(0)771 056 2605 (mobile);             
  • Name of vessels carrying out the work and equipment used:MV C-Odyssey (MMSI:235088132) (Leask Marine Limited, Phone: M: +44 (0)7718 424491 P: +44 (0)1856 874725 Email: info@leaskmarine.com)
  • Two floating Light Detection and Ranging (LiDAR) Systems (FLS);
  • One Wave Buoy; and
  • One Acoustic Doppler Current Profiler (ADCP).
  • Port of operation: Stromness, Scotland
See detailed map on our bulletin website
Show More

SSEN Transmission Spittal to Peterhead Cable Route Seabed Survey – Vessel – Marine Sensor



Mariners are advised of marine survey activities in the North Sea and outer Moray Firth between the 30th of October 2023 and the 15th of December 2023. The vessel shall be operating with restricted movement, and/or over the side equipment deployed to the seabed. Keep well clear of the vessel while under survey operations.


Survey Operations: The survey route at the North end covers a corridor of 500m, 250m on each side of the cable route centre line extending seaward to the 15m depth contour as shown in the image below.

 

Geophysical Survey: The Marine Sensor vessel shall survey the seabed using towed and vessel mounted sensors at a speed of approximately 2-4 knots. The vessel shall survey the Northern side (Brough Head), however the survey sequence may be adjusted with regards to the weather conditions.

 

 

See detailed map on our bulletin website
Show More

Offshore Site Investigation - Awel y Môr Proposed Wind Farm



A Geotechnical Site Investigation of the proposed Awel y Môr Offshore Wind Farm is due to be conducted off the North Wales coast between 11th November 2023 and early March 2024.


The jack-up barge Seafox 7 is due to start geotechnical site investigations on the 11th November 2023 and to continue the survey until early March 2024.  This estimate includes delays likely to be caused by bad weather. During the survey, Seafox 7 will drill 60 boreholes at discrete locations in the project site.  The vessel will operate for 24 hours per day during the survey.  The survey area is illustrated in the Notice to Mariners and bounded by the coordinates below:-

  • NE Marker: 53° 29.460’N 003° 35.220’W
  • SE Marker: 53° 29.532’N 003° 44.760’W
  • SW Marker: 53° 26.700’N  003° 51.600’W
  • NW Marker: 53° 29.280’N 003° 51.600’W

Seafox 7 will be supported by the vessels Elisa and Fairplay 32 in its daily operations, and these vessels will tow the barge between sampling locations.  The tugs will standby at anchor on the project site, and will also be transiting between the site and nearby ports. The vessel MCS Boreas will be assisting the Seafox 7 with crew transfer operations to shore on a twice-weekly basis.

 

Vessel details

Seafox 7 is a jack-up barge with a red hull and white superstructure.  It measures 55.5m long with a beam of 32.2m.  Details for this barge and its support vessels are provided below:-

  • Seafox 7: drilling vessel | MMSI 235065812 | Call sign 2BGC6
  • Elisa: Support vessel / tug | MMSI 236745000 | Call sign PBZP
  • Fairplay 32: Support vessel / tug | MMSI 210447000 | Call sign 5BAM6
  • MCS Boreas: Crew Transfer Vessel | MMSI 235096501 | Call sign 2GDR8

Operations will be conducted on a 24 hour basis.  A continuous listening watch will be conducted on VHF Channel 16.

 

Other vessels are requested to keep their distance, maintaining at least a 500m distance.

 

Full details of all of the vessels can be found in the Notice to Mariners.

 

About the proposed windfarm

The Awel y Môr Offshore Wind Farm would be built around six miles off the North Wales coast, to the west of the existing Gwynt y Môr windfarm.  Awel y Môr would be connected to the National Grid by an export cable coming ashore between Rhyl and Prestatyn.  The proposed windfarm would include up to 50 wind turbines.  It could generate enough power for up to half a million homes, and it will be the largest renewable energy investment in Wales in this decade. Full project details and maps of the windfarm location are available at the project website awelymor.cymru.

See detailed map on our bulletin website
Show More

Geotechnical Survey - Broadshore, Sinclair, and Scaraben



Please be advised that Benthic will be performing survey operations in the form of geotechnical soil investigation in the North Sea on behalf of a Renantis and Bluefloat Energy joint venture. Benthic will be aboard MV Ocean Zephyr. The Ocean Zephyr will be working within the proposed Broadshore and the adjacent Sinclair and Scaraben Wind Farm development areas. The Ocean Zephyr is intended to be within the site between the periods 6 November to 31 January.


Please be advised that Benthic will be performing survey operations in the form of geotechnical soil investigation in the North Sea on behalf of a Renantis and Bluefloat Energy joint venture. Benthic will be aboard MV Ocean Zephyr.

 

The Ocean Zephyr will be working within the proposed Broadshore and the adjacent Sinclair and Scaraben Wind Farm development areas. The Ocean Zephyr is intended to be within the site between the periods 6 November to 31 January. The Ocean Zephyr may not be within the development area the entire duration and may be transiting outside of the fields during this time.

 

The Broadshore, Sinclair and Scaraben areas are located approximately 60Nm North of Aberdeen and 40Nm North of Peterhead, Scotland, shown as the orange area in Figure 1 in the attached.

 

A specification sheet for the Ocean Zephyr is provided in the attached Notice to Mariners.

 

 

The scope of work involves acquiring insitu Cone Penetration Test data up to 60m below seafloor and collecting soil samples up to 60m below seafloor. While the vessel is collecting data the Ocean Zephyr will remain on DP2 and will effectively be anchored to the seafloor with a recovery time up to one hour if the vessel needs to be maneuvered in an emergency.

 

The Ocean Zephyr will deploy a PROD, a remotely operated seafloor drill. From where the Ocean Zephyr is positioned on DP2, the PROD may be located up to 100m horizontal distance from the vessel. The PROD requires up to one hour to recover from the seafloor in emergencies. During normal operations, the PROD is expected to be on the seafloor for between 12hours and 60 hours. Operations are likely to continue in seastates up to Hs 2.75m and wind speeds less than 30 knots.

 

The location where work will be performed is indicated in Figure 1 in the attached. The boundary coordinates for the Broadshore, Sinclair and Scaraben Offshore Wind Farm areas are in WGS-1984, UTM Zone 30N, and are listed in the attached NTM. 

 

The vessel Ocean Zephyr is a DP II (Dynamically Positioned) vessel and for the majority of the period of works will have restricted ability to manoeuvre. We request that all vessels within the vicinity of the Ocean Zephyr always remain at least 500 m clear and pass at a reduced speed. The vessel Ocean Zephyr has AIS installed. A specification sheet for the vessel is included as an attachment to this document.

Please be aware that, during the survey activities, by virtue of its mode of operation the vessel will be Restricted in her Ability to Manoeuvre (RAM) as defined under COLREGs (International Regulations for Preventing Collisions at Sea 1972, Rule 3). Masters of vessels are therefore requested to maintain their vessels and gears at a minimum safe passing distance from the vessel of 500 metres when it is undertaking work and showing the appropriate shapes and lights in accordance with COLREGs Rule 27.

Fishermen who have static gears deployed beyond 12 nm are reminded that static gear must be marked in accordance with Commission Implementing Regulation (EU) No. 404/2011 (Marking of fishing gear, retrieval and notification of lost gear - GOV.UK (www.gov.uk)).

 

 

See detailed map on our bulletin website
Show More

Rampion Offshore Wind Farm Notice To Mariners: Risk of cable exposure within the Rampion Wind Farm



Following the most recent subsea survey carried out in August 2023, updated information of inter-array cable exposures are listed and illustrated below. Analysis of survey data at the wind farm indicates the locations of exposures of sections of inter-array cables are subject to change resulting from dynamic movements of the seabed but are primarily focused within the South-South East of the wind farm area.


Following the most recent subsea survey carried out in August 2023, updated information of inter-array cable exposures are listed and illustrated below. Analysis of survey data at the wind farm indicates the locations of exposures of sections of inter-array cables are subject to change resulting from dynamic movements of the seabed but are primarily focused within the South-South East of the wind farm area.

 

Mariners are reminded that further safety information related to array cable exposures can be found in “The Risks of Fishing Near Cables and Renewable Energy Structures”, published on the KIS-ORCA website https://kis-orca.org/safety/the-risks-of-fishing-near-cables-renewable-energy-structures/. General safety information can be found here: https://www.seafish.org/article/kingfisher-bulletins.. All mariners are requested to make themselves aware of their obligations for conducting activities over buried and protected cables under International and UK Cable (Subsea) Protection Legislation.

See detailed map on our bulletin website
Show More

Cable exposures - IFA2000 Interconnector



A recent survey has detected a section of cable with intermittent exposures and potential free spans in the UK sector of the IFA 2000 Interconnector. These exposures are found across all four cables west of 001° 17.2’E . Fishing vessels are advised to keep clear of this area.


A recent survey has detected an area where the cable is intermittently exposed with some free spans a possibility. The exposures are present intermittently across all four cable routes in the area bounded by: 

51° 5.23’N 001° 17.20’E

51° 3.33’N 001° 17.20’E

51° 5.00’N 001° 11.67’E

51° 4.88’N 001° 11.67’E

 

A remedial plan is being formulated. Fishermen are requested to stay well clear.

See detailed map on our bulletin website
Show More

Marchwood ERF sea water intake dredging - Outside the navigational Channel of Southampton Water



Vessels to commence dredging at the sea water intake of Marchwood ERF outside the navigational Channel of Southampton Water near Port hand mark No.8


Works to be carried out outside of channel but a split hopper barge will be operating between the Dredge site (Marchwood ERF SW intake) and the Nab spoil ground once per day. Divers will be in the water periodically throughout the duration of the dredging so reduced wash in the vicinity should be in place. 

See detailed map on our bulletin website
Show More

Shetland HVDC Cable Project



As an update, Scottish Hydro Electric Transmission Plc NKT, continue installing the Shetland HVDC Link. For Campaign 2 (from Weisdale Voe, Shetland, KP0.225 to KP57), cable installation has been completed. For Campaign 3 (KP57 to KP160), rock placement works remain to be completed along the cable route between KP101 and KP160. Please see chart and coordinates provided below.


The Shetland HVDC link is a critical electricity transmission link and will form part of the electrical transmission grid that is essential to the transport of renewable energy between the locations where it is generated and areas of demand, and the delivery of both Scotland’s and the United Kingdom’s 2030 climate change targets.

 

Campaign 3 (KP57 to KP160)

For installation Campaign 3, the vessel, NKT Victoria, has laid the cable on the seabed and the trenching vessel, Grand Canyon III, has trenched the cable to the required burial depth in the seabed.

For any sections between KP101 – KP160 along the cable route that have been unable to be trenched, rock placement is being undertaken by the vessel Rockpiper to achieve the required protection.

 

All works will be continuous, 24 hours a day. For any crossings, protection will follow the agreement made with the asset owner. In the period between cable lay and cable burial, or protection by rock placement, the cable will be exposed on the seafloor. During this time the cable is sensitive to any external impact and constitutes a snagging risk for anchoring, fishing gear or other equipment with seabed intervention. For this reason, the Campaign 3 (KP101 – KP160) cable corridor will remain closed for any fishing that interacts with the seabed, anchoring or use of other equipment with seabed intervention.

 

To protect the cable in the cable corridor, Guard Vessels are deployed along the route. It is requested that all vessels maintain a minimum of 500m safe distance from the rock placement vessels and pass at reduced speed.

 

It is advised that mobile fishing gear should not be placed within 500m of the cable corridor. Static fishing gear, or any other equipment that interacts with the seabed, should not be deployed within the cable corridor.

 

Co-ordinates of the cable route and charts of the working area are provided below.

 

Please be aware that Rockpiper will be restricted in their ability to manoeuvre as defined under COLREGs (International Regulations for Preventing Collisions at Sea 1972). Masters of vessels are therefore requested to maintain their vessels at a minimum safe passing distance of 500 metres. For restricted areas, communication should be made to Rockpiper and the Guard Vessels for safe passage. Rockpiper will display the appropriate shapes and lights in accordance with COLREGs Rules 16 and 18.

 

 

 

 

 

See detailed map on our bulletin website
Show More

SSEN Transmission Spittal to Peterhead Cable Route Seabed Survey- Block 7-Support Vessel-Silver Wave



Mariners are advised of marine survey activities in the North Sea and Outer Moray Firth between the 25th of October 2023 and the 7th of January 2024. Keep well clear of the vessel while under survey operations.


The survey route is 165km in length and covers a corridor of 500m, 250m on each side of the cable route centerline as shown in the images below. The Silver Wave shall conduct supporting operations from approximately the 12m contour water depth through to 100m water depth.

Phase 1 – Geophysical Survey   

The Silver Wave shall operate within the detailed survey blocks (Offshore Block 2 to Block 7) from the Northern side working Southwards, however the survey block sequence may be adjusted with regards to the weather conditions.

Phase 2 – Benthic and Geotechnical Survey

On completion of the Phase 1 Geophysical Survey, the survey vessel Viking Reach shall begin the Benthic and Geotechnical Survey along the route. The support vessel Silver Wave will work alongside the Viking Reach during this time.

See detailed map on our bulletin website
Show More

Moorings and Scientific Equipment Installed - Beatrice, Moray East, Moray West & Caledonia Windfarms



Mariners are advised that the University of Aberdeen has installed 52 moorings and PAM equipment within the Beatrice, Moray East, Moray West and Caledonia Offshore Windfarm sites, at the locations listed in this notice. The moorings support acoustic loggers that record echolocation clicks of dolphins and porpoises and broad-band sound recorders. They will remain in place for approximately 6 months. All are subsurface moorings that extend no more than 6 m vertically from the seabed.


Show More

SSEN Transmission Spittal to Peterhead Cable Route Seabed Survey- Block 6-Support Vessel-Silver Wave



Mariners are advised of marine survey activities in the North Sea and Outer Moray Firth between the 20th of October 2023 and the 7th of January 2024. The vessel shall be operating with restricted movement, tethered ROV and/or over the side equipment deployed to the seabed. Keep well clear of the vessel while under survey operations.


The survey route is 165km in length and covers a corridor of 500m, 250m on each side of the cable route centerline as shown in the images below. The Silver Wave shall conduct supporting operations from approximately the 12m contour water depth through to 100m water depth.

Phase 1 – Geophysical Survey   

The Silver Wave shall operate within the detailed survey blocks (Offshore Block 2 to Block 7) from the Northern side working Southwards, however the survey block sequence may be adjusted with regards to the weather conditions.

Phase 2 – Benthic and Geotechnical Survey

On completion of the Phase 1 Geophysical Survey, the survey vessel Viking Reach shall begin the Benthic and Geotechnical Survey along the route. The support vessel Silver Wave will work alongside the Viking Reach during this time.

See detailed map on our bulletin website
Show More

SSEN Transmission Spittal to Peterhead Cable Route Seabed Survey- Block 7



Mariners are advised of marine survey activities in the North Sea and Outer Moray Firth between the 20th of October 2023 and the 7th of January 2024. The vessel shall be operating with restricted movement, tethered ROV and/or over the side equipment deployed to the seabed. Keep well clear of the vessel while under survey operations.


Survey Operations: The survey route is 165km in length and covers a corridor of 500m, 250m on each side of the cable route centerline as shown in the images below. The Viking Reach shall operate from approximately the 12m contour water depth through to 100m water depth.

 

Phase 1 – Geophysical Survey The Viking Reach shall operate with a tethered Remotely Operated Vehicle (ROV) which shall survey the seabed behind the vessel at a speed of 2-4 knots. The ROV shall survey the detailed survey blocks (Offshore Block 1 to Block 6) from the Northern side working Southwards, however the survey block sequence may be adjusted with regards to the weather conditions.

 

Phase 2 – Benthic and Geotechnical Survey: On completion of the Phase 1 Geophysical Survey the Viking Reach shall begin the Benthic and Geotechnical Survey along the route. The vessel shall deploy over the side equipment to inspect and sample the seabed

See detailed map on our bulletin website
Show More

SSEN Transmission Spittal to Peterhead Cable Route Seabed Survey- Block 6



Mariners are advised of marine survey activities in the North Sea and Outer Moray Firth between the 20th of October 2023 and the 7th of January 2024. The vessel shall be operating with restricted movement, tethered ROV and/or over the side equipment deployed to the seabed. Keep well clear of the vessel while under survey operations.


Survey Operations: The survey route is 165km in length and covers a corridor of 500m, 250m on each side of the cable route centerline as shown in the images below. The Viking Reach shall operate from approximately the 12m contour water depth through to 100m water depth.

 

Phase 1 – Geophysical Survey The Viking Reach shall operate with a tethered Remotely Operated Vehicle (ROV) which shall survey the seabed behind the vessel at a speed of 2-4 knots. The ROV shall survey the detailed survey blocks (Offshore Block 1 to Block 6) from the Northern side working Southwards, however the survey block sequence may be adjusted with regards to the weather conditions.

 

Phase 2 – Benthic and Geotechnical Survey: On completion of the Phase 1 Geophysical Survey the Viking Reach shall begin the Benthic and Geotechnical Survey along the route. The vessel shall deploy over the side equipment to inspect and sample the seabed

See detailed map on our bulletin website
Show More

Uncrewed Surface Vessels (USVs) are planned out of Eyemouth and Arbroath



Operations of remotely piloted Uncrewed Surface Vessels (USVs) are planned out of Eyemouth and Arbroath during October, November and December 2023. The vessels will be engaged in geophysical survey activities associated in the North Sea 85km off the Angus coastline.


Dates: Operations will take place subject to weather and other operational factors from 16th October for 13 weeks. Up to 6 USVs are expected to be operational at one time.

A support vessel will escort the USVs from the active ports to clear water.

 

Although the vessel is uncrewed, it is crewed throughout the 24 hour operation, piloted remotely using 360 degree cameras and other navigational aids.

Figure 1 below indicates the operational area. The survey area boundary is indicated in Table 1 below also. In addition to the survey area, the USVs will transit from one of the named ports above to site.

Fisheries Liaison for this survey will be co-ordinated by Natural Power. All commercial fishery queries, should be directed to Peter Berney or Hollie Maven; Mobile T: 07391402387  / Email: Ossian.FLO@naturalpower.com.

 

Table 2: Vessel Details

Name

X-04 Uncrewed

X-08 Uncrewed

X-11 Uncrewed

X-16 Uncrewed

X-17 Uncrewed

X-19 Uncrewed

X-21 Uncrewed

X-22 Uncrewed

X-23 Uncrewed

MMSI

232023832

232027631

232033343

232039413

232039414

232039416

232042738

232044014

232044015

Length

4.5mm

4.5mm

4.5mm

4.5mm

4.5mm

4.5mm

4.5mm

4.5mm

4.5mm

Beam

2.2m

2.2m

2.2m

2.2m

2.2m

2.2m

2.2m

2.2m

2.2m

Speed

3.5knts

3.5knts

3.5knts

3.5knts

3.5knts

3.5knts

3.5knts

3.5knts

3.5knts

Draught

1.0m

1.0m

1.0m

1.0m

1.0m

1.0m

1.0m

1.0m

1.0m

Tonnage

750kg

750kg

750kg

750kg

750kg

750kg

750kg

750kg

750kg

Towed Equipment

No

Yes

Yes

No

No

No

No

No

No

 

The USV sends real time images and situational awareness data over satellite to a team of operators keeping watch and controlling the vessel remotely 24/7.

 

Safety Precautions: The USV is equipped with the following to make it conspicuous to other marine traffic:

  • AIS
  • VHF
  • Navigation Lights & Sound Signal
  • Active Radar Reflector
  • Superstructure Painted Yellow

Seafarers are asked to avoid contact with the vessel and be aware of the operational area during this period

 

XOCEAN - Emergency Contact Details:

Name (Role)

Telephone Number

Email Address

USV Supervisor (24/7)

+353 1 223 9950

usv.supervisor@xocean.com

Rhiannon Evans (Project Manager)

+44 7817 485935

Rhiannon.evans@xocean.com

Oliver Harris (Head of Projects)

+44 (0) 2080 982108

oliver.harris@xocean.com

Anthony O’Toole (Marine Superintendent)

+353 1 223 9957

Anthony.otoole@xocean.com

 

See detailed map on our bulletin website
Show More

Offshore geophysical survey - Eastern Green Link 4



Mariners are advised that a marine geophysical survey is planned for the Eastern Green Link 4 (EGL4) project. The marine survey activities for EGL 4 are planned to commence early November 2023 and are expected to complete late January 2024.


Show More

Sofia OWF - Navigation Warning - Off-Station Met-Ocean Buoys



Mariners are advised that Met Ocean Buoys at KP2 (Position 54° 36.508N x 000° 00.175W) and KP40 (Position: 54° 40.524' N x 000° 26.735' W) have been reported as off station. They have been successfully recovered and are now in Hartlepool awaiting inspection and then reinstatement (date TBC). As it is currently unknown if the mooring is attached to these buoys, please avoid the KP2 and KP40 coordinates highlighted within the table above by at least 100m until further notice.


Show More

SSEN Transmission Spittal to Peterhead Cable Route Seabed Survey Vessel - Viking Reach



Mariners are advised of marine survey activities in the North Sea and Outer Moray Firth between the 20th of October 2023 and the 7th of January 2024. The vessel shall be operating with restricted movement, tethered ROV and/or over the side equipment deployed to the seabed. Keep well clear of the vessel while under survey operations.


Survey Operations: The survey route is 165km in length and covers a corridor of 500m, 250m on each side of the cable route centerline as shown in the images below. The Viking Reach shall operate from approximately the 12m contour water depth through to 100m water depth.

Phase 1 – Geophysical Survey The Viking Reach shall operate with a tethered Remotely Operated Vehicle (ROV) which shall survey the seabed behind the vessel at a speed of 2-4 knots. The ROV shall survey the detailed survey blocks (Offshore Block 1 to Block 6) from the Northern side working Southwards, however the survey block sequence may be adjusted with regards to the weather conditions.

 

Phase 2 – Benthic and Geotechnical Survey: On completion of the Phase 1 Geophysical Survey the Viking Reach shall begin the Benthic and Geotechnical Survey along the route. The vessel shall deploy over the side equipment to inspect and sample the seabed

See detailed map on our bulletin website
Show More

SSEN Transmission Spittal to Peterhead Cable Route Seabed Survey – Support Vessel - Silver Wave



Mariners are advised of marine survey activities in the North Sea and Outer Moray Firth between the 20th of October 2023 and the 7th of January 2024. The vessel shall be operating with restricted movement, tethered ROV and/or over the side equipment deployed to the seabed. Keep well clear of the vessel while under survey operations.


Survey Operations: The survey route is 165km in length and covers a corridor of 500m, 250m on each side of the cable route centerline as shown in the images below. The Viking Reach shall operate from approximately the 12m contour water depth through to 100m water depth.

Phase 1 – Geophysical Survey The Viking Reach shall operate with a tethered Remotely Operated Vehicle (ROV) which shall survey the seabed behind the vessel at a speed of 2-4 knots. The ROV shall survey the detailed survey blocks (Offshore Block 1 to Block 6) from the Northern side working Southwards, however the survey block sequence may be adjusted with regards to the weather conditions.

 

Phase 2 – Band sample the seabedenthic and Geotechnical Survey: On completion of the Phase 1 Geophysical Survey the Viking Reach shall begin the Benthic and Geotechnical Survey along the route. The vessel shall deploy over the side equipment to inspect. 

See detailed map on our bulletin website
Show More

Berwick Bank Geotechnical Survey - Fugro Quest and Scout



Mariners are advised that SSE Renewables will be returning to Berwick Bank Wind Farm area to undertake further Geotechnical survey work. The survey will be within the proposed Berwick Bank Wind Farm site boundary. It should be noted that SSE Renewables are not expecting fishermen to relocate gear - on this occasion the vessel(s) will work around any gear on location. A guard vessel will also be contracted to work alongside each survey vessel. 


The survey work is being undertaken by Fugro and will be conducted from two vessels: the Scout and the Quest. The geotechnical survey is due to start on 27 October 2023. The scouting/guard vessel will be the GV Courage SH170. 

 

Survey Duration  

The survey will mobilise 27 October 2023 lasting approximately 5 months. To account for all eventualities, we would like to extend the duration to 31 May 2023.  

 

Survey Tasks  

The survey will involve borehole sampling, using the Geobor-S coring system or similar, with the number and location of the boreholes yet to be finalised. 

 

As a consequence of equipment being deployed and the modes of operation, all mariners are advised to keep a safe clearance distance of no less than 500 m from the vessel(s). No towed equipment will be used.  

See detailed map on our bulletin website
Show More

Metocean and Floating LiDAR Campaign extension - MarramWind Offshore Wind Farm



Mariners are advised that MarramWind Limited (a 50/50 Joint Venture company between ScottishPower Renewables UK Limited and Shell New Energies Holding Limited) will be extending the Metocean and Floating LiDAR Campaign in the MarramWind Offshore Wind Farm array area to 30 September 2024.


The installation of two Floating LiDAR systems and one Seawatch Midi metocean buoy will be extended from 10 October 2023 to 30 September 2024 within the MarramWind Offshore Wind Farm array area to continue recording wind and metocean data.

 

All locations referred to are outlined in a table and displayed in Figure 1 within the Notice to Mariners (provided as an attachment to this notice). These locations are all within the MarramWind offshore wind farm 75 km off the east coast of Scotland.

 

The Seawatch Midi metocean buoy and the FLiDAR buoys are yellow in colour and will exhibit a navigation light according to IALA standards: five (5) flashes at one (1) Hertz, every twenty (20) seconds (Fl (5) Y 20s). The ranges for the lights on the buoys are 5 nautical miles for both Seawatch Midi and the FLiDAR Buoys.

 

Further details can be found within the attached Notice to Mariners.

See detailed map on our bulletin website
Show More

Commencement Inter-Array Cables Pre-Lay Grapnel Run - Neart na Gaoithe Offshore Wind Farm Limited



Neart na Gaoithe Offshore Wind Farm Limited (NnGOWL) have completed the pre-lay grapnel run (PLGR) for inter-array cables within the Neart na Gaoithe Offshore Wind Farm site. The PLGR activities began on the 10th of August and were completed on the 14th August. Cable lay commenced on the 25th August at the earliest.


The PLGR was completed by the vessel Pacific Dispatch (call sign: 9VFW6) using a grapnel towed from the vessel. The grapnel was deployed to detect and remove surface debris located on the inter-array cable routes, and at the wind turbine and offshore substation topside locations. The Pacific Dispatch has left the NnG site.

 

A Cable Lay Vessel, the Viking Neptun (call sign: LAYH7), will lay the inter-array cable onto the seabed for this second IAC campaign. Cable lay works commenced on the 25th August at the earliest and take around 4 weeks to complete. The laid cables will be left unburied and unprotected on the seabed until October 2023. Cable pull-in and termination and testing works will take place from the CF Explorer, call sign (5BKK5), from the 27th August at the earliest and last around 7 days.
Cable burial works are due to take place from the 1st October, from the vessel Living Stone, call sign (PBXN) and last around 6 weeks.

 

The crew transfer vessel; MCS Boreas has left site on the 15th of September 2023. The Seazip 9 (call sign: PGYL) left the
NnG site on the 3rd of October 2023 due to a breakdown and will be replaced by the crew transfer vessel Iceni Defender
(call sign: MAND2) that will be supporting this campaign from the 6th October at the earliest


Contact details for the Pacific Dispatch vessel have been updated in table 2 below. Further details of the vessels involved are provided in tables 3-7 below and vessel contact details will be provided in a subsequent NtM. Details of CTV’s and Walk to Work vessels involved in cable pull in and termination and testing works will also be provided in a subsequent NtM.

 

Area of Operations
Mariners are advised that the Pacific Dispatch, Viking Neptun, CF Explorer and Living Stone vessels will be working within the boundaries of the Neart na Gaoithe Offshore Wind Farm, shown in Figure 1 within the coordinates shown in Table 1 All vessels are requested to remain at least 500 meters away from all the work vessels and static fishing gear is requested to be removed from the exclusion area shown in Figure 1 and Table 1. Vessels over 15m are also requested to have AIS turned on and detectable when in the vicinity of construction works. The second cable lay in campaign is due to begin on the 14th of August and last around 4 weeks. Cable pull-in and termination and testing works are due to commence on the 20th August and continue throughout 2023. Cable burial is due to commence on the 1st October and is anticipated to last around 6 weeks. It is anticipated that all PLGR and cable lay in activities will be completed by end of December 2023, weather dependant.
 

Schedule
The inter-array cable PLGR commencedon the 10th August 2023 and was completed on the 14th August. The second cable lay in campaign is due to begin on the 25th of August and expected to last around 4 weeks. Cable pull-in and termination and testing works are due to commence on the 27th August and continue throughout 2023. Cable burial is due to commence on the 1st October and is anticipated to last around 6 weeks. It is anticipated that all PLGR and cable lay in activities will be completed by end of December 2023, weather dependant.


Weather permitting, constructions work will be carried out on a continuous basis; 24-hour working, seven days a week
 

For updates on the progress of the works, information will be provided in the Weekly Notice of Operations available on the NnG project website: https://nngoffshorewind.com/downloads/
 

Vessel Associated with the Activity

Vessel Name Vessel Role Call Sign Maritime Mobile Service Identity On board Contact
Iceni Defender Crew Transfer Vessel MAND2 232005975

Captain Phone: tbc
VSAT Phone: tbc

Email: tbc

Viking Neptune Cable Lay Out Vessel LAYH7 258789000

Mobile Captain

Captain.VikingNeptun@deme-group.com / Bridge.VikingNeptun@deme-group.com

+47 9746 9156

CF Explorer Cable pull-in, termination & testing 5BKK5 209816000 TBC
Living Stone Cable Burial Vessel PBXN 244010952 TBC
Seagull Guard Vessel MVBO2  

Vessel Master

seagullbf74@gmail.com

+44 (0)1261 8788040 +44(0) 7895 919100

Tranquility S Guard Vessel MJUH9  

David Spouse

spousefishing@gmail.com

01890 530 168

 


 

See detailed map on our bulletin website
Show More

Floating LiDAR and Metocean Survey Deployment - MachairWind Offshore Wind Farm



A floating LiDAR buoy, surface metocean equipment buoys and seabed landers have been deployed at two sites to assist with the development of MachairWind Offshore Wind Farm. The floating LiDAR buoy and metocean equipment was deployed between 28th April – 29th April 2023 by Fugro from the Port of Burntisland. The Forth Warrior vessel deployed the floating LiDAR and Metocean survey equipment. Mariners are requested to keep a distance of 500 metres from the Site 1 and Site 2 deployment locations.


The floating LiDAR buoy, surface metocean equipment buoys and seabed landers have been deployed at two separate locations. The equipment deployed will gather wind and metocean data which will be used to inform the development of the Project.

 

The Floating LiDAR  buoy , Metocean Midi Buoy and Metocean Wavescan Buoy are all surface buoys, tethered to the sea bed with single mooring lines. The Seabed Lander is a frame anchored on the seabed, approximately 1.7 m diameter and 0.6 m high. 

 

The Floating LiDAR buoy, Metocean Midi Buoy and Metocean Wavescan Buoy have light marking characteristics comprising FI (5) Y 20s with a nominal range of 5 nautical miles.

 

Surface equipment at Site 1 and Site 2 are transmitting their locations via AIS.

 

Equipment details and mooring designs of the floating LiDAR buoy, metocean buoys and seabed lander are provided in this notice to mariners.

See detailed map on our bulletin website
Show More

Deployment of Two LiDAR Buoys at NOAH Met Mast



Partrac have deployed two Floating LiDAR FLS200 buoys within the Blyth Met Mast consent area under Marine Licence L/2020/00313/1. Please maintain a 500m exclusion around each buoy. Deployment was carried out between 12th – 14th August 2023. Recovery is expected mid-November – early December 2023, weather permitting.


Show More

Cable exposures - BritNed HVDC Interconnector



A recent survey has detected a section of cable with intermittent exposures and possible free spans in the UK sector of the BritNed Interconnector. Start point: Lat:51°41.543'N, Long: 001°56.407'E. End point: Lat: 51°41.777'N, Long: 001°57.030'E. Fishing vessels are advised to keep clear of this location. A guard vessel is stationed at this location.


A recent survey has detected an area where the cable is intermittently exposed with some free spans in evidence. These exposures run between the following coordinates:

 

Start point: Lat:51°41.543'N, Long: 001°56.407'E. End point: Lat: 51°41.777'N, Long: 001°57.030'E.

 

A remedial plan is being formulated, in the meantime a guard vessel is stationed at the location.

See detailed map on our bulletin website
Show More

Exposed Cable - Shefa-2 (Segment 7)



Shefa-2 Segment 7 cable breaks occurred 14th October 2022 and 11th May 2023. Due to rocky seabed features Post Repair Inspection and Burial (PRIB) works are not possible and await other cable protection measures. Hence, a section of 2600 m cable is exposed to seabed and poses a high risk to fishing activity. Please pay attention to this section of wet stored cable which is sensitive to any external impacts and constitutes a snagging risk for fishing, anchoring or other seabed equipment.


Show More

Exposed Cable - Shefa-2 (Segment 7)



Shefa-2 Segment 7 cable break has been repaired and the Post Repair Inspection and Burial (PRIB) operation has been completed. Hence, minor sections of wet stored cable is sensitive to any external impacts and constitutes a snagging risk for anchoring, fishing gear or other equipment with seabed intervention.


Show More

Temporary Marker Buoy - Dogger Bank B Export Cable Burial Operations



Rock placement works are currently ongoing for the DBB export cable corridor (please see NtM LF600013-ESI-DOG-NOT-0006). Rock placement is required at KP1.557 to KP1.606 (approx. 49m in length), this will reduce the water depth at that location by up to 20%. A temporary marker buoy will remain in position to the north of the rock berm to mark the area until navigational charting has been updated to reflect the as-built rock berm.


The marker buoy vessel, Bright Blue, will transit to the work site and deploy the temporary marker buoy at the location set out in Table 1. The total duration of this activity will be one working day. Figure 2 below shows the type of marker buoy that will be installed.

 

It is requested that all vessels give Bright Blue a wide berth and pass at reduced speed when the vessel is engaged in deployment activities.

 

All vessels will monitor VHF CH16 and VHF DSC Ch70 continuously throughout.

The marker buoy vessel, Bright Blue, will transit to the work site and deploy the temporary marker buoy at the location set out in Table 1. The total duration of this activity will be one working day. Figure 2 below shows the type of marker buoy that will be installed.

 

It is requested that all vessels give Bright Blue a wide berth and pass at reduced speed when the vessel is engaged in deployment activities.

 

All vessels will monitor VHF CH16 and VHF DSC Ch70 continuously throughout.

See detailed map on our bulletin website
Show More

Asset Preservation Campaign - Dogger Bank A



The Offshore Supply Vessel, VOS Start, will carry out Asset Preservation operations within Dogger Bank A construction site. The works will be performed in a single campaign, commencing on the 6th of November 2022 and continuing until approximately 30th December 2023. The works will be continuous, 24 hours a day. The operations will include visual inspections and maintenance at installed wind turbine foundation locations.


During operations, the VOS Start will be restricted in its ability to manoeuvre as defined under COLREGs (International Regulations for Preventing Collisions at Sea 1972) and will display the appropriate day shapes and lights. The vessel will also transmit an Automatic Identification System (AIS) message. It is requested that all vessels maintain a minimum of 500m separation distance from the Offshore Supply Vessel and pass at reduced speed. Fishing gear or other equipment with seabed intervention should not be deployed when approaching the working area.

See detailed map on our bulletin website
Show More

Installation of Monopile foundations - Moray West offshore wind farm



This notice to mariners is to inform that Moray Offshore Windfarm (West) Limited (Moray West) will be commencing Monopile, Transition Piece and Offshore Substation installation works at the Moray West Offshore Wind Farm


(Windfarm Marine Licence MS-00009774) installation from and no earlier than 1 October 2023. The first work scope, which will be undertaken, is the installation of Monopiles from the 1 October 2023.

 

Please be aware that, during the Monopile installation works, the Bokalift 2, by virtue of its mode of operation the vessel, will be Restricted in its Ability to Manoeuvre (RAM). Masters of vessels are requested to maintain their vessels and gears at a minimum safe passing distance from the vessel of 500 meters when it is undertaking work and showing the appropriate shapes and lights in accordance with COLREGs Rule 27 (International Regulations for Preventing Collisions at Sea 1972, Rule 3).

 

The scope of work includes the installation of Monopiles and Transition Pieces at 62 foundation locations, and the installation of two Offshore Substations. The installation of Monopiles and Topsides will be carried out with dynamically positioned installation vessels.

The installation of the Transition Pieces will be carried out from a jack-up vessel. A separate Notice to Mariners will be issued ahead of the start of Offshore Substation installation and ahead of the Transition Piece installation works.  

See detailed map on our bulletin website
Show More

Wind Turbine Installation - Neart na Gaoithe Offshore Wind Farm Limited



Mariners are advised that Neart na Gaoithe Offshore Wind Farm Limited (NnGOWL) has commenced the installation of offshore wind turbines within the Neart Na Gaoithe (NnG) Wind Farm Area. The work began on the 15th of July 2023 and is presently ongoing.


Wind turbines will be installed onto pre-installed jackets in the NnG Wind Farm Area. The turbines will be brought to site and installed from the Port of Dundee by the Blue Tern vessel (call sign 9HA5208) and WTG commissioning will be carried out using the HST Swansea call sign (MNGM8). The Farra Ciara call sign (MKPT9) crew transfer vessel (CTV) will be supporting the turbine installation campaigns. The Channel Chieftain VI CTV (call sign 9HB8741) will be replaced by the Green Storm (call sign: 2EXU3) from the 28th of August 2023, at the earliest. The Green Storm will be carrying out refuelling works for the WTG temporary generators.


Additional vessel information and contact details will be updated in subsequent notices.

 

Mariners are advised that the aforementioned vessels will be working within the NnG Wind Farm Area

 

Vessels over 15m are also requested to have AIS turned on and detectable when in the vicinity of construction
works
 

Schedule

The turbine installation work commenced from 15th of July 2023and is currently ongoing. It is anticipated that the
installation works will continue throughout 2023.
Weather permitting, construction works will be carried out on a continuous basis, 24-hours per day, seven days a
week.

 

For updates on the progress of the works, information will be provided in the Weekly Notice of Operations available
on the NnG project website: https://nng
 

Vessel Name Vessel Type Vessel Role Call Sign Maritime Mobile Service Identity IMO On Board Contact Onshore Representative
Blue Tern Jack-up Vessel Turbine Installation 9HA5208
 
215644000 9598737

Blue Tern Master

email: master.blt@fredolsen.com

+47 5100 5334 or +47 5120 6200

TBC
HST Swansea Turbine Commissioning Turbine Commissioning MNGM8 232046426 9958951 TBC TBC
Farra Ciara CTV CTV VRUG4 232039877 9944041 TBC TBC
Green Storm CTV CTV 2EXU3 235089035 9638240

Vessel Master

cc6@carlinboatcharters.com

+44 (0) 7947 885 809

Rachel Glen

rg@mreltd.co.uk

+44 (0) 7597 210 104

Seagull Guard Vessel   MVBO2    

Vessel Master

seagullbf74@gmail.com

+44 (0)1261 878040 + 44(0)7895 919100

 
Tranquillity S Guard Vessel   MJUH9    

Vessel Master

spousekeil@yahoo.com

+4 (0) 1346 454758

 

 

See detailed map on our bulletin website
Show More

MetOcean Buoy Installation - East of Bell Rock (North Sea)



A floating LiDAR buoy and a Waverider Buoy for Metocean data gathering have been installed approximately 4.6 NM east of Bell Rock (North Sea).


Details of buoys, lights and other navigational aids:

 

Description             

North Sea. Bell Rock LiDAR.

Dimensions                 

Diameter 5.0 metres. Height above waterline 3.5 metres              

Character

Fl (5) Y 20s       

Range

4 miles

Colour/Shape

Yellow

Topmark

Yellow X

AIS AtoN MMSI

992351385

AIS AtoN Description

Flidar Buoy Oldbaum

 

 

Description             

North Sea. Bell Rock Waverider Buoy

Dimensions                 

Diameter 0.9 metres. Height above waterline 0.4 metres           

Character

Fl (5) Y 20s

Range

2 miles

Colour/Shape

Yellow/ spherical

Topmark

none

 

 

Instructions to Vessels:

Mariners are requested to keep a wide berth

 

See detailed map on our bulletin website
Show More

Marine Hazard and Archaeological Exclusion Zone - Dogger Bank C Export Cable



A new marine hazard has been identified during UXO identification and investigation operations in the Dogger Bank C export cable corridor.


The marine hazard is located on the seabed in the near vicinity of the intended route of the DBC export cable and is a group of metallic objects associated with military (probably WW2) activity in nature.

 

A 50 metre Archaeological Exclusion Zone (AEZ) has been implemented under the terms of the Written Scheme of Investigation (WSI) produced and agreed with Historic England as per Licence condition in accordance with 16(g) of dML 1 and Condition 13(g) of dML 3.

 

Fishing vessels and other vessels engaged in the deploying of sub-surface and bottom interacting gear should avoid the area.

See detailed map on our bulletin website
Show More

Surface Laid Cable - The Whitley Bay Stub Route (2)



The installation of the Havhingsten fibre optic telecommunication Whitley Bay Stub Route has been completed. Due to challenging soil conditions and rocky seabed, there are sections of surface laid cable and areas with shallow burial. No further operations to bury this section of cable are planned due to the presence of rock. The cable is protected by the armoured cable type and from the BMH up to kilometre point (KP) 0.474 the cable is additionally protected by Articulated Pipe.


Please be advised that installation of the Havhingsten fibre optic telecommunication Whitley Bay Stub Route has been completed.

 

The supplier of the Havhingsten cable is Alcatel Submarine Networks (ASN). Intertek are the environmental and permitting consultants.

 

The Whitley Bay Stub Route has been installed between the Beach Man Hole (BMH) and the territorial sea limit but it will not yet be connected to the telecommunication network. This cable is to provide infrastructure for the network to expand relatively easily when demand is required within the next 10 - 15 years.

 

Due to challenging soil conditions and rocky seabed, there are sections of surface laid cable and areas with shallow burial (less than 0.20m burial depth), coordinates can be found below. No further operations to bury these sections of cable are planned due to the challenging soil conditions. The cable is protected by the armoured cable type and from the BMH up to kilometre point (KP) 0.474 the cable is additionally protected by Articulated Pipe.

 

Coordinates for the surface laid cable and shallow burial areas are provided in the attached Notice to Mariners.

 

Post-Lay Inspection & Burial (PLIB) by jetting for the section of surface laid cable close to the territorial sea limit was completed on the 1 November 2022.

See detailed map on our bulletin website
Show More

Nearshore Works Temporary Marker Buoy - Dogger Bank C



The nearshore works to prepare for installation of the Dogger Bank C export cable have now been completed. The temporary marker buoy will remain in position in the vicinity of the Horizontal Directional Drill (HDD) North and South exit points as shown in the graphic inlcuded with this notice with a chart of the general area where the temporary marker buoy is located. The characteristics of the temporary marker buoy are included in this notice.


Show More

WTG Installation Campaign - Dogger Bank A



The Jack-up WTG Installation Vessel, Voltaire, will install wind turbine generators (WTG) within the Dogger Bank A construction area.


The works will commence on the 05th of July 2023, continuing until approximately Q2 2024.  The works will be continuous, 24 hours a day.  A chart of the DBA construction area boundary coordinates and a table of WTG location coordinates is provided below. A running list of the completed WTG installations and the next locations to be installed is presented in the Weekly Notice of Operations.

 

During operations, the Voltaire will be restricted in its ability to manoeuvre as defined under COLREGs (International Regulations for Preventing Collisions at Sea 1972) and will display the appropriate day shapes and lights. The vessel will also transmit an Automatic Identification System (AIS) message. 

 

During operations, a Statutory Safety zone of 500m radius will be in place around the Voltaire during the installation of WTGs.  The safety zone will be monitored by a guard vessel. The primary response will be to warn passing traffic of the ongoing works and any active safety zones, and to alert any vessels where an infringement may occur or has occurred. 

See detailed map on our bulletin website
Show More

Potentially exposed cable - Caithness Moray HVDC link



Scottish Hydro Electric Transmission Plc has become aware of two areas of potential cable exposure on the Caithness Moray HVDC link, and request that a 500m safety zone is observed


Scottish Hydro Electric Transmission Plc has become aware of two areas of potential cable exposure on the Caithness Moray HVDC link, and request that a 500m safety zone is observed centred on the co-ordinates below.

 

KP

Longitude (WGS 84)

Latitude (WGS 84)

99.240

-2.8633908494

58.4590588736

105.282

-2.9656976221

58.4615448756

 

Mariners are requested not to anchor or tow equipment inside the 500m safety zone surrounding the potentially exposed cable, as this would pose a risk of both snagging and / or damage to vessels, gear and the Caithness Moray HVDC link.

 

This email serves as notification under condition 35 of licence 04368/18/2

 

See detailed map on our bulletin website
Show More

Marine Mammal Monitoring Passive Acoustic Monitoring Deployment - East Anglia Offshore Windfarm



Seiche limited has deployed 12 Passive Acoustic Monitoring (PAM) Stations on the seabed in the East Anglia Offshore Windfarm Area on the 16th of May 2023. The PAM stations will remain on the seabed till the 31st of October 2027. The PAM stations have 12 m height above the seabed, and their location will not be marked by a surface buoy. All marine traffic is advised to maintain 500 m exclusion zone around these PAM locations for their safety.


East Anglia THREE Offshore Windfarm Marine Mammal Monitoring - Passive Acoustic Monitoring Baseline Deployment

 

Seiche Limited

Passive Acoustic Monitoring at the East Anglia Three Offshore Windfarm

NTM:  PAM-EA3- 003                                                                                   Date of issue: 03 May 2023

 

Dear Owners, Ships Agents, Masters, Pilots and Fishermen,

 

Please, be advised that Seiche Limited will deploy 8 Passive Acoustic Monitoring (PAM) Stations on the seabed in and at locations around the East Anglia THREE Offshore Windfarm Area, starting from the 13th of May 2023. The deployment phase is expected to be completed on the 20th of May 2023.

 

 

 

 

Seiche will utilise the Reykjanes vessel for the deployment.

Reykjanes

Scope: PAM stations deployment

Vessel: Reykjanes

LOA: 40.16 m

Call sign: OVSI2

IMO: 7392311

MMSI: 219329000

Phone: +45 (0) 8213 6973

Mobile: +45 (0) 2614 9844

 

Once deployed, the PAM stations will remain on the seabed until approximately the 31st of October 2027.  The PAM stations have 12 m height above the seabed, and their location will not be marked by a surface buoy.

All marine traffic is advised to maintain 500 m safety zone around the Reykjanes or any other vessel at these locations during deployment or servicing for their safety.

Locations of the PAM stations in WGS-84 coordinates:

East Anglia THREE Offshore Windfarm Marine Mammal Monitoring - Passive Acoustic Monitoring Baseline Deployment

 

Seiche Limited

Passive Acoustic Monitoring at the East Anglia Three Offshore Windfarm

NTM:  PAM-EA3- 004                                                                                   Date of issue: 08 June 2023

 

Dear Owners, Ships Agents, Masters, Pilots and Fishermen,

 

Please, be advised that Seiche Limited has deployed 12 Passive Acoustic Monitoring (PAM) Stations on the seabed in and at locations around the East Anglia THREE Offshore Windfarm Area, as of the 16th of May 2023.

 

 

 

 

The PAM stations will remain on the seabed until approximately the 31st of October 2027.  The PAM stations have 12 m height above the seabed, and their location is not marked by a surface buoy.

All marine traffic is advised to maintain 250 m safety zone around the PAM Stations for their safety.

Unfortunately, a fishing vessel has passed over location EA3_12, and caught the PAM Equipment in their net on the 6th of June. This station will be deployed again on the 12th of July.

Locations of the PAM stations in WGS-84 coordinates:

Date Deployed

Location Number

Latitude

Longitude

 

For general enquiries, please, contact via e-mail:

environmental@seiche.com

https://www.seiche.com/

Tel: +44 (0) 1409 404050

 

 

Fisheries Liaison Officer (FLO):

Name: Jonathan Keer // Freya Sandison

Email: jonathan@brownmay.com // freya@brownmay.com

Telephone: +44 (0) 7850 604851 //

+44 (0) 7857 500609

16 May 23

EA3_01

52°

39.757'

N

002°

50.892'

E

16 May 23

EA3_02

52°

43.944'

N

002°

56.888'

E

16 May 23

EA3_03

52°

43.323'

N

002°

48.350'

E

16 May 23

EA3_04

52°

39.478'

N

002°

43.975'

E

16 May 23

EA3_05

52°

33.833'

N

002°

43.954'

E

16 May 23

EA3_06

52°

29.218'

N

002°

33.556'

E

16 May 23

EA3_07

52°

23.948'

N

002°

27.678'

E

16 May 23

EA3_08

52°

19.731'

N

002°

21.606'

E

16 May 23

EA3_09

52°

37.079'

N

002°

50.340'

E

16 May 23

EA3_10

52°

31.734'

N

002°

49.630'

E

16 May 23

EA3_11

52°

24.449'

N

002°

45.480'

E

16 May 23

EA3_12

52°

17.573'

N

002°

52.304'

E

 

This notification supersedes all previous notifications issued in relation to this activity.

Location Number

Latitude

Longitude

 

For general enquiries, please, contact via e-mail:

environmental@seiche.com

https://www.seiche.com/

Tel: +44 (0) 1409 404050

 

 

Fisheries Liaison Officer (FLO):

Name: Jonathan Keer // Freya Sandison

Email: jonathan@brownmay.com // freya@brownmay.com

Telephone: +44 (0) 7850 604851 //

+44 (0) 7857 500609

 

EA3_01

52°

39.752'

N

002°

50.896'

E

18 Apr 23

EA3_02

52°

43.925'

N

002°

56.873'

E

18 Apr 23

EA3_03

52°

43.319'

N

002°

48.340'

E

18 Apr 23

EA3_04

52°

39.487'

N

002°

43.939'

E

 

EA3_05

52°

33.840'

N

002°

43.950'

E

 

EA3_06

52°

29.220'

N

002°

33.560'

E

 

EA3_07

52°

23.942'

N

002°

27.679'

E

 

EA3_08

52°

19.727'

N

002°

21.599'

E

18 Apr 23

EA3_09

52°

37.073'

N

002°

50.343'

E

 

EA3_10

52°

31.731'

N

002°

49.633'

E

 

EA3_11

52°

24.453'

N

002°

45.476'

E

 

EA3_12

52°

17.568'

N

002°

52.296'

E

 

This notification supersedes all previous notifications issued in relation to this activity.

See detailed map on our bulletin website
Show More

MCRP-MM-DOC-0029 MCRP Research Buoy Deployment - Morlais Demonstration Zone.



Notification of deployment of scientific research buoy in the Morlais Demonstration Zone.


Show More

Floating LiDAR and Metocean Survey - Muir Mhòr Offshore Wind Farm



Metocean instrumentation and a floating LiDAR system (FLS) have been deployed within the boundary of the proposed Muir Mhòr Offshore Wind Farm Project site. All instrumentation was deployed by Green Rebel from the Port of Aberdeen to the site in February 2023 via the vessel BB Ocean (IMO 9196503, MMSI 258825000). MARINE USERS are requested to maintain a safe clearance distance of 500m from all assets. May 2023: Northern Guard Buoy no longer present, replacement process is ongoing.


All instrumentation is deployed at a single deployment location within the project site. The purpose of the instrumentation is to gather Metocean and wind data to inform the proposed Muir Mhor Offshore Wind Farm Project.

 

The FLS mooring comprises of a surface visible buoy moored to the seabed via a two-point mooring system constructed using a combination of rope and chain.  Two guard buoys are located at approximately 30m from the main FLS buoy in a North/South orientation, with the mooring spread covering an approximate 315m radius. There is also a seabed frame for current measurements contained within the overall deployment footprint, approximately 30m East of the main FLS buoy. Note: there are 2x orange polyform marker buoys located above the northern anchor position (detailed below) which will be removed during the first planned maintenance visit.

 

The FLS light characteristics are Fl (5) Y 20s with 5nm range. The guard buoys’ light characteristics are FI Y 5s with 3nm range and include a yellow St. Andrew’s Cross topmark. The FLS is designated as “Muir Mhor Floating Lidar” on AIS, with MMSI number 992351400.

 

Details of the surface visible buoy, guard buoys, seabed frame and mooring arrangement are provided in the attachments.

 

MARINE USERS are requested to maintain a safe clearance distance of 500m from all assets.

See detailed map on our bulletin website
Show More

Dogger Bank A Boundary Buoy Installation - as installed locations



The Trinity House Buoy Installation Vessel, Galatea, has installed the Dogger Bank A boundary Demarcation Buoys in the Southern North Sea.


The 17 construction boundary demarcation buoys will remain in location until the windfarm construction activities have been completed and handed over to the Operations and Maintenance teams.

 

Once the permanent Aids to Navigation (AtoN) have been installed on the WTGs, Trinity House will approve the permanent AtoN and the boundary buoys will be removed.

 

If anyone finds a buoy that is off station or encounters a buoy location where it is not functioning or is missing, they should report this to the Dogger Bank Duty Marine Coordinator as soon as possible.

See detailed map on our bulletin website
Show More

Metocean buoy - Broadshore Offshore Wind Farm Site Investigation



Eolos has deployed two (2) Floating LiDAR Devices offshore Scotland for the acquisition of Wind and Metocean Data for a minimum period of 12 months.


Eolos has deployed two (2) Floating LiDAR Devices offshore Scotland for the acquisition of Wind and Metocean Data for a minimum period of 12 months.

 

The units deployed are:

  • FLS200 E25 (deployed 09 Apr 2023); and
  • FLS200 E26 (deployed 08 Apr 2023)

 

Metocean buoy

Illustrative figures showing the buoy dimensions and general arrangement are provided in the attached NtM. 

 

Once in the water the top of the tallest mast is around 4 meters above the sea level.

 

The buoy is fitted with the following navigational safety features:

  • Buoy painted yellow in colour;
  • Yellow St Andrews Cross;
  • Radar reflector;
  • AIS AtoN (with MMSI 992351405, corresponding to Broadshore FLIDAR E26); and
  • Marine lantern (with flash character Fl (5) Y 20s - 5 yellow flashes every 20 seconds) with a range of 5 nautical miles.

 

Mooring design

 

The buoy drifting radius is approximately 240 m from its deployment position. All material will be removed from the seabed after the measurement campaign is complete. The mooring layout design is provided on the final page of this document. The mooring layout design is provided as the final page of the attached NtM.

 

 

See detailed map on our bulletin website
Show More

Metocean buoy - Bellrock Offshore Wind Farm Site Investigation



Eolos has deployed two (2) Floating LiDAR Devices offshore Scotland for the acquisition of Wind and Metocean Data for a minimum period of 12 months.


Eolos has deployed two (2) Floating LiDAR Devices offshore Scotland for the acquisition of Wind and Metocean Data for a minimum period of 12 months.

The units deployed are:

  • FLS200 E25 (deployed 09 Apr 2023); and
  • FLS200 E26 (deployed 08 Apr 2023).

 

Deployment coordinates and chart are provided in the attached NtM. 

 

Metocean buoy

Illustrative figures showing the buoy dimensions and general arrangement are provided in the attached NtM. 

 

Once in the water the top of the tallest mast is around 4 meters above the sea level.

 

The buoy is fitted with the following navigational safety features:

  • Buoy painted yellow in colour;
  • Yellow St Andrews Cross;
  • Radar reflector;
  • AIS AtoN (with MMSI 992351404, corresponding to Bellrock FLIDAR E25); and
  • Marine lantern (with flash character Fl (5) Y 20s - 5 yellow flashes every 20 seconds) with a range of 5 nautical miles.

 

Mooring design

 

The buoy drifting radius is approximately 165 m from its deployment position. All material will be removed from the seabed after the measurement campaign is complete. The mooring layout design is provided on the final page of this document. The mooring layout design is provided as the final page of the attached NtM.

 

 

See detailed map on our bulletin website
Show More

Dogger Bank B Boundary Installation Campaign - as installed locations



The Trinity House Buoy Installation Vessels Patricia and Galatea, have installed the Dogger Bank B boundary demarcation buoys in the Southern North Sea.


The 20 construction boundary demarcation buoys will remain in location until the windfarm construction activities have been completed and handed over to the Operations and Maintenance teams.

 

Once the permanent Aids to Navigation (AtoN) have been installed on the WTGs, Trinity House will approve the permanent AtoN and the boundary buoys will be removed.

 

If anyone finds a buoy that is off station or encounters a buoy location where it is not functioning or is missing, they should report this to the Dogger Bank Duty Marine Coordinator as soon as possible.

See detailed map on our bulletin website
Show More

Disclaimer

TO DOWNLOAD THIS FILE, YOU MUST AGREE TO THE TERMS AND CONDITIONS "TERMS" NOTED AT THE FOOT OF THIS WEBSITE WHICH APPLY TO YOUR USE OF THIS WEBSITE AND TO USE OF THE FILE YOU HAVE CLICKED TO DOWNLOAD. IF YOU DO NOT AGREE TO THE TERMS, YOU WILL NOT BE ABLE TO DOWNLOAD THE FILE AND YOU SHOULD NOT USE THIS WEBSITE. TO CONFIRM YOUR ACCEPTANCE OF THE TERMS AND TO COMMENCE THE DOWNLOAD OF THE FILE, PLEASE CLICK THE "DOWNLOAD" CHECK BOX. IF YOU DO NOT AGREE TO THE TERMS, PLEASE CLICK THE "CANCEL" BUTTON. YOUR ATTENTION IS DRAWN TO CONDITION 3 NOTED BELOW WHICH FORMS PART OF THE TERMS IN RELATION TO OUR LIABILITY TO YOU.

Agree and download Cancel
The website stores some data in your browser. We do not store any personal information. By clicking 'OK', you accept this. See our privacy policy. OK